Resolved to (1) grant reserved matters approval subject to: (a) no adverse, material comments being received by the 28th February 2023 which arise from further publicity and consist of issues other than those already addressed by this report; (b) the indicative conditions substantially in the form of those listed in the draft decision notice at the end of this report. (2) delegate power to determine the final details of the conditions to the Director for Planning and Transport.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Application No: 22/00083/PRES4 for approval of reserved matters
Application by: Carney Sweeney on behalf of Peveril Securities Limited
Proposal: Application for reserved matters in relations to details of appearance and landscaping for Phase 2 office development (Use Class B1) approved under hybrid planning application reference 18/02277/POUT
The application is brought to Committee because it relates to a major application on a prominent site, where there are important design considerations. The original hybrid application was approved at the January 2019 Planning Committee.
To meet the Council's Performance Targets this application should have been determined by 15th April 2022. An Extension of Time has been agreed until the 28th February 2023.
Recommendations
2.1GRANT PLANNING PERMISSION for the reasons set out in this report, subject to:
a) No adverse, material comments being received by the 25th February 2023 which arise from further publicity and consist of issues other than those already addressed by this report.
b) The indicative conditions substantially in the form of those listed in the draft decision notice at the end of this report.
2.2To delegate power to determine the final details of the conditions of planning permission to the Director for Planning and Transport.
3 SITE, SURROUNDINGS AND BACKGROUND
3.1Unity Square occupies a triangular site which is located to the south of the City Centre. It has frontages to Queen’s Bridge Road/Sheriffs Way, Burnham Way, and also adjoins the main railway line from which it is separated by the Tinker’s Leen watercourse. It sits directly opposite the Grade II* Nottingham Midland Railway Station and the Station Conservation Area.
3.2Adjoining the site to the south and west is the Vat and Fiddle Public House, the Castle Rock Brewery and manufacturing units and warehouses accessed either from Traffic Street or Queen’s Bridge Road. On the east side of Sheriffs Way is a further industrial unit and the former Queens Hotel. Further to the south is the Meadows residential area. 3.3 In January 2019 planning permission was granted for a hybrid planning application (18/0277/POUT), meaning one that seeks full planning permission for part of a site and outline planning permission for the remaining part. The ‘Unity Square’ development comprised two office buildings which were to be constructed in two phases. Full planning permission was granted for Phase 1 and outline planning permission for the Phase 2. Details approved as part of the outline permission included layout, scale and access. Details of appearance and landscaping were reserved for future approval.
3.4Phase 1 of Unity Square is now complete and occupied by HM Revenue and Customs (HMRC).
4 DETAILS OF THE PROPOSAL
4.1This reserved matters application relates to Phase 2, to be positioned on the remaining cleared part of the site to the rear/west of Phase 1. It is immediately adjoined by the railway to the north and industrial/warehouse units to the south and west. The outline permission set the parameters for Phase 2, including its layout/siting, scale/height and access. This application seeks approval for the outstanding ‘reserved matters’, namely appearance and landscaping.
4.2Phase 2 is to be a 12 storey (plus lower ground) office development. The lower ground floor is to accommodate parking for 30 cars (including 2 disabled parking spaces), 100 cycles (including ancillary changing facilities for their users), bin storage and plant. The ground floor has a double height main reception area aligned at the end of the colonnaded pedestrian route incorporated on the northern side of Phase 1. The remaining part of the ground floor and upper floors would provide open plan office floorspace. Vehicular access is via the new junction from Sheriffs Way, shared with Phase 1.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Station Street, Nottingham, NG2 3NGResolved (1) To grant planning permission for the reasons set out in the report, subject to: (a) The indicative condi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.