Nottinghamshire and City of Nottingham Fire and Rescue Authority Policy and Strategy Committee
COLLABORATION UPDATE Report of the Chief Fire Officer Date: 04 February 2022
Purpose of Report: To present Members with an update on the Service’s Joint Headquarters Programme.
Recommendations: That Members note the contents of this report.
CONTACT OFFICER Candida Brudenell Name: Assistant Chief Fire Officer Tel: 0115 967 0880
Email: [email protected]
Media Enquiries Corporate Communications Contact: [email protected] 1. BACKGROUND
1.1The Joint Headquarters Programme Board meets on a regular basis to oversee each of the projects identified as being required to deliver a successful joint Police and Fire Headquarters in 2021/22.
1.2The Board regularly reports on progress to the Collaboration Delivery Board and Strategic Collaboration Board.
2. REPORT
JOINT HEADQUARTERS (JHQ) PROGRAMME
2.1Issues relating to supply-chain delays, and subsequent impacts, have led to the delay of ‘practical completion’ on the Joint Headquarters new build project. This saw a delay of completion from 20 December 2021, as planned, to 20 January 2022.
2.2On 10 January 2022, the Fire Investigation team co-located in the refurbished accommodation now shared with the Crime Scene Investigation team, vacating their previous accommodation at Mansfield Fire Station.
2.3On 17 January 2022, the Nottinghamshire Fire and Rescue Service (NFRS) People and Organisational Development (POD) team moved from Bestwood Lodge to Sherwood Lodge. They have occupied the ground floor of the new building, along with colleagues from the Police Human Resources team.
2.4The relocation of Pulp Friction from Bestwood Lodge to Sherwood Lodge will take place at the beginning of February. This will see them take up residence in the newly fitted restaurant facilities within the new-build premises at Sherwood Lodge.
A summary update on the eight key projects is provided for Members below:
2.5The New Build Development and Redevelopment project (P1) This project has experienced some delays due to supply chain issues and subsequent impacts on development. The new build element of the JHQ reached ‘practical completion’ on 20 January 2021 and was marked with the formal ‘hand-over of keys’ ceremony on this date. The development works on the current Sherwood Lodge building are now underway and are due for completion by June 2022.
2.6A number of areas of development continue on the Sherwood Lodge site including additional car parking at the previous country park site to offer more spaces for staff and visitors, installation of a new higher-power generator for the site to offer more resilience, and continuing grounds work to improve accessibility. 2.7 Whilst the builders, Henry Brothers, have formally handed over the new-build project. They will remain responsible for ‘snagging’ and remedial works in the first 12 months of occupation.
2.8Work has now started on preparing the area vacated by the Police Human Resources team where the Police and Fire Finance teams will be collocated from mid-February.
2.9The Legal Framework (P2) and Finance (P3) These projects have been closed as the legal framework and financial aspects for the Joint Headquarters have been finalised and reported to Strategic Collaboration Board and Members previously.
2.10The financial costs of the Programme continue to be monitored closely however they are currently within budget and due to complete within the predicted spends. Members are reminded that the Service has a capped liability for contributions to the programme and therefore there is no risk of an over-expenditure for the Authority.
2.11Human Resources and People (P4) Work continues to progress for the necessary processes to ensure a smooth transition of personnel between the current Fire Headquarters and the new JHQ. These include vetting processes, a revised equality impact assessment, reasonable adjustments and workforce engagement including employee forums and joint meetings.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Collaboration UpdateReport | 149 KB | DownloadRead as text |
Follow Nottingham Fire and Rescue Authority - Policy and Strategy at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 May 2026 | Exclusion of the PublicResolved to exclude the public from the meeting during consideration of the remaining items in accordance with Sectio... | Decided | Open |
| 15 Nov 2024 | Service Improvement - Futures 25 Closure ReportResolved to note the contents of the report. | Noted | Open |
| 15 Nov 2024 | Exclusion of the publicResolved to exclude the public from the meeting during consideration of the remaining items in accordance with Sectio... | Decided | Open |
| 26 Apr 2024 | Governance ArrangementsResolved to note (1) The arrangements with regard to the direct employment of the Clerk and Monitoring Officer. (2) T... | Noted | Open |
| 26 Apr 2024 | 10-Year Workforce Diversity PlanningResolved to (1) Endorse a long-term commitment to workforce diversity via a 10-year Diversity Plan. (2) Note the cont... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.