Resolved
RESOLVED to thank KPMG for the annual report;
Audit Committee decided this item on Friday 27 February 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to thank KPMG for the annual report;
KPMG LLP Tel +44 (0) 115 945 4490 Infrastructure, Government & Healthcare Fax +44 (0) 115 935 3504 St Nicholas House DX 728460 Nottingham 47 Park Row [email removed] Nottingham NG1 6FQ Mobile [phone removed] United Kingdom
s
Geoff Walker Acting Director for Strategic Finance Nottingham City Council Our ref SS/RW Loxley House Station Street Nottingham, NG2 3NG
17 February 2015
Dear Geoff,
Certification of claims and returns - annual report 2013/14
The Audit Commission requires its external auditors to prepare an annual report on the claims and returns it certifies for each client. This letter is our annual report for the certification work we have undertaken for 2013/14.
In 2013/14 we carried out certification work on the following claims/returns:
Claim/return Certified value (£) BEN01 – Housing Benefit subsidy claim 149,146,860 CFB06 – Pooling of Housing Capital Receipts 5,731,934 TRA11 3,085,000 Total 157,963,794
Matters arising
BEN01 Housing Benefits Subsidy Claim As in previous years, our certification work in respect of the Housing Benefit subsidy claim identified a number of errors. It was possible to amend the claim for some of these errors and given the scale and complexity of this claim, the amendments were for relatively minor amounts. However, DWP rules require that all issues are reported or amended regardless of size. Where it was not possible to calculate an amendment, these errors were reported in a qualification letter to the DWP. Generally items are included in qualification letters, rather than the claim form being amended, if the effect of the errors found can only be extrapolated from a sample of cases tested.
KPMG LLP, a UK limited liability partnership, is a subsidiary of KPMG Europe LLP and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative, a Swiss Registered in England No OC301540 entity. Registered office: 15 Canada Square, London, E14 5GL ABCD KPMG LLP Certification of claims and returns - annual report 2013/14 17 February 2015
The reasons for the errors leading to qualification of the claim were varied and included: • Incorrect calculation of earnings – extrapolated impact circa £515,000 • Incorrect tax credit values – extrapolated impact circa £90,000 • Incorrect calculation of childcare costs – extrapolated impact cica £50,000 • Non-dependent deductions omitted – extrapolated impact £9,000 The DWP use the information provided in the qualification letter to decide what if any further evidence the Council needs to provide and ultimately what adjustment will be made to grant payments. As in previous years, the Council can also undertake further work and make representations to DWP to reduce the extrapolated impact.
Going forward it is recommended that the Authority reviews the areas in question and ensures that these are communicated to staff and covered in future quality checks.
CFB06 - Pooling of Housing Capital Receipts
Our certification work did not identify any issues or errors with the Pooling of Housing Capital Receipts claim, and we certified this claim unqualified without amendment.
TRA11 – Local Transport Major Projects Grant
This grant is scheme rather than year specific and there was no comparable claim in 2012/13. Our certification work did not identify any issues with the claim, and we certified this claim without amendment or qualification.
Progress against last year’s recommendations
In our 2012/13 Certification Annual Report we raised five recommendations, three of which related to improving the accuracy of the Council’s Housing Benefits claim. Of these three, one related specifically to Council Tax benefit and is no longer covered by the Housing Benefit claim and for the other two we are satisfied from our testing that the Council has improved its arrangements and addressed the recommendations.
One recommendation related to the Pooling of Housing Capital Receipts and we are satisfied from our testing that this issue has been resolved.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
KPMG CERTIFICATION OF CLAIMS AND RETURNS ANNUAL REPORTReport | 77 KB | DownloadRead as text |
Follow Audit Committee at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 31 Jul 2026 | Draft Statement of Accounts 2025/26It was agreed that an analysis would be done and provided ... view the full minutes text for item 21. | Agreed | Open |
| 31 Jul 2026 | Internal Audit Q1 progress updateResolved to note the progress of the 2026/27 Audit plan. | Noted | Open |
| 31 Jul 2026 | Audit Committee Annual Report 25/26Resolved to endorse the Audit Committee Annual Report to Council in September 2026. | Decided | Open |
| 26 Jun 2026 | Appointment of the Vice ChairResolved to appoint Councillor Pavlos Kotsonis as the Vice Chair of the Committee for the 2026/27 municipal year. | Decided | Open |
| 26 Jun 2026 | Future Meeting DatesResolved to meet on the following Fridays at 9:30am: · 31 July 2026 · 25 September 2026 · 27 November 2026 · 29 Janau... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.