RESOLVED THAT: (i) A Section 106 sum of £97,321 forming part of a Sports Facilities Fund in the ‘Horsewell Lane Pavilion and 3G Artificial Pitch’ report to Council on 31 October 2017 be allocated to the project to create a total sum of Section 106 funding available for the project of £375,299. (ii) The remainder of the funding required to deliver the project be allocated from the Council’s Capital Programme budget, up to a total value of £621,387. (iii) Faithful and Gould be instructed to proceed with developing the concept design to bring the new building forward for planning permission in June 2018 and to proceed with the procurement of the main contractor. (iv) Key stakeholders including Councillors L A Bentley and J W Boyce, as Ward Councillor and Chair of Place Shaping Working Group, to be regularly consulted at significant stages of the development, with all Members kept regularly updated on progress of the project and build. (v) Delegated authority be given to the Director of Finance and Transformation / Section 151 Officer, in agreement with the Leader of the Council and Councillor L A Bentley, to make any further decisions relating to the replacement of Horsewell Lane Pavilion and its environs that are within the approved budget in order to enable the project to be delivered within the required timescale.
Word for word from the decision Oadby and Wigston published for this meeting.Source: moderngov.oadby-wigston.gov.uk
Matter for Tuesday, 24 April Full Council Information and 2018 Decision
Title: Replacement of Horsewell Lane Pavilion, Wigston
Adrian Thorpe (Head of Planning, Development Author(s): and Regeneration)
1. Introduction
1.1At its meeting on 31 October 2017 the Council considered a report regarding the provision of a replacement pavilion at Horsewell Lane Recreation Ground. Members agreed to proceed with the development of a new pavilion at the site. This report provides an update on the progress of the project to date.
1.2Since 31 October 2017 Officers have employed Faithful and Gould to act on behalf of the Council to manage the design and construction of the building. They have identified that the budget of £660,000 contained within the Capital Programme is insufficient to deliver a building of the nature and type that would fully meet the needs of the Council and users for the reasons set out in this report. However, this reports sets how the building can be fully funded through financial re-structuring and the use of available Section 106 contributions, thereby reducing the extent of borrowing risk to the Council.
2. Recommendation(s)
That Council considers the report and approves accordingly that:
2.1A Section 106 sum of £97,321 minuted as forming part of a Sports Facilities Fund in the ‘Horsewell Lane Pavilion and 3G Artificial Pitch’ report to Council on the 31 October 2017 is allocated to this project to create a total sum of S106 funding available for this project of £375,299. This re-allocation of the £97,321 will not impact upon the delivery of the enhancements to playing pitch provision in Wigston and South Wigston as the Sports Facilities Fund will still contain £446,000. Additionally, the contribution to the 3G pitch as match funding for Oadby Owls is unaffected. This Section 106 funding coupled with the amount allocated within the Capital Programme detailed in 2.2 below will be sufficient to deliver the new pavilion, providing the best possible facility for residents of the Borough.
2.2The remainder of the funding required to deliver this project is allocated from the Council’s Capital Programme budget, up to a total value of £621,387, thus reducing the Council’s exposure to borrowing within the Capital Programme through the use of Section 106 funding.
2.3Faithful and Gould are instructed to proceed with developing the concept design to bring the new building forward for planning permission in June 2018 and to proceed with procurement of the main contractor. Key Stakeholders including Councillors L A Bentley and J W Boyce, as Ward Councillor and Chair of Place Shaping Working Group, to be regularly consulted at significant stages of the development and for all Members to be kept regularly updated on progress of the project and build.
2.4Delegated authority is given to the Director of Finance and Transformation / Section 151 Officer in agreement with the Leader of the Council and Councillor L A Bentley to make any further decisions relating to the replacement of Horsewell Lane Pavilion and its Environs that are within the approved budget (as set out in paragraph 2.1 and 2.2) in order to enable this project to be delivered within the required timescale.
3. Information
3.1The Economic Regeneration Team Leader has undertaken a review of the project to date. Faithful and Gould (F&G) were then employed to on behalf of the Council to manage the design and construction of the new pavilion. They initially reviewed the project background and also undertook a desktop cost assessment exercise based upon the estimated replacement cost of a community building of a like for like size. Building on this review they have produced a final concept design which has been scrutinised and agreed by key stakeholders and is included at Appendix 1.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Update on Community Governance ReviewRESOLVED THAT: i) Recommendation B known as “Option 2” be approved, as amended; ii) A budget of £250k to undertake th...
Local Government ReorganisationRESOLVED THAT: (i) The Council notes the recent announcement by the Labour Government for Local Government reorganisa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.