RESOLVED to (1) note the update and performance information in appendices 1 and 2 of the report; (2) note the allocation of funds for 2016/17: Ward Actual budget (including carry over from 2015/16) Schemes approved Schemes committed Scheme de committed Remainining budget Dales £86,344.68 £0 £0 £0 £82,114.68 Mapperley £44,328.05 £0 £0 £0 £44,328.05 St Anns £141,385.36 £129,217.24 £129,217.24 £0 £10,315.75 (3) approve £4700 from the Area Capital Programme for the following scheme: Address Action Reason Cost Beverley Square St Anns Convert the grass verge in the south-west corner to hard standing, along with line markings to allocate the square in terms of parking spaces and pedestrian walkways. A total of 18 spaces can be achieved at a cost. Beverley Square has no defined car parking spaces ... view the full minutes text for item 31.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Report to Area Committee East (A.C.E) Dales, St Ann's & Mapperley
Appendix 1
NCH update report
Time: 1700
Date: October 2016
Presented by: Toni Smithurst
Item Executive Summary / Key Points For information or decision 1 Information RemoUrban Windmill Lane, Sneinton complete apart from a small number of access Capital Programme & major issues. Feedback from customers has been very positive with many finding works they do not need their heating on. A programme to install LED lighting in proeprties with external wall insulation is being collated.
Hemmingway Designs submitted design for Newark Crescent after a site visit. Consultation event to be held for residents with help from Sneinton Alchemy. Event for 2050 residents to be organised. Hemmingway Designs also visited these properties. Possible community growing opportunity for both projects.
Victoria Centre Engineers started onsite week commencing 10 October working in the corridors on each floor taking out old cables and putting in new ones for the intercom upgrade. Work in corridors will continue throughout the project and access to individual flats will be required. This is a six month project.
Passenger lift replacement is due to commence during 2017. A planning meeting is scheduled for the end of October in preparation for this large project to ensure residents are communicated with thoroughly throughout.
As part of the ten year inspection programme the passenger lifts received some maintenance work at the beginning of October.
Highwood House Subject to funding two flats in the complex will be receiving equalities act work to make them more accessible. Corridor walls will be have anti-graffiti paint applied. Passive fans were installed last year in the living areas but residents keep turning them off, new fans are being installed to remove the ability for them to be turned off.
Sample checks of water systems in tenant homes will be undertaken in Independent living schemes across the City to the end of the financial year. This is to confirm that water stored in water tanks and pipework is clean and hygienic.
Stock condition and energy performance surveys continue Citywide targeting homes where we have little or no information, this could be due to previous no access. This information helps plan future works including a programme of maintaining decency continues across the City replacing windows, doors, kitchens and bathrooms where needed.
Grander designs to Courtney Court is part way through. Scooter store facility due to commence at Bullace Court in November.
2 Dales Information
Findern Green parking scheme has been passed to NCC Highways team to design and quote. We have received a preliminary price and design and these have been shared with Elected Members for consideration. We need to carry out consultation with local residents before any decisions are made.
BMK – NCH are currently carrying out external improvements to all 3 tower blocks following the huge success of the external wall and balcony project delivered last winter. We will be complete with the external areas before winter.
Area Regeneration and Tatton Park Garden – we have recently installed a RHS Gold Award Medal Environmental Issues garden into Manvers Court and this will be a very nice addition to the block for residents to enjoy and use the external spaces positively.
Mapperley We are currently costing options to improve the major wall on Dooland Drive as it is significantly damaged and decaying. We are also looking to secure some funding towards the improvements to Kingsthorpe Court within the Dooland Drive area. We recognised that there is a block of 5 houses within this area that look tired in light of the new build project that has been delivered nearby.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Area Committee East (A.C.E) Dales, St Ann's & Mapperley at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
Area Capital Fund 2018/19 ProgrammeRESOLVED to: (1) Approve the new schemes prioritised by Ward Councillors since the last area committee as detailed be...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.