East Midlands Shared Services financial outturn position 2025/26
NotedCommittee1 paper
AI summaryEast Midlands Shared Services reports a £281,000 underspend for 2025/26, with each partner authority reimbursed £141,000. The 2026/27 partnership budget is set at £5.82 million following a pension contribution reduction.
Written from the decision and the officer reportPDF Pro
OutcomeNotedReimbursement of £141,000 to each partner
Money£281,000 underspend, £141,000 each partner2026/27 budget set at £5.82 million
What happens nextPension contribution reduced from 17.2% to 11.2%Takes effect from 1 April 2026, saving £205,000
Who it affectsNottingham City Council and Leicestershire County Council. All wards across both authorities
What was decided
The joint committee noted the 2025/26 financial outturn position for East Midlands Shared Services, showing an underspend of £281,000, resulting in a reimbursement of £141,000 to each partner authority. Report P2
The committee noted the amendment to the approved EMSS budget for 2026/27 onwards and the associated partner contributions, including a revised 2026/27 partnership budget of £5.82 million. Report P3, 1.3, 4.2
Why
Individual partnership contributions are affected by the outcome of the 2025/26 outturn position and amendments to the 2026-30 Medium Term Financial Plan agreed in December 2025. Report 2.1
The financial results will be included in the financial reporting of both Nottingham City Council and Leicestershire County Council. Report 2.1
Providing budget forecast information to the joint committee is a key part of the financial management process. Report 3.1
What happens next
The pension contribution will reduce from 17.2% to 11.2% with effect from 1 April 2026, resulting in a £205,000 cost reduction. Report 4.1
A 3.5% provision (£148,000) has been made for the 2026/27 pay award, though the current employer offer of 3.2% may be rejected. Report 4.4
Pay award negotiations are ongoing, with a risk that the final award may exceed the budget provision for 2026/27. Report 4.4
The money
£281,000 Underspend for 2025/26 Report P2, 1.2, 2.1
£141,000 Reimbursement to each partner authority Report P2, 1.2, 2.5
£5.82 million Revised EMSS partnership budget for 2026/27 Report 1.3, 4.2
£205,000 Cost reduction from pension contribution change Report 4.1
£3.276 million NCC partnership contribution for 2025/26 (55.09%) Report 1.1
£2.670 million LCC partnership contribution for 2025/26 (44.91%) Report 1.1
£142,000 2025/26 pay award cost (3.2%) Report 2.3
£5,664,994 Overall funding requirement for 2025/26 Report P67
£3,135,339 NCC share of 2025/26 funding (55.3%) Report P67
£2,529,654 LCC share of 2025/26 funding (44.7%) Report P67
£127,364 Decrease in partner contributions for 2026/27 Report P61, 4.2
Options considered
Chosen: Note the 2025/26 financial outturn position and amended 2026/27 budget. Required to inform partner authorities of the financial outturn and MTFP amendments Report 3.1
Rejected: No other options. Providing budget forecast information to the joint committee is a key part of financial management Report 3.1
Implications
Financial: An underspend of £281,000 for 2025/26 leads to a reimbursement of £141,000 to each partner authority. Report P2, 2.5
Financial: The 2026/27 partnership budget is set at £5.82 million, representing a £127,364 decrease compared to 2025/26 contributions. Report 4.2, P61
Financial: Pension contribution will reduce from 17.2% to 11.2% from 1 April 2026, saving £205,000. Report 4.1
Risk: The 2026/27 pay award provision of 3.5% may be insufficient if the current 3.2% offer is rejected. Report 4.4
Risk: Staffing cost rises through increments and pay awards are assumed, with a 3.5% pay award applied annually from 2026/27. Report P15
Risk: An Oracle contract price increase of 10% is assumed in 2028/29. Report P15
December 2025: 2026-29 Medium Term Financial Plan approved by joint committee Report 1.3, 2.1
31 March 2026: End of 2025/26 financial year, outturn position recorded Report 1.1, 2.1
1 April 2026: Pension contribution reduction takes effect (17.2% to 11.2%) Report 1.3, 4.1
Week commencing 11 May 2026: Sponsors met and approved the report in principle
2026/27: Revised partnership budget of £5.82 million applies Report 1.3, 4.2
Plain English for the jargon
EMSS: East Midlands Shared Services, a joint service between Nottingham City Council and Leicestershire County Council
MTFP: Medium Term Financial Plan, covering the period 2026-27 to 2029/30
FSC: Finance Service Centre, part of EMSS operations
ESC: Employee Service Centre, part of EMSS operations
Claremount: A new archiving solution shared between the partner authorities
Fit for the Future: A legacy programme with associated costs now funded separately from the partnership budget
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
Resolved to note: (1) the financial outturn position for EMSS for 2025/26, reporting an underspend of £281,000, which represents a reimbursement of £141,000 to each partner authority; and (2) the amendment to the approved EMSS budget for 2026/27 onwards and associated partner contributions. Reasons for decision: To inform the partner authorities of the financial outturn position for 2025/26. Individual partnership contributions are affected by the outcome of both the 2025/26 financial outturn position and the amendments to the EMSS 2026-2030 Medium Term Financial Plan post agreement in December 2025. The financial results will be included in the financial reporting of both Nottingham City Council and Leicestershire County Council. Other options considered: No other options were relevant as EMSS is required to provide budget forecast information to the Committee as part of the financial management processes.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Report to East Midlands Shared Services Joint Committee
Recommendations
The EMSS Joint Committee is requested to note the:
1. financial outturn position for EMSS for 2025/26, reporting an underspend of £281,000, which represents a reimbursement of £141,000 to each partner authority.
2. amendment to the approved EMSS budget for 2026/27 onwards and associated partner contributions.
If a Key Decision, state the reason:
(a) Expenditure, Income or Savings of £750,000 or more taking account of the overall impact of the decision.
(b) Significant impact on communities living or working in two or more wards in either Authority.
Does this report contain any information that is exempt from publication? No 1. Background
1.1The report presents the outturn position of the East Midlands Shared Service (EMSS) for the financial year 2025/26 as at 31 March 2026. An update on the spend against earmarked funding for the Claremount archiving solution, currently funded separately to the EMSS partnership contribution, is also provided together with an update on amendments made to the EMSS approved 4-year Medium Term Financial Plan (MTFP) covering the period 2026-27 to 2029/30.
1.2The joint committee is requested to note the outturn position of EMSS for 2025/26, reporting an underspend of £281,000. Reimbursement to each partner authority was £141,000.
1.3Subsequent to the 2026-29 MTFP approval in December 2025, the EMSS pension contribution will reduce with effect from 1 April 2026 resulting in a further cost reduction. The revised EMSS partnership budget of £5.82 million for 2026/27, therefore, is also to be noted. 2. Reasons for recommendations
2.1Individuals partnership contributions are affected by the outcome of both the 2025/26 financial outturn position and the amendments to the EMSS 2026-30 MTFP post agreement in December 2025. These financial results will be included in the financial reporting of both Nottingham City and Leicestershire County Councils.
3. Other options considered and reasons why these were rejected
3.1The requirement to provide budget forecast information to the Joint Committee is a key part of the financial management process and therefore no other options were relevant.
4. Consideration of risk and mitigations
Risk Mitigation Staffing cost rises Increments applied according to payment policy Pay award implications Assumed 3.5% annually from 2026/27 onwards Oracle contract price increase Assumed 10% uplift in 2028/29
Comments and considerations 5. Finance
5.1Total value of the decision: £281,000 Capital Revenue N/a Expenditure Income Savings N/a 5.2 The report has been reviewed and approved in principle by the sponsors at the meeting held week commencing 11 May 2026.
• Simone Hines – Assistant Director of Finance, Transformation and Commissioning, Leicestershire County Council (LCC);
• Hayley Mason– Director of Finance, Nottingham City Council (NCC)
5.3Has the spend been approved by the Section 151 Officer? Yes No N/A
6. Legal
6.1None.
7. Other comments and considerations
7.1None.
8. Additional implications
8.1None.
9. List of appendices to this report
9.1Appendix A – Medium Term Financial Plan 2026-30.
10. List of background papers relied upon in writing this report
10.1None.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow East Midlands Shared Services Joint Committee at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.