Resolved
1) to note the update. 2) to recommend that officers prepare a report to review air-conditioning capacity and investigate upgrades which may improve heat-preparedness across the tram network, and report back to the Advisory Committee.
AI summaryNottingham's light rail advisory committee noted December 2025 to May 2026 tram performance, with reliability at 92.51% and punctuality 91.21%, and asked officers to report back on air-conditioning upgrades.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
1) to note the update. 2) to recommend that officers prepare a report to review air-conditioning capacity and investigate upgrades which may improve heat-preparedness across the tram network, and report back to the Advisory Committee.
Agenda Item GNLRT ADVISORY COMMITTEE Dec 2025 – May 2026
NET OPERATIONAL PERFORMANCE AND PROGRESS UPDATE
1. Summary of Issues This report updates the Committee on the performance and progress of Nottingham Express Transit (NET) from the beginning of December 2025 to May 2026
2. RECOMMENDATION It is RECOMMENDED that the Committee notes the report.
3. OPERATIONAL PERFORMANCE The reliability and punctuality of the tram service during this period were recorded at 92.51% and 91.21% respectively. The months of February and March were our worse performing months due to a combinations of driver and tram availability in addition to some significant incidents.
The network continues to experience a significant number of road traffic collisions involving trams and other road vehicles. A total of 33 such collisions were recorded during the period under review. The most significant of these was a collision between Tram 228 and a Nottingham City Transport bus at the Inham Road crossing.
The frequency of these incidents continues to have a significant impact on service delivery, as each occurrence requires the affected tram to be withdrawn from service pending inspection and, where necessary, repair. Tram 228 is expected to remain out of service for several months while these works are completed, with consequent implications for NTL ability to maintain a full timetable.
NTL are working collaboratively with both local authorities and Nottinghamshire Police to try to target high risk locations and where possible design the risk out or mitigate it.
NTL also launched phased 2 of the Road Traffic Collision awareness media campaign, this attracted coverage from the local TV news programs, local radio and online media platforms. This campaign was focused around not trying to race the tram and taking risks at traffic light- controlled junctions. Tram Availability
Tram availability during the period has been challenging in terms of Operation Service Delivery and has had a detrimental impact on overall performance. NTL have commenced a process of managing performance in this area to secure improved tram availability going forward.
Whilst this is expected to improve overall availability, some significant issues remain. Two trams remain off the Network undergoing repairs, alongside a rolling programme to stand down one tram per week for the remainder of the year to complete the overspeed modifications. This programme is necessary to ensure compliance with the actions set by the Office of Rail and Road (ORR) in relation to the Sandilands recommendations.
Driver Availability
Driver availability also remained challenging during the period, with high levels of sickness absence and attrition continuing to hinder recovery. Management of absence has been strengthened through full weekly reviews, ensuring staff are supported to return to work safely at the earliest appropriate opportunity, in line with our internal absence management procedures.
NTL have also accelerated our driver recruitment plan to counteract vacancies arising from attrition, with the aim of returning to a full driver workforce as quickly as possible.
Longer term, NTL have commenced several workstreams aimed at improving sustainability and efficiency. This has included a review of informal working arrangements and a substantial piece of work to either formalise these arrangements or return drivers to standard rosters. This work has now been completed, and as NTL move into the next period, NTL will introduce a new roster designed to make best use of flexible working arrangements.
Goldsmith Street Engineering Works
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
NET Operational Performance and Progress UpdateReport | 107 KB | DownloadRead as text |
Follow Greater Nottingham Light Rapid Transit Advisory Committee at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Appointment of ChairResolved to appoint Councillor Andy Brown as Chair of the Committee for the 2026/27 municipal year. Councillor Andy B... | Decided | Open |
| 14 Jul 2026 | Appointment of Vice-ChairResolved to appoint Councillor Angela Kandola as Vice Chair of the Committee for the 2026/27 municipal year. | Decided | Open |
| 14 Jul 2026 | Future Meeting DatesResolved to meet on 12 January 2027, 2pm at Loxley House, Station Street, Nottingham. | Decided | Open |
| 13 Jan 2026 | NET Operational Performance and Progress UpdateResolved to note the update. | Noted | Open |
| 13 Jan 2026 | Tramlink UpdateResolved to note the update. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.