RESOLVED THAT: (i) It be approved that the Borough Council enters into a formal Building Control Shared Service arrangement operated and managed by Blaby District Council and including Harborough District Council with effect from 1st January 2018 in order to revitalise the service that the Borough Council provides and to create greater resilience; and (ii) Matters relating to the agreement of the detailed procedural and operational arrangements, including the agreement and signing of an inter-authority agreement relating the Shared Service arrangement be delegated to the Director of Finance & Transformation / Section 151 Officer.
Word for word from the decision Oadby and Wigston published for this meeting.Source: moderngov.oadby-wigston.gov.uk
Matter for Tuesday, 05 Council Information and December 2017 Decision
Title: Proposed Future of the Building Control Service
Adrian Thorpe (Head of Planning, Development Author(s): and Regeneration)
1. Introduction
1.1This report follows the resolution of Council on 6 July 2017 regarding the delivery of discretionary services. Elements of the Building Control service can be considered discretionary as set out below. This report explores a number of options with regard to the future provision of a cost effective and resilient Building Control Service.
1.2Members previously considered the Council’s Building Control service at Policy, Finance and Development Committee in February 2015 in the context of the outcomes of a review of the service that had been carried out by an external consultant at that time. That report recommended that alternative methods of delivering Building Control services be investigated. This process has been ongoing since that date but it is only recently that a realistic and viable option has come forward.
2. Recommendation(s)
2.1Members approve that the Borough Council enters into a formal Building Control Shared Service arrangement operated and managed by Blaby District Council and including Harborough District Council with effect from 1st January 2018 in order to revitalise the service that the Borough Council provides and to create greater resilience.
2.2Members delegate matters relating to the agreement of the detailed procedural and operational arrangements, including the agreement and signing of an inter-authority agreement relating the Shared Service arrangement to the Director of Finance and Transformation.
3. Information
3.1The scope of the service is primarily to process applications for Building Regulations approval, providing guidance and enforcing building standards. The workload is split into two areas – Building Regulation fee earning work and statutory non fee earning services. The introduction of Approved Inspectors and private sector alternative service providers has created a challenging market for Building Control services resulting in local authorities experiencing a significant reduction in market share and therefore fee income.
3.2The Building Control Team sits within the Planning, Development and Regeneration Section of the Council. The Establishment has two Building Control Surveyor posts. Due to the small size of the Team there is no Team Leader/Manager post on the Establishment. Both posts therefore report directly to the Head of Planning, Development and Regeneration.
3.3One of the two posts is filled by a longstanding and experienced member of staff. The second post is currently being covered by an agency member of staff and this has been the case since March 2016. The cost of agency cover since March 2016 to the end of September 2017 is £114,000. Several attempts have been made to recruit to the post, both in the usual way and also to recruit a contractor directly on a temporary basis. However, these attempts have all proved unsuccessful as other councils have also found to be the case. Consideration has also been given to recruiting a graduate officer, but this was not considered appropriate given the small size of the Building Control Service due to the level of training and support that would be required.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Update on Community Governance ReviewRESOLVED THAT: i) Recommendation B known as “Option 2” be approved, as amended; ii) A budget of £250k to undertake th...
Local Government ReorganisationRESOLVED THAT: (i) The Council notes the recent announcement by the Labour Government for Local Government reorganisa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.