Resolved
Resolved to: 1. note the actions already completed and the impact of these actions; 2. agree actions planned and being implemented, noting the planned impact of these actions.
Audit Committee noted this item on Friday 31 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved to: 1. note the actions already completed and the impact of these actions; 2. agree actions planned and being implemented, noting the planned impact of these actions.
1.1Internal audit issued in 2020/21 two reports into Contract Management and Procurement Dispensations respectively. Together, these identified a number of actions that Nottingham City Council needs to implement across all departments to ensure compliance with Contract Procedure Rules and to deliver best value. The actions identified were considered to be in line with contracting and procurement best practice and should be implemented to ensure the Council has robust processes in place for procurement and contract management.
1.2A number of actions have already been completed and these are having a significant impact with increased requests to support teams with undertaking procurement exercises. With a reduction in the number of exemptions as per the Exemption Report presented to Audit Committee on the 31st March 2023.
2.1The Contract Management Audit was initially undertaken in 2020 with actions planned during 2020. Due to COVID-19 actions were delayed due to the pressures on teams to deliver a response to the pandemic. The subsequent review of the audit in 2021 clearly identified that actions are still required.
2.2The Procurement Dispensation report was undertaken as a follow up to an initial review of Dispensations by the Head of Contracting and Procurement. The review and audit identified significant non-compliance with Financial Regulations and Contract Procedure Rules which resulted in higher than would be expected requests from officers for Dispensation from Financial Regulations.
2.3These two audit reports are separate in their own right, although the issues raised in each points to historic non-compliance with procedures and a need to ensure Contract Management and Procurement processes are embedded across the Council. 2.4 Resources were agreed through the Transformation Programme and these have been used to develop a new Operating Model for Commercial, Procurement and Contract Management. This informed the senior management restructure in 2022 and the restructure of Procurement that is currently underway.
2.5A Director of Commercial, Procurement and Contract Management was appointed in November 2022 and has developed the Commercial Strategy alongside supporting the implementation of the new Operating Model.
2.6The new Operating Model will further support commercial decision making so that all decisions are robustly considered and implemented in a way that gets best value for the Council and the citizens of Nottingham and also ensures probity.
2.7The funding for the new structure including 15 additional posts was agreed at Full Council on 6th March 2023.
3. Key Actions Undertaken
3.1Quarterly reports on exemptions are reported to Audit Committee showing the number of exemptions and why approved.
3.2New Operating Model for Commercial, Procurement and Contract Management agreed at CLT and additional resources included in MTFP for 2023/24. This has been agreed as part of the Budget Report taken to Full Council on 6th March 2023.
3.3Appointed a Change Lead for Commercial, Procurement and Contract Management and a Procurement Officer to support the implementation of the new Operating Model. Over £400k of savings identified for the Council in 2022/23 with plans being developed for savings over the next 4 years.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Contract Management and Procurement Audits UpdateReport | 211 KB | DownloadRead as text |
Follow Audit Committee at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 31 Jul 2026 | Draft Statement of Accounts 2025/26It was agreed that an analysis would be done and provided ... view the full minutes text for item 21. | Agreed | Open |
| 31 Jul 2026 | Internal Audit Q1 progress updateResolved to note the progress of the 2026/27 Audit plan. | Noted | Open |
| 31 Jul 2026 | Audit Committee Annual Report 25/26Resolved to endorse the Audit Committee Annual Report to Council in September 2026. | Decided | Open |
| 26 Jun 2026 | Appointment of the Vice ChairResolved to appoint Councillor Pavlos Kotsonis as the Vice Chair of the Committee for the 2026/27 municipal year. | Decided | Open |
| 26 Jun 2026 | Future Meeting DatesResolved to meet on the following Fridays at 9:30am: · 31 July 2026 · 25 September 2026 · 27 November 2026 · 29 Janau... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.