Resolved
That the report be noted.
Full Council noted this item on Tuesday 9 December 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
That Members note the progress set out in this report.
3. Information
The report of 22 January 2014 awarding the contract to SLM set out that the next stage involved two parallel work streams these being the applications for planning permissions and the close of contract negotiations.
Planning permission was granted for the two new pools by the Development Control Committee on 29 May 2014.
Detailed contract negotiations could only take place once the contract had been awarded and these commenced virtually immediately upon contract award. These negotiations not only involved those between the Council and SLM as the operator, but also the contracts between SLM and their appointed building contractors. Whilst there has been willing on all sides to conclude negotiations as soon as possible, as it is clearly in everyone’s interest for the works to be completed as soon as possible, the negotiations became far more protracted than was envisaged would be the case. In particular this can mainly be contributed to two factors. The first being that, by having two separate building developments has effectively meant that there are two projects. The two projects are quite distinct from each other, one a complete new build at Wigston and the other, a split between new build and refurbishment at Parklands; this has meant that the projects have progressed at different speeds as they have had different issues to resolve. However the final contract signing had to incorporate both projects together. In hindsight, the appointment by SLM of two separate building contractors has made the contract negotiations more complex with having to deal with two separate developers and their individual legal teams. The purpose of this approach was founded on financially prudent measures and to counteract the potential for a sole building contractor being unable to deliver the two projects running side by side.
The other factor has been the negotiation of the costs of unforeseen additional works as the tender price was subject to detailed surveys being undertaken. This meant that at the time of tendering, assumptions had to be made as to, for example, ground conditions, from visual inspections and other information available. This is a standard approach in procurement, in that further intrusive surveys are undertaken at contract award principally because the Council is reliant on the warranties coming from any bidder and these will be reliant on the intrusive surveys (particularly for ground conditions), as a result it is important that the bidders undertake the survey. If bidders are asked to undertake surveys prior to award then this has led to difficulties in bidders withdrawing or lack of responses because of the additional cost. Any additional works identified are subject to testing and ensuring that they are fully justified as below.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Leisure Contract UpdateReport | 97 KB | DownloadRead as text |
Follow Full Council at Oadby and Wigston and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | Update on Community Governance ReviewRESOLVED THAT: i) Recommendation B known as “Option 2” be approved, as amended; ii) A budget of £250k to undertake th... | Approved | Open |
| 30 Jul 2026 | Apologies for AbsenceRESOLVED THAT: Councillor J K Chohan assist the Deputy Mayor (in the Chair) for the duration of this meeting only. | Decided | Open |
| 30 Jul 2026 | Local Government ReorganisationRESOLVED THAT: (i) The Council notes the recent announcement by the Labour Government for Local Government reorganisa... | Decided | Open |
| 7 Jul 2026 | Conferment of Title of Honorary Alderwoman to Mrs Helen Elizabeth LoydallRESOLVED THAT: (i) In accordance with section 249(1) of the Local Government Act 1972, that [name removed] had render... | Decided | Open |
| 7 Jul 2026 | Tuesday, 14 April 2026RESOLVED THAT: The minutes of the previous meeting held on 14 April 2026 be taken as read, confirmed and approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.