AI summaryNottingham City Planning Committee grants permission for 42 extra one-bed flats in the Riverleen House loft, waiving £528,104 of policy-compliant planning contributions on viability grounds.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedSubject to conditions and delegated to Director
Money£528,104 waived on viabilityPolicy-compliant S106 contributions not paid
What happens nextFinal conditions delegatedDirector of Planning and Transport to settle details
Who it affectsRiverleen House, Electric AvenueLoft of former office building
What was decided
Planning Committee granted planning permission for the loft conversion, subject to the conditions in the draft notice and a further employment and training plan condition from the update sheet. Report P5
Final details of the conditions were delegated to the Director of Planning and Transport. Report P6
The application was reported to Committee because planning obligations were proposed to be waived on viability grounds. Report P3
Why
A prior approval last year already established the principle of residential use on the site, and Housing, Highways, the Lead Local Flood Authority and the Environment Agency raised no objection. Report 3.1, P15, P16, P17, P18, 7.1
An independent viability review found the scheme unable to pay any S106 contribution, so policy requirements for affordable housing and public open space were waived. Report 7.4, 7.5
Officers judged the dormer windows, outlook, and living space met design and amenity policies, with all flats exceeding national space standards. Report 7.2, 7.3, 4.1
What happens next
Development must begin within three years of the permission. Report P69
Before first occupation, bird and bat boxes, and bin and bike storage, must be installed. Report P73, P75
The Director of Planning and Transport will determine the final wording of conditions, including the further employment and training plan condition from the update sheet. Report P6
The money
£528,104 Policy-compliant S106 contributions (affordable housing and public open space) that would normally be required Report 7.4
£456,342 Affordable housing contribution identified as policy compliant Report 7.4
£71,761 Public open space contribution identified as policy compliant Report 7.4
Options considered
Chosen: Grant planning permission with conditions and waived S106 contributions on viability grounds. Independent assessor found the scheme unable to pay any S106 contribution, and consulted officers raised no objection Report P5, 7.5, P15, P16, P18
Implications
Financial: Council foregoes approximately £528,104 in policy-compliant planning contributions because an independent assessor found the scheme unviable. Report 7.4, 7.5
Legal: Decision is subject to standard planning conditions and the right of appeal to the Secretary of State under section 78 of the Town and Country Planning Act 1990. Report P69, P87
Equalities: The development is designed to meet Building Regulation accessibility standards and requirements under the Disability Discrimination Act. Report P46
Climate: Reuse of an existing building is recognised as positive in sustainability terms, with limited scope for further intervention; bird and bat boxes required for biodiversity. Report 8.1, P73
Risk: Officers reported no risk management issues arising from the application. Report P48
Who and where
Future residents of 42 additional one-bed flats at Riverleen House Report 4.1, 7.3
Neighbouring properties on Electric Avenue near Queens Drive Report 3.1, P12, P13
Applicant undertaking the loft conversion Report P2, P66
Timeline
Validated 14 October 2025: Application validated by the council Report P79
13th January 2026: Target determination date under Council performance targets Report P4
31/1/26: Extended deadline agreed with the applicant Report P4
Within three years of the permission: Development must begin Report P69
Plain English for the jargon
Prior approval: A light-touch check under permitted development rights, where the council confirms specific matters such as flood risk and highways before work starts, rather than a full planning application.
S106: A legal agreement under section 106 of the Town and Country Planning Act 1990 used to secure planning obligations such as affordable housing or open space contributions from developers.
NDSS: Nationally Described Space Standards, the minimum sizes set by government for new dwellings.
Flood Zone 1 and 2: Environment Agency flood risk classifications, with Zone 1 being low probability and Zone 2 being medium probability of flooding.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item43
Resolved
Resolved to 1. grant planning permission subject to the conditions listed in the draft decision notice at the end of the report, and the further condition (relating to compliance within the employment and training plan) referred to in the update sheet; 2. delegate power to determine the final details of the conditions to the Director of Planning and Transport.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Application No: 25/01823/PFUL3 for planning permission
Application by: [name removed] on behalf of [name removed]: Conversion of loft space to provide residential accommodation (C3)
The application is brought to Committee because planning obligations are proposed to be waived on viability grounds.
To meet the Council's Performance Targets this application should have been determined by 13th January 2026. An extension of time has been agreed with the applicant until 31/1/26.
Recommendations
1. GRANT PLANNING PERMISSION subject to the conditions listed in the draft decision notice at the end of this report.
2. Power to determine the final details of the conditions to be delegated to the Director of Planning and Transport.
Background
3.1The site is a former 2/3 storey office building located on Electric Avenue close to Queens Drive. Prior approval was granted last year for the conversion of the building to provide 118 x 1 bed units (25/01132/PACPD) with development having commenced on site. The prior approval process is a "light-touch" check for certain developments under “permitted development rights”, where you apply to your local council to confirm specific aspects (e.g. flood risk, ground contamination, highways impact etc) are acceptable before starting work, rather than a full planning application. It involves a simpler and less subjective assessment that is judged against set central government criteria rather than local planning policies.
3.2The building is broadly square in shape and formed of interlocking wings around a central courtyard. It is constructed from red brick with elements of stone cladding. The site has extensive landscaping to the north and a generous carpark to the west and is primarily within a commercial setting.
4 Details of the proposal
4.1planning permission is sought to convert the loft space of the building to provide a further 42 x 1 bed flats. 20 are proposed on the 2nd floor and a further 22 on the 3rd floor. A number of dormer windows and roof lights are proposed to be installed to facilitate the conversion and all units would exceed nationally described space standards (NDSS). Bin and bike stores are proposed within the ground floor of the building.
5 Consultations and observations of other officers
Adjoining occupiers consulted:
27 neighbouring properties consulted and site/press notices displayed/published. No letters of representation received.
Additional consultation letters sent to:
Housing: No objection. Based on the information provided by the applicant they are satisfied that the proposal would meet a need for 1 bed accommodation and in this instance do not consider it necessary to seek larger units.
Lead Local Flood Authority: No objection.
Environment Agency: Standing advice applies.
Highways: No objection.
6 Relevant policies and guidance
Aligned Core Strategies (ACS) (2014) Policy A: Presumption in Favour of Sustainable Development Policy 8: Housing Size, Mix and Choice Policy 10: Design and Enhancing Local Identity Policy 14: Managing Travel Demand Policy 19: Developer Contributions
Land and Planning Policies (LAPP) (2020) Policy CC1: Sustainable Design and Construction Policy CC3: Water Policy HO1: Housing Mix Policy HO3: Affordable Housing Policy DE1: Building Design and Use Policy DE2: Context and Place Making Policy TR1: Parking and Travel Planning Policy EE3: Change of Use to Non-Employment Uses Policy EN2: Open Space in New Development Policy EN6: Biodiversity Policy IN4: Developer Contributions
Supplementary Planning Documents
The Provision of Open Space in New Residential and Commercial Development (2019)
Biodiversity (February 2020)
Reduction of Carbon in New Development (June 2025) 7. Appraisal of proposed development
Main Issues (i) Principle of the Development (ii) Design and Visual Impact (iii) Amenity of Future Occupiers (iv) Other Matters
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Station Street, Nottingham, NG2 3NGResolved (1) To grant planning permission for the reasons set out in the report, subject to: (a) The indicative condi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.