North West Leicestershire District Council
Audit and Governance Committee, Wednesday 29 April 2026 at 6.30pm

Internal Audit Strategy

Noted Finance 2 papers

AI summaryNorth West Leicestershire Audit and Governance Committee noted 2025/26 internal audit progress and endorsed carrying outstanding actions, including the external quality assessment and data analytics training, into 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCarry outstanding work into 2026/27, support modernisation
MoneyNot stated
What happens nextDeliver outstanding actions in 2026/27External quality assessment and data analytics capability
Who it affectsInternal Audit ServiceCouncil assurance and governance arrangements

What was decided

The Committee noted the progress made against the Internal Audit Strategy during 2025/26.

The Committee supported continued delivery of outstanding actions into 2026/27, including the external quality assessment and development of data analytics capability. Report P6, P9

The Committee endorsed ongoing improvement activities to enhance the effectiveness and modernisation of the Internal Audit Service. Report P13, P66

Why

The Internal Audit Strategy 2025/26 to 2027/28 sets three critical success factor areas: management support, skilled and competent staff, and continuous improvement. Report P28, P31, P32

The strategy was informed by a SWOT analysis that identified weaknesses such as a gap in data analytics skills, an audit skills gap, and threats including budget constraints and rising demand on the service. Report P58, P59, P60

Several initiatives are partially complete or postponed, with the external quality assessment awaiting further guidance from CIPFA because the service is shared. Report P6, P8

What happens next

Carry out the External Quality Assessment during 2026/27 after further CIPFA guidance is received. Report P6

Complete basic data analytics training for Internal Audit staff, rolled forward into 2026/27. Report P9

Continue using Copilot and analytics tools, incorporating analytics into fieldwork, and enhancing root cause analysis through to March 2028. Report P11, P12, P13

Implications

  • Risk: Less action taken as a result of audit findings could lead to greater risk tolerance, identified as a threat in the SWOT analysis. Report P60
  • Staffing: An audit skills matrix is being developed and PDRs were delayed, leaving training and development needs to be finalised. Report P8
  • Risk: Reactive fraud demand and resource constraints may limit audit coverage, with a risk of non-compliance with GIAS in the UK Public Sector. Report P60
  • Other: Digital transformation may make auditing more difficult and is listed as a threat to the service. Report P60

Who and where

  • Internal Audit team and Audit Manager Report P36, P44
  • Audit and Governance Committee Report P36, P42
  • Corporate Leadership Team Report P36, P42
  • Strategic Director of Resources, acting as S151 officer Report P36, P42
  • External Auditor, Azets, and professional bodies CIPFA and IIA Report P37

Timeline

  • July 2025: GIAS overview to CLT and annual report to CLT completed Report P3, P4
  • September 2025: Annual report on Internal Audit resource levels to Audit and Governance Committee completed Report P7
  • October 2025: External Quality Assessment postponed, awaiting CIPFA guidance Report P6
  • March 2026: Training to Audit and Governance Committee and data analytics training due Report P4, P9
  • 2026/27: External Quality Assessment to be carried out, data analytics training to be delivered Report P6, P9
  • 2026/27: Target for 85% of agreed audit actions to be signed off as implemented Report P75
  • 2027/28: Target for 100% of agreed audit actions to be signed off as implemented Report P75
  • March 2028: Ongoing support for innovation within the Internal Audit Service Report P13

Plain English for the jargon

  • GIAS: Global Internal Audit Standards, as applied in the UK Public Sector
  • EQA: External Quality Assessment of the Internal Audit Service
  • CSF: Critical Success Factor, an element essential to the service's purpose
  • S151 officer: The council officer with statutory duties for financial management, here the Strategic Director of Resources
  • CLT: Corporate Leadership Team
  • CIPFA: The Chartered Institute of Public Finance and Accountancy
  • IIA: Institute of Internal Auditors
  • PDR: Personal Development Review
  • SWOT: Strengths, Weaknesses, Opportunities and Threats analysis
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item73

Resolved

RESOLVED THAT: 1) The progress made against the during 2025/25 was noted. 2) The Committee supported the continued delivery of outstanding actions into the 2026/27, including the external quality assessment and the development of data analytics capability. 3) The Committee endorsed the ongoing improvement activities designed to enhance the effectiveness and modernisation of the Internal Audit Service.
Word for word from the decision North West Leicestershire published for this meeting. Source: minutes-1.nwleics.gov.uk

Follow this further

Built from North West Leicestershire's papers

What the report saysPro

Report to Audit and Governance Committee

Update on Initiatives Identified in the Internal Audit Strategy 2025/26 – 2027/28 Appendix A

Critical Success Factor Area: Management Support

Initiative Time Frame Update Internal Audit Manager to provide Corporate Leadership July 2025 Completed Team with an overview of the GIAS in the UK Public Sector, in particular Domain 3 and the underpinning documentation for 2025/26 (i.e. Charter / Mandate / Strategy).

Internal Audit Manager to provide relevant training to the March 2026 Global Internal Audit Standards Training Audit and Governance Committee, as identified in the skills carried out and knowledge questionnaires. Internal Audit Manager to present annual Internal Audit July 2025 Completed Report and Opinion to the Corporate Leadership Team in advance of reporting to the Audit Committee.

Develop Internal Audit intranet page July 2025 Awaiting new intranet

External Quality Assessment against the requirements of October 2025 Postponed while awaiting further guidance the GIAS in the UK Public Sector to include senior from CIPFA due to being a shared service. management and Audit Committee members. This postponement was agreed with the S151 officer and Audit and Governance Committee members were advised and in agreement. The EQA will be carried out during 2026/27 Critical Success Factor Area: Resources/ Skilled and Competent Staff

Initiative Time Frame Update Internal Audit manager to report annually to the Audit and September 2025 Completed for 2025/26 as part of the Governance Committee on Internal Audit resource levels quarterly update reports. and any implications.

Internal Audit staff to complete an annual assessment of September 2025 Partially completed. There was a delay in this skills (via Audit Skills Matrix). Internal Audit Manager to due to a new skills matrix being developed assess skills and determine training and development November 2025 and also a delay in PDR’s. needs.

Basic data analytics training for Internal Audit staff March 2026 To be carried forward in to 2026/27

Critical Success Factor Area: Continuous Improvement

Initiative Time Frame Update Invest time in utilising Copilot/ analytics tools where March 2026 In progress and will continue to be utilised. appropriate and alongside sufficient professional oversight Consider data requirements and availability in the audit April 2025 Implemented. planning stage Begin to incorporate analytics into fieldwork and testing. December 2025 In progress and will continue to be utilised.

Enhance root cause analysis March 2026 Implemented

Support innovation within the Internal Audit Service to March 2028 In progress and will continue. continuously improve Appendix 1

INTERNAL AUDIT STRATEGY

2025/26 – 2027/28 Contents

1. Internal Audit Vision ......................................................................................... 5

2. Internal Audit Mission ....................................................................................... 5

3. Strategic Objectives and Critical Success Factors ........................................ 5

4. Supporting Initiatives ....................................................................................... 6

5. Stakeholder Engagement ................................................................................. 6

Appendix A ............................................................................................................... 5

Appendix B ............................................................................................................... 7

Appendix C ............................................................................................................... 8

Appendix D……………………………………….………………………………………..11 1. Internal Audit Vision

To be a trusted advisor and promoter for continuous improvement, helping the Council optimise efficiency, achieve goals and priorities, and stay resilient in the evolving public sector.

2. Internal Audit Mission

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for Internal Audit StrategyMinutes 446 KB DownloadRead as text
PDF
Internal Audit StrategyMinutes 226 KB Download

At this meeting

Whole meeting

Who was there

7 of 14 attended
JS
Councillor Jenny SimmonsChair, present
RS
Councillor Ray SuttonCommittee Member, present
PM
Councillor Peter MoultCommittee Member, present
RB
Councillor Russell BoamCommittee Member, apologies
DC
Councillor Doug CooperCommittee Member, present
DE
Councillor David EverittCommittee Member, present
GR
Councillor Guy RogersCommittee Member, apologies
NS
Councillor Nigel SmithCommittee Member, present
AW
Councillor Avril WilsonCommittee Member, present
EH
Emma HutchinsonCommittee Member, apologies
KB
Kerry BeavisOfficer, in attendance
AC
Anna CrouchOfficer, in attendance

All 14 on the meeting page

On this subject at North West Leicestershire

Search all
  1. Internal Audit StrategyThis decision
  2. Internal Audit Annual PlanNoted
  3. Internal Audit Charter and MandateApproved
  4. Internal Audit Progress ReportAgreed
  5. Internal Audit CharterApproved
  6. Internal Audit Progress Continuation ReportNoted

More from North West Leicestershire Audit and Governance Committee

All decisions
MeetingDecisionOutcome
5 Aug 2026 Amendments to the Constitution to Reflect the Town and Country Planning (Discharge of Local Planning Authority Functions) (England) Regulations 2026RESOLVED THAT: Recommendation 2 be removed from the recommendations. It was moved by Councillor P Moult, seconded by ... Noted Open
10 Jun 2026 Outstanding Actions UpdateIt was agreed that the Chief Executive would be invited to the next available meeting so a discussion could take plac... Agreed Open
10 Jun 2026 Member Code of Conduct Annual ReportRESOLVED THAT: The Member Code of Conduct annual report 2025/26 be recommended for submission to Council on 11 June 2... Decided Open
10 Jun 2026 Draft Annual Governance Statement 2025-26RESOLVED THAT: The draft Annual Governance Statement 2025-26 be approved for publication subject to minor amendments ... Approved Open
10 Jun 2026 Audit and Governance Committee Annual ReportRESOLVED THAT: 1) The draft Audit and Governance Committee annual report be noted and comments provided. 2) Authority... Noted Open