CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Nottingham City Council

EMERGENCY SERVICES NETWORK (ESN) UPDATE

Noted Committee 1 paper

Nottingham Fire and Rescue Authority - Policy and Strategy noted this item on Friday 21 July 2017. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

RESOLVED to note the contents of the report and agree to receive further updates as the project develops, including any costs to the Authority beyond Central Government funding.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Nottingham Fire and Rescue Authority - Policy and Strategy

Purpose of report

To provide an update on the progress of the Emergency Services Network (ESN) programme by Nottinghamshire Fire and Rescue Service.

CONTACT OFFICER

Craig Parkin Name : Assistant Chief Fire Officer Tel : (0115) 967 0880

Email : [email protected]

Media Enquiries Therese Easom Contact : (0115) 967 0880 [email protected] 1. BACKGROUND

1.1The Emergency Services Mobile Communications Programme (ESMCP) is intended to provide the next generation communication system for the three emergency services and other public safety users as the contract for Airwave expires by 2020. This system will be called the Emergency Services Network (ESN) and provides integrated critical voice and broadband data services for the emergency services.

1.2The programme has three key objectives it aims to achieve:

 Better – integrated service, functionality and coverage;  Smarter – more flexible and pay only for what is used;  Cheaper – address budget pressures and leverage market forces.

1.3The Fire Authority previously received (March 2016) a financial information and sign off pack which provided information about participation in the ESMCP and that the lead government department was committed to provide all reasonable transition funding, this agreement was signed and returned to Department of Communities and Local Government prior to the 25 March 2016 deadline, committing the Fire Authority to ESMCP.

1.4An update report was initially presented to the November 2016 Policy and Strategy committee meeting and highlighted that further reports would be provided at subsequent meetings to ensure that the Fire Authority is fully briefed on the ESN work as a critical national project.

1.5East Midlands fire services have an established regional programme board with representatives from all Services and Nottinghamshire Fire and Rescue Service’s Assistant Chief Fire Officer (ACFO) as the lead officer on behalf of East Midlands fire. An Area Manager is seconded from Lincolnshire as the regional fire programme manager, with a major day-to-day role on behalf of the East Midlands and works closely with the ACFO.

1.6The Area Manager Corporate leads on behalf of Nottinghamshire Fire and Rescue Service (NFRS) project structure, co-ordinating key roles across the organisation and works closely with East Midlands colleagues to seek opportunities for mutual support to deliver the ESN.

1.7The ACFO attends regular Fire Customer Group (FCG) meetings; this forum is the sounding board for the fire sector to feed into the national programme team within the Home Office.

1.8Alongside the ESN work, NFRS has already commenced work as part of the previous Authority agreed ICT strategy to demonstrate compliance with the Public Services Network (PSN) as this will better prepare the Service to deliver ESN and a team have been recruited to discharge the highlighted actions for PSN compliance. 1.9 PSN compliance will ensure that the Service has a robust ICT infrastructure, with greater levels of security; this will require additions to policies and procedures, but more crucially, a change to working practices for all members of staff to maintain compliance.

2. REPORT

2.1An Information Technology Health Check (ITHC) was completed by an external supplier on the Tri-Service Control partner networks; this formed the basis for the remediation work each Service needs to complete prior to connecting to the ESN and the Service continues work through all outstanding actions to support transition.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EMERGENCY SERVICES NETWORK (ESN) UPDATEReport 177 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
BG
Councillor Brian GrocockChair, present
AB
Councillor Andrew BrownCommittee Member, apologies, sent representative (personal reasons)
SF
Councillor Sybil FieldingCommittee Member, apologies, sent representative (personal reasons)
MP
Councillor Michael PayneCommittee Member, present
JW
Councillor Jonathan WheelerCommittee Member, present
MW
Councillor Malcolm WoodCommittee Member, present
JB
John BuckleyOfficer, present
MT
Malcolm TownroeOfficer, present
CZ
Catherine Ziane-PryorClerk, present
VH
Councillor Vaughan HopewellSubstitute, present as substitute

On this subject at Nottingham

Search all
  1. EMERGENCY SERVICES NETWORK (ESN) UPDATEThis decision
  2. Emergency services network updateNoted
  3. Emergency services network updateNoted
  4. Emergency services network updateNoted
  5. Emergency services network (esn) updateNoted
  6. Response to pressures on urgent and emergency care services in the post-Christmas periodNoted

More from Nottingham Nottingham Fire and Rescue Authority - Policy and Strategy

All decisions
MeetingDecisionOutcome
1 May 2026 Exclusion of the PublicResolved to exclude the public from the meeting during consideration of the remaining items in accordance with Sectio... Decided Open
15 Nov 2024 Service Improvement - Futures 25 Closure ReportResolved to note the contents of the report. Noted Open
15 Nov 2024 Exclusion of the publicResolved to exclude the public from the meeting during consideration of the remaining items in accordance with Sectio... Decided Open
26 Apr 2024 Governance ArrangementsResolved to note (1) The arrangements with regard to the direct employment of the Clerk and Monitoring Officer. (2) T... Noted Open
26 Apr 2024 10-Year Workforce Diversity PlanningResolved to (1) Endorse a long-term commitment to workforce diversity via a 10-year Diversity Plan. (2) Note the cont... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies