Internal Audit Progress Report 2015/16 and Audit Plan 2016/17
NotedFinance3 papers
Policy, Finance & Development Committee noted this item on Tuesday 29 March 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED THAT: (i) The content of the Progress Report for 2015/16 be noted by Members; (ii) The Audit Plan for 2016/17 be approved; and (iii) The Audit Plan for 2016/17 be noted as indicative at this stage insofar as the days allocated to each audit may change following the reviews in 2015/16.
Word for word from the decision Oadby and Wigston published for this meeting.Source: moderngov.oadby-wigston.gov.uk
2.1That Members note the content of the Progress Report for 2015/16
2.2That Members approve the Audit Plan for 2016/17 and note that the Plan is indicative at this stage, and the days that are allocated to each audit may change following the reviews in 2015/16.
3. Information
3.1The Internal Audit Plan for 2015/16 totals 254 days and includes 27 reviews planned to be conducted in year. To date in 2015/16 Internal Audit have issued nine final reports and one draft report with thirteen other audits in progress and at various stages of completion. Four audits were agreed to be dropped in order to resource additional work.
The purpose of the Report is to:
a) Show progress against the Audit Plan b) Summarise key findings and conclusions arising from the work performed during the period.
Appendix 1 gives details of the audits completed so far in 2015/16 and provides information on the audit recommendations.
3.2Appendix 2 to this report contains the Internal Audit Plan for 2016/17. The plan included 23 audit assignments programmed over 260 days. Audits are identified by and linked to the Council’s business objectives and strategic risks.
Background Documents:-
Internal Audit 2015/16 Plan
Email: [email protected] Tel: (0116) 257 2891 Implications Financial (CR) No significant implications. Legal (AC) No significant implications. The internal audit is a key component of the Council’s internal control Risk (CR) framework. Outcomes of all internal audit reviews will be considered in the context of the strategic risk register. Equalities (AC) No significant implications.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy, Finance & Development Committee at Oadby and Wigston and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.