CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Nottingham City Council

Highway Maintenance

Decided Scrutiny 3 papers

AI summaryNottingham scrutiny committee recommends the Council reviews future heat-related highway defect risk and improves public communication on road repairs.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedOn heat risks and communications
Money£79.00 million backlogHighway maintenance shortfall
What happens nextExecutive to considerRecommendations for action
Who it affectsHighway users and residentsAcross Nottingham

What was decided

The committee recommended that consideration be given to whether long periods of high temperatures could give rise to future highway defects, and what proportionate action could be taken at an early stage in design, management and maintenance.

The committee recommended that consideration be given to how communications and engagement with Nottingham people could be further developed in a simple and accessible way to set out how the Council identifies and delivers highway repair work, what does and does not constitute a priority repair, and the timelines for action.

Why

The committee reviewed an overview of how the Council manages its roads to keep them maintained and safe, covering inspection regimes, response times, planned investment, pothole fixing, claims and safety management. Report 1.1

The committee heard that a significant funding shortfall exists against the level of investment needed to keep the network in its current condition, alongside a growing national backlog of repairs. Report 3.13

The committee heard that public understanding of how repair priorities are set could be improved to help residents and road users know what to expect. Report 3.16, 3.17, 3.18

What happens next

The Council is asked to consider whether long periods of high temperatures pose a future risk of highway defects and what proportionate early action could be taken in design, management and maintenance to mitigate these risks.

The Council is asked to consider how communications with Nottingham people about identifying and delivering highway repair work, what counts as a priority, and the timelines for action could be made simpler and more accessible.

The money

  • £18.62 billion National backlog of highway repairs Report 3.13
  • £79.00 million Current Nottingham highway maintenance backlog Report 3.13
  • £9.150 million Annual steady state investment needed to maintain network in current condition Report 3.13
  • £5.770 million EMCCA maintenance funding for 2026/27 Report 3.13
  • £1.800 million Estimated Streets for People funding for 2026/27 Report 3.13
  • £1.580 million Shortfall against steady state requirements for 2026/27 Report 3.13
  • £8,246.17 Total payment on highway claims for 2025/26 Report 3.14
  • around £0.5 million Potential cost of all 2025/26 claims if 100% had been successful Report 3.14

Implications

  • Financial: A £1.580 million shortfall against steady state investment in 2026/27 risks further deterioration of the network and growth of the £79.00 million maintenance backlog. Report 3.13
  • Risk: Defects are categorised by risk with emergency defects attended within two hours and urgent defects within 36 hours, with customer reports currently responded to at 99.6%. Report 3.4, 3.5
  • Legal: Highway claims for 2025/26 totalled 235 notifications with a 91% repudiation rate; 19 remain in progress and could affect the final financial outcome. Report 3.14
  • Climate: The committee flagged a potential future risk that long periods of high temperatures could give rise to highway defects, asking for proportionate early action.
  • Other: Innovation trials are under way, including Elastomac (a pothole treatment using end-of-life waste tyres) and Thermal Patch (heat-based recycling of failed surfacing). Report 3.6
  • Other: A 24 hour, seven day a week emergency call-out service covers dangerous potholes, road traffic accidents, highway obstructions, road collapses, spillages and debris, with the Highways team also leading the Council's operational flood response. Report 3.8

Who and where

  • Nottingham residents and road users Report 1.1, 3.16
  • Cyclists, pedestrians and shared-use path users Report 3.2
  • Emergency services, public transport operators, utility providers, the Ministry of Defence and neighbouring Highway Authorities Report 3.10
  • Highway claimants and potential claimants Report 3.14

Timeline

  • 1 April 2025 to 31 March 2026: Period covered by the highway claims data reported Report 3.14
  • 2026/27: Funding year in which identified carriageway funding leaves a £1.580 million shortfall against steady state Report 3.13
  • by 2028/29: Based on current funding awards, funding is expected to reach the steady state value Report 3.13
  • At least once each year: All roads are inspected at least annually, with higher category roads inspected monthly Report 3.2
  • Annual review: Winter service plan reviewed annually with five gritting routes Report 3.7

Plain English for the jargon

  • EMCCA: East Midlands Combined County Authority, a source of maintenance funding for the Council
  • DfT: Department for Transport, a source of grants for highway maintenance
  • Steady state: The level of annual investment the Council estimates is needed to maintain the road network in its current condition
  • Streets for People: A ward-level planned maintenance programme funded by a population and deprivation formula
  • Elastomac: A pothole treatment using end-of-life waste tyres, currently being trialled
  • Thermal Patch: A repair method using heat and added bituminous material to recycle failed surfacing into a re-laid repair, currently being trialled
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16

Resolved

1) To recommend that consideration is given to whether there is a potential risk in the future that long periods of high temperatures could also give rise to defects in the highway, and what proportionate action could be taken at an early stage in the context of highway design, management and maintenance to mitigate these risks. 2) To recommend that consideration is given to how communications and engagement with Nottingham people could be further developed in as simple and accessible a way as possible to set out how the Council identifies and delivers highway repair work, what does and does not constitute a priority repair issue and why, and the timelines for associated action being taken.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Homes, Economy and Infrastructure Scrutiny Committee

Homes, Economy and Infrastructure Scrutiny Committee 20 July 2026

Report Title: Highway Maintenance

Executive Remit: Regional Development, Growth and Transport

1. Purpose

1.1The purpose of this report is to provide an overview of how the Council manages its roads to ensure that they are maintained and safe to use. It covers the strategic approach to road maintenance, planned investment, repair management, pothole fixing, claims and how safety of the roads is managed.

2. Context

2.1Highway Maintenance is a core part of the Highway and Public Realm Service within Resident Services. The Service prioritises the effective use of Council revenue funding, East Midlands Combined County Authority (EMCCA) funding and Department for Transport (DfT) grants to deliver core highway functions.

2.2Following a transformational reorganisation in 2025, the Service now comprises six key delivery areas: Highway Maintenance, Highway Construction, Highway Design, Highway Contracts and Compliance, Public Realm Grounds, and Public Realm Trees. A modern hybrid operating model is in place to provide flexibility, capacity and access to specialist services, when required.

3. Highway Maintenance

3.1The Highway Maintenance elements of the Service are structured around three main operational areas: the Highway Safety Regime, the Highway Response Service and Planned Maintenance. The Highway Safety Regime includes highway safety inspections, customer response and highway safety repairs. The Highway Response Service includes winter gritting, emergency call-out and flood response. Planned Maintenance includes asset management, planned maintenance delivery and the ‘Streets for People’ programme.

Assessing Defects on the Highway

3.2The Council has an established highway maintenance regime in place to keep residents and road users safe. Safety inspections cover footways, shared-use cycleways, carriageways, on-road cycleways, highway drainage, street furniture, safety barriers and restraint systems, non-illuminated signs, highway trees and road markings. Defects identified through inspection are either managed by the Highway Maintenance team or passed to the relevant responsible organisation where they sit outside the highway maintenance remit. 3.3 All roads are inspected at least once each year, with some higher category roads inspected monthly. Inspections include carriageways, footways and cycle routes, and are undertaken through both driven and walked inspections across the city. In the event of a claim, inspection records and defect data held in the Council’s asset management system are reviewed to evidence compliance with the adopted inspection regime.

3.4Defects are categorised according to risk and required response times. Emergency safety defects are attended within two hours where there is potential for serious risk or major disruption. Urgent safety defects are made safe as soon as reasonably practicable within 36 hours. Other safety defects are managed through 14-day or 28-day responses, depending on severity, while condition defects that do not represent a safety concern are monitored or addressed through planned routine maintenance.

3.5Road repairs are managed through both the highway maintenance regime and responses to issues reported by residents and road users. Customer reports are received through the Council’s ‘Report a Problem’ website. Enquiries are inspected and responded to within three days, while emergency items are attended within two hours. Current performance for responses is reported at 99.6%. Reports are sent directly to highway inspectors’ mobile devices and subsequent works orders are managed through the asset management system.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for Highway MaintenanceReport 93 KB DownloadRead as text
PDF
Enc. 2 for Highway MaintenanceReport 3 MB Download
PDF
Highway MaintenanceReport 86 KB Download

At this meeting

Whole meeting

Who was there

5 of 17 attended
LA
Councillor Leslie AyoolaCommittee Member, apologies (council business)
SB
Sophia BeswickOfficer, in attendance
KC
Councillor Kevin ClarkeCommittee Member, present
SH
Councillor Sam HarrisCommittee Member, absent
JH
Councillor Jay HayesGuest, in attendance
DH
David HobbsOfficer, in attendance
PU
Councillor Patience Uloma IfedioraGuest, in attendance
KL
Councillor Kirsty L JonesCommittee Member, present
CK
Chris KeaneOfficer, in attendance
ML
Mary LesterOfficer, in attendance
AM
Adrian MannClerk, in attendance
SN
Councillor Sana NasirCommittee Member, present

All 17 on the meeting page

On this subject at Nottingham

Search all
  1. Highway MaintenanceThis decision
  2. Highways Planned Maintenance Programme Delivery 2024-25 - key decisionApproved
  3. Contract to carry out planned road maintenance and highway construction works for Nottingham City 2021-22 - Key DecisionApproved

More from Nottingham Homes, Economy and Infrastructure Scrutiny Committee

All decisions
MeetingDecisionOutcome
20 Jul 2026 Appointment of the Vice ChairResolved to appoint Councillor Michael Savage as the Vice Chair of the Committee for the 2026/27 municipal year. Decided Open
20 Jul 2026 Private Rented Housing LicensingResolved to recommend that a proportionate ongoing review process is developed to continue to monitor and report on t... Decided Open
15 Jun 2026 Appointment of the Vice ChairResolved to defer the appointment of the Vice Chair to the Committee’s next meeting. Deferred Open
15 Jun 2026 Student Accommodation in Nottingham1) To request that further information is provided on the current number of Houses in Multiple Occupation (HMOs) in N... Decided Open
15 Jun 2026 Housing Consumer Standards DeliveryResolved to recommend that consideration is given to the extent that Housing Services’ in-house capacity to deliver c... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies