RESOLVED THAT: The proposals and schemes as detailed in the report regarding Brocks Hill and Parklands Leisure Centre, including the capital borrowing requirement of £1.2 million including contingencies, be approved and delivered by extending the existing partnership arrangements with Sports and Leisure Management Limited. Votes For 16 Votes Against 4 Abstentions 1
Word for word from the decision Oadby and Wigston published for this meeting.Source: moderngov.oadby-wigston.gov.uk
Matter for Tuesday, 05 Council Information and September 2017 Decision
Potential Developments at Parklands Leisure Centre Title: and Brocks Hill, Oadby
Author(s): Anne Court (Director of Services / Monitoring Officer)
1. Introduction
1.1This report follows on from the Budget Options report presented to Council on 6 July 2017 which set out a range of future policy budget options for Members to consider, one of which was reducing the revenue costs of the running of the Brocks Hill Centre, Oadby (“the centre”). A comprehensive explanation of the financial situation was provided to Members together with strategic options for the future of the centre. The most viable of these options which anticipates significant revenue efficiencies and most importantly, will substantially retain the ethos of the existing Centre and the park itself, was considered to be the proposal of the Council’s existing Leisure Contractor, Sports Leisure Management Ltd (SLM). Members requested a further report and presentation be brought to this meeting on the proposal together with an update on the proposals for enhancing car parking facilities at the Parklands/Brocks Hill site and enhancing pedestrian access to the site from both Oadby and Wigston.
1.2There will be a presentation by [name removed], SLM’s Area Manager, at the meeting to provide further details of the proposal and costings; a summary of which is provided within this report. [name removed] will explain how the combination of the existing leisure facilities across the Parklands/Brocks Hill site and new facilities will substantially enhance the whole site making it a unique “one stop shop” leisure destination for families, creating a flagship “leisure park” which will enhance the health and wellbeing for all.
1.3In addition, the report sets out the progress that has been made to enhance access for users of the site in terms of car parking but also pedestrian access through the creation of new footpaths from both Oadby (B582 Wigston Road, Oadby) and from Wigston (Tendring Drive).
2. Recommendation(s)
That Members consider the proposals within this report and approve the schemes, including the capital borrowing requirement of £1.2 million including contingencies.
3. Information
3.1The Country Park (“the park”) surrounding the Centre
As emphasised in the report of 6 July, the park and its facilities will continue to be directly managed by the Council through a combination of the Park Warden, the grounds maintenance team and significant input from volunteers. This will ensure the expertise will ensure biodiversity and conservation elements continue to flourish and nationally accredited standards are maintained. The park and centre will continue to be open to all and events such as the annual garden party will continue to be held and promoted. SLM’s proposal includes working in partnership to increase awareness of the park and support the Council with events which will provide increased resources and to put on more events.
3.2The Centre
3.2.1 As explained in the report of 6 July, despite a significant amount of effort and initiatives in recent years to increase the revenue of the centre, it continues to run at a significant loss of approximately £100,000 per annum. A comprehensive explanation of the major sources of income and expenditure over recent years was set out in the report which fall short of coming anywhere near meeting the running costs of the centre (it is understood that cost neutrality has not been achieved by any country park service in the UK, particularly one that does not charge for car parking and entrance). In particular, and by far the largest element of costs, are staffing costs due to the centre being open all but four days a year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Update on Community Governance ReviewRESOLVED THAT: i) Recommendation B known as “Option 2” be approved, as amended; ii) A budget of £250k to undertake th...
Local Government ReorganisationRESOLVED THAT: (i) The Council notes the recent announcement by the Labour Government for Local Government reorganisa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.