Coalville Regeneration Framework - 2025 Update

Agreed Scrutiny 2 papers

Community Scrutiny Committee agreed this item on Thursday 11 September 2025. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

It was agreed that in future project reports, officers would provide a tabulated financial summary and timelines for all projects. Members discussed the use of the New Market and enquired about the data available to review. Officers confirmed that there was some data, however an external organisation was currently compiling a more detailed data set which would be available in the coming months. It was suggested that this be something for the committee to review. Members went on to consider the current practice with the use and storage of trailers and stalls, and the issues this could cause with possible event providers. The Strategic Director of Place suggested that this discussion continue with the Scrutiny Work Programming Group so that an item could be scoped, if appropriate, and placed on the work programme for a future meeting. Members spoke positively about the events held at both Snibston and Coalville, including the positive impact to the town of the mother and child statue. In relation to the Hermitage Recreation Ground, Members raised concerns regarding the use of electric scooters speeding around the lake which was spoiling the area for people walking. It was acknowledged that the police were aware that it was an ongoing problem. A discussion was had on the options available to prevent this from occurring and it was suggested that it be a possible topic for the Scrutiny Work Programming Group to consider. RESOLVED THAT: The topics in relation to the New Market and use of electric scooters at Hermitage Recreation Ground be considered by the Scrutiny Work Programming Group to scope for possible future committee items.
Word for word from the decision North West Leicestershire published for this meeting. Source: minutes-1.nwleics.gov.uk

Follow this further

Built from North West Leicestershire's papers

What the report saysPro

Report to Community Scrutiny Committee

NORTH WEST LEICESTERSHIRE DISTRICT COUNCIL

COMMUNITY SCRUTINY COMMITTEE – THURSDAY, 11 SEPTEMBER 2025

Title of Report COALVILLE REGENERATION FRAMEWORK - 2025 UPDATE

Presented by Councillor Richard Blunt Leader of the Council and Coalville Regeneration Portfolio Holder

Paul Wheatley Head of Regeneration and Property Services

Background Papers Coalville Regeneration Framework - 2023 Public Report: Yes Cabinet: Tuesday 10 January, 2023

Financial Implications The adoption of the updated Regeneration Framework itself does not have any direct financial implications for the Council. However, the implementation of the Framework may require financial resources from the Council. Where these resources are not included in the approved capital programme or revenue budget already, they will require specific approval in line with the Constitution and will be subject to resources being available.

Signed off by the Section 151 Officer: Yes

Legal Implications Adoption of the updated Regeneration Framework does not have any direct legal implications for the Council. However, legal advice will be sought on individual projects.

Signed off by the Monitoring Officer: Yes

Staffing and Corporate The Regeneration Framework has been produced and will be Implications promoted using existing staff resource. Signed off by the Head of Paid Service: Yes

Purpose of Report For Community Scrutiny Committee to consider the Coalville Regeneration Framework 2025 update ahead of September Cabinet.

Recommendations THAT COMMUNITY SCRUTINY COMMITTEE REVIEWS THE COALVILLE REGENERATION FRAMEWORK UPDATE AND PROVIDES FEEDBACK FOR CONSIDERATION BY CABINET AT ITS MEETING ON 23 SEPTEMBER 2025. 1.0 BACKGROUND

1.1In April 2022, Community Scrutiny Committee reviewed the first edition of the Coalville Regeneration Framework.

1.2Following further development work and reflecting on Scrutiny Committee feedback, the final version of the Coalville Regeneration Framework was presented to Cabinet in April 2023, agreed and subsequently published.

2.0COALVILLE REGENERATION FRAMEWORK

2.1Since the adoption of the Coalville Regeneration Framework the Council has made significant progress on its Regeneration plans for Coalville.

2.2Some of the projects that the Council has delivered include:

- The new high quality public amenity in Marlborough Square.

- Coalville’s Mother and Child Statue has been beautifully restored and relocated to a prominent place at the entrance to the Belvoir Shopping Centre and the entrance to the town.

- Mantle Lane gateway to the town has been enhanced by the redecoration and lighting of the historic railway bridge.

- The former Mitchell and Grieves factory site has been redeveloped into a new residential neighbourhood.

- The Belvoir Shopping centre has seen private sector led improvements to the public space with new furniture, greenery, shop frontage improvements, pedestrian access and a new public square.

- The creation of the new Council Customer Service Centre, putting the Council at the heart of the town and improving access.

- The sympathetic internal restoration of Stenson House, including the preservation and reinstating of original features.

- Improvements to Hermitage Recreation Ground providing new equipment to support health and wellbeing, alongside new footpaths, landscaping and planting of a new eco park.

2.3The Council continues to make progress on ongoing projects within the Framework such as the regeneration and renewal of the Marlborough Centre building, Stenson Square Gardens and the restoration of the former Memorial Square toilets into modern workspace. 3.0 2025 FRAMEWORK UPDATE

3.1The Council has prepared an updated Coalville Regeneration Framework, attached as appendix 1. This update builds from the original Framework and showcases those regeneration projects which have been successfully completed and continues to highlight those ongoing regeneration priority projects in Coalville Town Centre.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Coalville Regeneration Framework 2025 UpdateAppendix 1 1.7 MB Download
PDF
Coalville Regeneration Framework: 2025 UpdateMinutes 242 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 22 attended
DT
Councillor Dr Terri EynonChair, present
AB
Councillor Anthony BarkerDeputy Chair, present
MB
Councillor Mike BallCommittee Member, apologies
DB
Councillor Dave BigbyCommittee Member, apologies, sent representative
MF
Councillor Marie FrenchCommittee Member, present
JG
Councillor John GearySubstitute, present as substitute
KH
Councillor Kenny HornCommittee Member, apologies
SL
Councillor Simon LambethCommittee Member, present
PL
Councillor Paul LeesCommittee Member, present
EP
Councillor Elizabeth ParleCommittee Member, present
LW
Councillor Lee WindramCommittee Member, present
AW
Councillor Andrew WoodmanPortfolio Holder, in attendance

All 22 on the meeting page

On this subject at North West Leicestershire

Search all
  1. Coalville Regeneration Framework - 2025 UpdateThis decision
  2. Coalville Regeneration Framework - 2025 UpdateApproved
  3. Coalville Regeneration FrameworkApproved
  4. Coalville RegenerationDecided

More from North West Leicestershire Community Scrutiny Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 Recommendations of the Water Management in the Coalville Strategic Growth Area Task and Finish GroupIt was agreed to take the paper to the next meeting of the Scrutiny Work Programming Group for further discussion, wi... Agreed Open
25 Jun 2026 Scrutiny Annual ReportRESOLVED THAT: Authority be delegated to the Scrutiny Committee Chairs to make final amendments to the report followi... Decided Open
23 Apr 2026 Exclusion of Press and PublicRESOLVED THAT: In pursuance of Section 100A(4) of the Local Government Act 1972, the press and public be excluded fro... Decided Open
26 Jun 2025 Foundations Review - Disabled Facilities Grants DeliveryRESOLVED ... view the full minutes text for item 5. Decided Open
26 Jun 2025 Scrutiny Annual ReportRESOLVED THAT: a) The decision of the Corporate Scrutiny Committee to request the Governance Working Group to include... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies