RESOLVED to (1) expect a further report to a future Policy and Strategy Committee; (2) consider the appropriate earmarked reserves in January at the Finance and Resources Committee.
Nottingham Fire and Rescue Authority - Policy and Strategy decided this item on Friday 11 November 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to (1) expect a further report to a future Policy and Strategy Committee; (2) consider the appropriate earmarked reserves in January at the Finance and Resources Committee.
This report provides an update on the progress of the Emergency Services Network (ESN) programme by Nottinghamshire Fire & Rescue Service.
CONTACT OFFICER
Name : Craig Parkin Assistant Chief Fire Officer Tel : (0115) 967 0880
Email : [email protected]
Media Enquiries Therese Easom Contact : (0115) 967 0880 [email protected] 1. BACKGROUND
1.1The Emergency Services Mobile Communications Programme (ESMCP) is intended to provide the next generation communication system for the three emergency services and other public safety users as the contract for Airwave expires by 2020. This system will be called the Emergency Services Network (ESN) and provides integrated critical voice and broadband data services for the emergency services.
1.2The programme has three key objectives it aims to achieve: Better – integrated service, functionality and coverage; Smarter – more flexible and pay only for what is used; Cheaper – address budget pressures and leverage market forces.
1.3The Fire Authority previously received a financial information and sign off pack which provided information about participation in the ESMCP and that the lead government department was committed to provide all reasonable transition funding, this agreement was signed and returned to Department of Communities and Local Government prior to the 25 March 2016 deadline, committing the Fire Authority to ESMCP.
1.4The East Midlands under the current, national programme timescales are due to transition by winter 2017 as one of the first areas nationally. Like all ICT projects, ESN is an extremely complex area of work, both in detail and project structure and these timescales are under frequent review.
1.5East Midlands Fire Services have established a regional programme board with representatives from all Services and ACFO Parkin as the lead officer on behalf of the East Midlands Fire. An Area Manager is seconded from Lincolnshire as the regional Fire programme manager, with a major day-to-day role on behalf of the East Midlands and works closely to the ACFO.
1.6ACFO Parkin attends Regular Fire Customer Group (FCG) meetings; this forum is the sounding board for the Fire sector to feed into the national programme team within the Home Office.
1.7Alongside the ESN work, Nottinghamshire Fire and Rescue Service (NFRS) have already commenced work as part of the previous Authority agreed ICT strategy to demonstrate compliance with the Public Services Network (PSN) as this will better prepare the Service to deliver ESN and a team have been recruited to discharge the highlighted actions for PSN compliance.
1.8PSN compliance will ensure that the Service has a robust ICT infrastructure, with greater levels of security; this will require additions to policies and procedures, but more crucially, a change to working practices for all members of staff to maintain compliance. 2. REPORT
2.1An Information Technology Health Check (ITHC) has already been completed by an external supplier on the Tri-Service Control partner networks; this forms the basis for the remediation work each Service needs to complete prior to connecting to the ESN.
2.2This check has been funded by the Home Office and work is now on-going with Home Office accreditors to see which elements of remediation work may be funded centrally; however, initial indications are that elements are highly likely to fall to individual Services to fund.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Emergency Services Network updateReport | 209 KB | DownloadRead as text |
Follow Nottingham Fire and Rescue Authority - Policy and Strategy at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 May 2026 | Exclusion of the PublicResolved to exclude the public from the meeting during consideration of the remaining items in accordance with Sectio... | Decided | Open |
| 15 Nov 2024 | Service Improvement - Futures 25 Closure ReportResolved to note the contents of the report. | Noted | Open |
| 15 Nov 2024 | Exclusion of the publicResolved to exclude the public from the meeting during consideration of the remaining items in accordance with Sectio... | Decided | Open |
| 26 Apr 2024 | Governance ArrangementsResolved to note (1) The arrangements with regard to the direct employment of the Clerk and Monitoring Officer. (2) T... | Noted | Open |
| 26 Apr 2024 | 10-Year Workforce Diversity PlanningResolved to (1) Endorse a long-term commitment to workforce diversity via a 10-year Diversity Plan. (2) Note the cont... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.