Nottingham and Nottinghamshire Economic Prosperity Committee noted this item on Tuesday 27 November 2018. Below is the council's own wording, with the papers it was decided on.
(1) to note the progress made to date on the delivery of the N2 Town Centre Programme; (2) to approve a further call for town centre projects to maximise the available remaining funding and to meet the outstanding job outputs; (3) to note the forthcoming Future High Street Fund.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Report to Nottingham and Nottinghamshire Economic Prosperity Committee
Reasons for recommendations
1.1This report is largely for information but seeks approval for a further call for projects given remaining resources and a shortfall in expected outputs. The government’s announcement of a new fund potentially offers an opportunity to explore further partnership activity in support of our town centres.
2 BACKGROUND (INCLUDING OUTCOMES OF CONSULTATION)
2.1The “Unlocking Growth in N2 Town Centres” Programme is a formally approved £7.625m initiative, supported by the D2N2 Local Enterprise Partnership’s (LEP) Local Growth Fund (LGF). It is designed to deliver a set of physical / capital improvements within key town and local centres across the N2 EPC area, designed to stimulate economic growth. Each individual project is the subject of a full and independent business case assessment, taking the form of a submission which follows the D2N2 LEP’s published Local Assurance Framework.
2.2Nottinghamshire County Council acts as the accountable body for the programme and facilitates the process of bringing forward projects for consideration and ultimately determines approvals in liaison with the wider N2TC partners and the D2N2 LEP. At its meeting of 23rd October 2017, this Committee noted the background to the Programme and delegated the responsibility to approve individual projects to the County Council’s Chief Officer and Section 151 Officer, subject to the partners’ consideration (via a now established Project Board meeting) with monitoring and overall progress being reported to future meetings of this Committee. The key items to report may be summarised as follows:
Project Progress 2.3 Nottinghamshire County Council has facilitated the approval of the Programme’s overall Business Case and its governance arrangements and supported the applicants with further requirements including the template agreements and expectations regarding project progress.
2.4Genecon, the appointed consultant is working closely with the Council and each of the individual project sponsors (in brackets below) to bring forward the respective initial projects in line with the due process. The partners have held their first Project Board meeting and the latest position may be summarised as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Mrs Kay Cutts MBECommittee Member, present
RJ
Councillor Richard Jackson (Broxtowe)Committee Member, present
DJ
Councillor David J LloydCommittee Member, present
SR
Councillor Simon RobinsonCommittee Member, present
JW
Councillor Jo WhiteCommittee Member, present
JZ
Councillor Jason ZadroznyCommittee Member, present
Hear about the next one first
Follow Nottingham and Nottinghamshire Economic Prosperity Committee at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.