RESOLVED THAT: (i) The remedial solutions (as outlined in Option 2 of the report) be approved subject to carrying out a more detailed and in depth technical survey; (ii) The existing windows be replaced and financed by bringing forward expenditure from future provision contained in the 30 year business plan; and (iii) The cost of the works to be partly or wholly funded through the under spend on the External Wall Insulation (EWI) Contract and the works to be procured by a variation to the existing EWI contract.
Word for word from the decision Oadby and Wigston published for this meeting.Source: moderngov.oadby-wigston.gov.uk
2.1It is recommended that the remedial solutions as outlined in Option 2 of the report be approved subject to carrying out a more detailed and in depth technical survey.
2.2In addition it is also recommended that the existing windows be replaced which would be financed by bringing forward expenditure from future provision contained in the 30 year business plan.
2.3That the cost of the works to be partly or wholly funded through the under spend on the External Wall Contract and the works to be procured by a variation to the existing EWI contract.
3. Information
3.1Elizabeth Court is a general needs block of flats, constructed circa 1970 consisting of - 80 units built over 2 and 3 storeys. - 3.2 The building is a mixture of masonry cavity walls, with hung tile solid walls to window - panels and solid wall decorative end elevation infill’s. - 3.3 Over 30 % of the flats have experienced issues with dampness, mould growth and - condensation and we recently had to move one of the tenant’s out due to health - issues aggravated by the problems. - 3.4 A sample survey was carried out in 5 flats which have been suffering with dampness - issues together with an invasive investigation into the structure of the building. - 3.5 The inspection report revealed that there are a number of failed fabric elements and - poor ventilation issues which are having a significant impact on the thermal - performance of the building. In order to fully address all of the issues it is proposed to - carry out a full building survey to ascertain a comprehensive assessment of the all - defects and to finalise the remedial solutions. - 3.6 In summary the defects comprise of the following: - - Faulty Cavity Wall Insulation - Cold bridging and mould growth - Heat loss due to missing and poorly laid loft insulation - Lack of adequate ventilation - Poor condition of double glazing - Heat loss due to partial solid wall construction - High energy bills leading to fuel poverty -- Health risks due to excessive airborne moisture content. - 3.7 A range of measures are recommended to address the issues listed above which - include the following: - Extraction of the failed cavity wall insulation and refilling with high performance - thermal beads - Removal of debris and obstructions in the cavities - Partial External Wall insulation to solid wall areas - - Improved ventilation - New loft insulation - New replacement double glazing - 3.8 It is estimated that the cost of the works as shown in option 2 of the report will cost in - the region of £290,000 plus professional fees of 2.5% which can be wholly or partly - funded from savings in the current external wall contract. ECO (Energy Companies - Obligation) funding of around £20,000 is likely to be available which will be used to -- offset the costs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.