CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
North West Leicestershire District Council
Audit and Governance Committee, Wednesday 12 November 2025 at 6.30pm

Statement of Accounts Update

Decided Finance 1 paper

AI summaryNorth West Leicestershire Audit and Governance Committee endorses Director of Resources' steps to clear delays in publishing accounts, with 2024/25 sign-off targeted by February 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCommittee recognised and backed steps being taken
Money£168,327 audit fee for 2025/26Includes 2.8% contractual indexation increase
What happens nextSign 2024/25 accounts by November 2025Statutory backstop for accounts is February 2026
Who it affectsCouncil's financial reporting and audit positionFour years of accounts published in past year

What was decided

The Committee recognised and endorsed the steps being taken by the Director of Resources to resolve the delays to the publication of accounts.

Why

The Council has cleared a backlog and published the 2023/24 Statement of Accounts at the end of August 2025, putting it on course to meet the November 2025 deadline and the February 2026 statutory backstop for 2024/25 accounts. Report 2.1, 2.2

The Finance Team has made significant progress on the Unit4 financial system, including work on automated bank reconciliation, automated invoice payments, improved reporting and speedier closedown, though bug fixes depend on the implementation partner. Report P9, 3.2, 5.1

What happens next

Sign the 2024/25 Statement of Accounts within the November 2025 deadline, after which future reporting will be limited to standard external audit reports. Report 2.2, 5.2

Procure additional short-term resource to enhance administration of the Unit4 system, and review options for future support as the current three-year contract expires in December 2025. Report 3.4, 5.1

The money

  • £168,327 External audit fee for 2025/26, including 2.8% contractual indexation Report 4.2
  • £163,742 External audit fee for 2024/25 Report P14
  • £186,390 External audit fee for 2023/24 Report P14
  • £18,500 MHCLG funding received in 2023/24 to offset higher audit fees Report 4.7
  • up to £49 million Government grant funding announced 9 April 2025 to clear the local audit backlog, split as up to £18 million for 2024/25 and up to £31 million for 2025/26 Report 4.8

Options considered

  • Chosen: Continue relying on the Unit4 implementation and support partner to fix system bugs. Progress has been made on automated reconciliation, invoice payments and reporting, though pace is constrained because the Council cannot work directly with Unit4 Report P9, 3.2, 5.1
  • Chosen: Procure additional short-term resource to administer the Unit4 system. To further enhance overall administration and accelerate closedown Report 3.4
  • Chosen: Review options to secure reliable future support for the Unit4 system. The current three-year support and maintenance contract expires in December 2025 Report 5.1

Implications

  • Financial: Audit fees have risen, placing strain on already overstretched council budgets and risking resources being diverted from frontline services, as raised by the Director of Resources in response to the 2025/26 fees consultation on 7 October 2025. Report 4.2, 4.4
  • Financial: MHCLG has provided specific funding to offset higher audit fees and up to £49 million of national grant funding to clear the local audit backlog, with the Council's allocation subject to meeting backstop dates. Report 4.7, 4.8, 4.9
  • Risk: Risks include loss of public trust and confidence in the Council's financial management, reduced transparency and accountability, and increased scrutiny and intervention from bodies such as MHCLG, the National Audit Office, the Local Government Association and Public Sector Audit Appointments. Report P32
  • Legal: The Council missed the backstop date for the 2023/24 Statement of Accounts but is targeting the statutory backstop for 2024/25 accounts by February 2026. Report 2.1

Who and where

  • Council taxpayers and service users Report P32
  • Council creditors, grant providers and regulators Report P32
  • The Council's Finance Team Report 2.2, 3.4
  • The Council's external auditor, appointed through Public Sector Audit Appointments Report 4.1
  • The Unit4 implementation and support partner Report 3.2, 5.1

Timeline

  • 22 February 2024: Council considered report on Government proposals for addressing the audit backlog and the Council's position on its Statement of Accounts Report 1.1
  • 5 November 2024: Council considered further report on audit backlog proposals and Statement of Accounts Report 1.1
  • 5 February 2025: Audit and Governance Committee considered update report Report 1.1
  • 9 April 2025: Government announced up to £49 million of grant funding to cover additional costs of clearing the local audit backlog Report 4.8
  • 23 April 2025: Director of Resources gave a verbal update to the Committee Report 1.1
  • 4 June 2025: Audit and Governance Committee considered a report highlighting challenges with the financial system implemented in April 2023 Report 1.1, 3.1
  • End of August 2025: Council published its Statement of Accounts for 2023/24 Report 2.1
  • 6 August 2025: Audit and Governance Committee requested a regular progress report from the Director of Resources Report 1.1
  • 7 October 2025: Director of Resources responded to the 2025/26 audit fees consultation Report 4.4
  • End of November 2025: Target for finalising the 2024/25 Statement of Accounts Report 2.1
  • December 2025: Current three-year Unit4 support and maintenance contract expires Report 5.1
  • February 2026: Statutory backstop date for the 2024/25 Statement of Accounts Report 2.1

Plain English for the jargon

  • Backstop date: A statutory deadline set by Government for local authorities to publish audited financial statements
  • Statement of Accounts: The Council's annual financial statements setting out its income, spending, assets and liabilities
  • Unit4: The financial system implemented by the Council in April 2023 to manage its accounts and reporting
  • PSAA: Public Sector Audit Appointments, the body responsible for appointing external auditors and setting the scale of audit fees for local government
  • MHCLG: Ministry of Housing, Communities and Local Government, the Government department overseeing local authority funding and policy
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item28

Resolved

RESOLVED THAT: The Committee recognised and endorsed the steps being taken by the Director of Resources to resolve the delays to the publication of accounts.
Word for word from the decision North West Leicestershire published for this meeting. Source: minutes-1.nwleics.gov.uk

Follow this further

Built from North West Leicestershire's papers

What the report saysPro

Report to Audit and Governance Committee

Background

1.1Reports were considered by Council on 22 February 2024 and 5 November 2024, and Audit and Governance Committee on 5 February 2025 and 4 June 2025, which provided details of the Government’s proposals for addressing the audit backlog, as well as outlining the Council’s position in respect of its Statement of Accounts. Additionally, the Director of Resources provided a verbal update to this Committee on 23 April 2025. At the Audit and Governance Committee meeting on 6 August 2025, Members requested that a regular report is provided by the Director of Resources outlining the Council’s progress against meeting its statutory financial reporting requirements.

2.0STATEMENT OF ACCOUNTS PROGRESS

2.1Since the August meeting, the Council has published its Statement of Accounts for 2023/24 at the end of that month, in accordance with its schedule to finalise the 2023/24 and 2024/25 accounts by the end of August 2025 and the end of November 2025, respectively. Whilst the Council missed the backstop date for the Statement of Accounts 2023/24, this approach ensures the Council is on target to meet the statutory backstop for the 2024/25 Statement of Accounts by February 2026. Once achieved, the Council will be able to fulfil its statutory reporting requirements in terms of meeting the backstop dates for the Statement of Accounts 2025/26 and future years.

2.2As of now, the Council remains on course to meet the November 2025 deadline. In the past year, four years' accounts have been published, reflecting the Finance Team’s commitment to restoring the Council’s financial reporting to pre-2020/21 standards.

2.3The Council has again used third party support to the closedown of the Statement of Accounts 2024/25 with key reconciliations.

3.0FINANCIAL SYSTEM

3.1The Audit and Governance Committee's report on 4 June 2025 highlighted challenges with the financial system implemented in April 2023. The Council has been working to address these issues and improve its financial reporting processes.

3.2Over the last 12 months, the Council has had to experience regular bugs in the system, each time having to rely on its implementation partner to fix the issues. However, significant progress has been made which includes:

 Detailed scoping document to support automated bank reconciliation  Significant progress in moving to automated invoice payments  Improved reporting and controls  Transactions and reports to support speedier financial closedown.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Statement of Accounts UpdateMinutes 247 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 19 attended
RS
Councillor Ray SuttonChair, present
PM
Councillor Peter MoultDeputy Chair, present
RB
Councillor Russell BoamCommittee Member, present
DC
Councillor Doug CooperCommittee Member, present
DE
Councillor David EverittCommittee Member, present
RJ
Councillor Russell JohnsonCommittee Member, present
GR
Councillor Guy RogersCommittee Member, present
JS
Councillor Jenny SimmonsCommittee Member, present
NS
Councillor Nigel SmithCommittee Member, present
AW
Councillor Avril WilsonCommittee Member, present
EH
Emma HutchinsonCommittee Member, in attendance
PM
Paul MontgomeryCommittee Member, in attendance

All 19 on the meeting page

On this subject at North West Leicestershire

Search all
  1. Statement of Accounts UpdateThis decision
  2. Statement of Accounts 2023/24 and 2024/25Approved
  3. Statement of Accounts 2023/24Approved
  4. Statement of Accounts 2024/25Approved
  5. Statement of Accounts UpdateAgreed
  6. Statement of Accounts 2023/24 UpdateAgreed

More from North West Leicestershire Audit and Governance Committee

All decisions
MeetingDecisionOutcome
5 Aug 2026 Amendments to the Constitution to Reflect the Town and Country Planning (Discharge of Local Planning Authority Functions) (England) Regulations 2026RESOLVED THAT: Recommendation 2 be removed from the recommendations. It was moved by Councillor P Moult, seconded by ... Noted Open
10 Jun 2026 Outstanding Actions UpdateIt was agreed that the Chief Executive would be invited to the next available meeting so a discussion could take plac... Agreed Open
10 Jun 2026 Member Code of Conduct Annual ReportRESOLVED THAT: The Member Code of Conduct annual report 2025/26 be recommended for submission to Council on 11 June 2... Decided Open
10 Jun 2026 Draft Annual Governance Statement 2025-26RESOLVED THAT: The draft Annual Governance Statement 2025-26 be approved for publication subject to minor amendments ... Approved Open
10 Jun 2026 Audit and Governance Committee Annual ReportRESOLVED THAT: 1) The draft Audit and Governance Committee annual report be noted and comments provided. 2) Authority... Noted Open