Resolved to note: (1) the progress update, as set out in Appendix 1 to the report; (2) the comments of the newly established Governance Improvement Board on the progress to date and the lessons learnt, as set out in Appendix 3 to the report; (3) the comments of the Audit Committee on 18 December 2020 on the review of the appointment of Councillors as Directors on Boards of Council Owned and Controlled Companies, as set out in Appendix 4 to the report; and (4) that the amended draft Terms of Reference for the Overview and Scrutiny Committee were included for approval in the Amendments to the Constitution report on this meeting agenda.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
1.1In response to the recommendations of the External Auditor in the Report in the Public Interest on Robin Hood Energy (the PIR), Nottingham City Council formally adopted an Action Plan in August 2020, that was subsequently amended in November 2020, setting out a series of actions to address the issues raised by the External Auditor.
1.2A Governance Improvement Programme has been established to deliver the Action Plan. This report provides an update on progress of the programme to date in delivering the actions.
1.3It also captures and sets out the review outcomes and key considerations identified to date, in line with the actions set under Recommendation 10 of the Action Plan.
Recommendations
2.1To note:
a) the progress update;
b) the comments of the newly established Governance Improvement Board on the progress to date and the lessons learned, as set out in Appendix 3;
c) the comments of the Audit Committee on 18 December 2020 on the review of the appointment of councillors as Directors on Boards of Council owned and controlled companies, as set out in Appendix 4; and
d) that amended draft terms of reference for the Overview and Scrutiny Committee are included for approval in the Amendments to the Constitution report on this agenda.
Reasons for recommendations
3.1The Governance Improvement Programme was established to oversee the delivery of the City Council’s Action Plan responding to the PIR concerning the Council’s Governance Arrangements for Robin Hood Energy Ltd, and to review the wider governance issues at Nottingham City Council identified in the report.
3.2In response to Recommendation 10 of the PIR which reads; “In addition to those referred to in recommendations above, the Council should apply the lessons from Robin Hood Energy in a further review of its company governance arrangements, in particular to ensure that risks are appropriately flagged and managed, as well as successfully implementing the more robust monitoring agreed by the Companies Governance Executive Sub-Committee”, the City Council’s Action Plan requires that an overarching report covering the outcomes of the various reviews be produced in December 2020 and brought to Full Council for consideration.
3.3One of the key requirements of the PIR and Action Plan was the establishment of an Improvement Board to oversee delivery and drive progress against the PIR Action Plan, to support improvement in the Council’s wider governance arrangements, and to ensure that a range of voices, including those independent of the Council, contribute to the development of improved governance at Nottingham City Council.
3.4Included at Appendix 3 are the draft minutes of the first meeting of the Nottingham City Council Governance Improvement Board which include the comments, questions and observations of the Board members at the meeting on 9 December 2020.
4 Background (including outcomes of consultation)
4.1The External Auditor published the PIR on Robin Hood Energy in August 2020. The report highlighted a number of areas for improvement, with regard to the Council’s governance arrangements for its companies.
4.2The report also recommended a broader review of the Council’s governance and decision making processes be undertaken.
4.3The findings of the PIR were accepted by the Council and an Action Plan drawn up to address the issues raised. The Action Plan was formally approved by the Council on 30 August 2020. The Action Plan was subsequently amended by Council on 9 November 2020.
4.4The Action Plan has 13 recommendations from the External Auditor and an additional 3 recommendations from the Council, with a clear set of actions. There is a programme of improvement work to deliver the actions in the plan, with a dedicated Project Management Office to lead delivery of the programme. Dedicated workstream leads cover the key areas, and the council owned companies are involved.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Decisions taken under Urgency ProceduresResolved to note that (1) Two decisions have been taken under urgency provisions within the Overview and Scrutiny Pro...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.