RESOLVED to (1) note the contents of the report; (2) approach the Heritage Officer on the possibility of applying for Heritage Lottery Fund money for the bridge; (3) investigate the installation of a ‘Welcome to Nottingham’ sign on the approach to the bridge; (4) investigate installation of an interpretation panel outlining the history of the bridge; (5) investigate updating the decorative lights to a more modern standard and making them more accessible for repairs; (6) provide figures on actual spend on ... view the full minutes text for item 30.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Title of paper: Structural Maintenance of Trent Bridge (Information Report) Director(s)/ David Bishop, Deputy Chief Wards affected: Bridge Corporate Director(s): Executive/Corporate Director of Development and Growth Report author(s) and Chris Capewell contact details: Ext 65277 [email protected] Other colleagues who have provided input: Date of consultation with Portfolio Holder(s) Not Applicable (if relevant)
Relevant Council Plan Strategic Priority: Cutting unemployment by a quarter Cut crime and anti-social behaviour Ensure more school leavers get a job, training or further education than any other City Your neighbourhood as clean as the City Centre Help keep your energy bills down Good access to public transport Nottingham has a good mix of housing Nottingham is a good place to do business, invest and create jobs Nottingham offers a wide range of leisure activities, parks and sporting events Support early intervention activities Deliver effective, value for money services to our citizens X
Summary of issues (including benefits to citizens/service users): At the meeting of the Trusts and Charities Committee on 11 September 2015, Councillors requested information from Highways regarding the maintenance of Trent Bridge. This report has been prepared in response to that request.
Recommendation(s): 1 That the committee note the contents of this report and provide comment.
1. REASONS FOR REPORT
To give the committee the assurance that the maintenance regime in place will ensure that Trent Bridge will be able to fulfil its primary purpose as a crossing of the River Trent, as well as its preservation as a historic landmark structure.
2. ADVICE
One of the objectives of the Bridge Estate is “to provide for the efficient maintenance and repair of Trent Bridge and the approaches to it”. Consequently at the last meeting of this committee, members requested information on the maintenance of Trent Bridge. This report has been prepared in response to the information requested as detailed in the minutes of that meeting. (i) The process undertaken to assess the structural integrity and planned maintenance of Trent Bridge.
A strength assessment was carried out in 1995 in accordance with Department of Transport standards for the assessment of Highway Bridges. This assessment found that the bridge was satisfactory for 40 / 44 tonne vehicles, with a maximum axle load of 11.5 tonnes. Since this assessment any abnormal loads heavier than this have been routed away from the bridge. As there have been no further changes in maximum permissible vehicle loads since this date it has not been necessary to re-assess the structure. Only if there is a significant change in the condition of the structure, or changes in legislation regarding vehicle weights, would the strength of the structure be re-assessed.
The regime for bridge inspections adopted by Nottingham City Council is in accordance with the Code of Practice for the Management of Highway Structures, (TSO 2005). This is for a general bridge inspection ever two years and a principal bridge inspection every six years. A general bridge inspection is carried out without specialist access equipment; whereas during a principal bridge inspection, the inspector is required to get with arms reach of all parts of the structure. The last principal bridge inspection was carried out in February 2012. At these inspections structural maintenance work required is noted. However, unless the work identified has immediate structural safety implications, it is generally left until the next major maintenance.
It is currently proposed to carry out major maintenance, including re-painting of the bridge, is carried out in 2018.
(ii) Information on the causes of solutions to the erosion of the roadside sandstone.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.