RESOLVED to (1) approve expenditure on architectural, structural and surveying fees to enable the preparation of tender documentation for the reinstatement of Units 22-24 Whitemoor Court; (2) authorise the Interim Director Strategic Asset and Property Management to proceed with the project and report back to a subsequent Trust and Charities Committee meeting to seek consent to proceed with the work on the basis of the offered price.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Title of paper: Pre- Construction Fees – Units 22-24 Whitemoor Court, Nuthall Road
Director(s)/ Kevin Shutter – Interim Director Wards affected: Corporate Director(s): Strategic Asset and Property Leen Valley Management Report author(s) and Richard Cox, Senior Estates Surveyor contact details: Email: [email protected]
Other colleagues who Georgina Lewis, Finance Analyst have provided input: Malcolm Townroe, Head of Legal Services Date of consultation with Portfolio Holder(s) 15 July 2015 (if relevant)
Relevant Council Plan Strategic Priority: Cutting unemployment by a quarter Cut crime and anti-social behaviour Ensure more school leavers get a job, training or further education than any other City Your neighbourhood as clean as the City Centre Help keep your energy bills down Good access to public transport Nottingham has a good mix of housing Nottingham is a good place to do business, invest and create jobs Nottingham offers a wide range of leisure activities, parks and sporting events Support early intervention activities Deliver effective, value for money services to our citizens
Summary of issues (including benefits to citizens/service users): Units 22-24 Whitemoor Court were badly damaged following a fire. To enable the units to be reinstated it is necessary to incur costs in obtaining architectural services, a structural conditions survey and ecology/bat surveys prior to obtaining a price for the construction contract. The report seeks approval to this. Once the work has been completed the units will be let to produce a rental income and to provide good quality accommodation for businesses.
Recommendation(s): 1 To approve expenditure on architectural, structural and surveying fees, as set out in the exempt appendix, to enable the preparation of tender documentation for the reinstatement of Units 22-24 Whitemoor Court;
2 To authorise the Interim Director Strategic Asset and Property Management to proceed with the project and report back to a subsequent Trust and Charities Committee meeting to seek consent to proceed with the work on the basis of the offered price 1. REASONS FOR RECOMMENDATIONS
Units 22-24 Whitemoor Court are currently vacant and incapable of occupation due to fire damage. To proceed with their reinstatement it is first necessary to carry out pre- construction architectural, structural and surveying work to enable the tender documentation to be completed and a quote obtained for the work. When the work is carried out the three units, when let, should produce an income of approximately £75,000 per annum
2. BACKGROUND (INCLUDING OUTCOMES OF CONSULTATION)
Bridge Estate owns the freehold of Units 21-29 Whitemoor Court, a terrace of light industrial units located off Nuthall Road. A major fire broke out in Unit 22 and subsequently spread to the two adjoining units. The units were badly damaged and had to be vacated by the occupying tenants. Before a contractor can be appointed to reinstate the units it is necessary to carry out further architectural design, examine the condition of the structural steel work to ascertain what needs to be replaced, survey the roof and carry out some additional studies to include an ecology/wildlife survey. The cost associated with this work is set out in the Exempt Appendix.
3. OTHER OPTIONS CONSIDERED IN MAKING RECOMMENDATIONS
To enable the units to be reinstated and capable of occupation it is necessary to carry out this work. Therefore no other options were considered.
4. FINANCE COMMENTS (INCLUDING IMPLICATIONS AND VALUE FOR MONEY/VAT)
Finance Advice is included in the exempt appendix
5. LEGAL AND PROCUREMENT COMMENTS (INCLUDING RISK MANAGEMENT ISSUES, AND LEGAL, CRIME AND DISORDER ACT AND PROCUREMENT IMPLICATIONS)
The proposals set out in the report raise no significant legal issues and, in the circumstances outlined, are supported.
Malcolm R. Townroe, Solicitor, Head of Legal Services – 23 July 2015
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.