Resolved
RESOLVED THAT: That the contents of the report and appendix be noted.
Service Delivery Committee noted this item on Tuesday 20 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT: That the contents of the report and appendix be noted.
Service Delivery Tuesday, 20 Matter for Committee November 2018 Information
Report Title: Community Services Update (Q2 2018/19)
Report Author(s): Steve Nash (Housing Services Manager) John Stemp (Community Property Manager)
Purpose of Report: This report is to provide an update to the Committee regarding the delivery of community services, half-year outturn 2018/19.
Report Summary: This report includes standing reported items on voids, gas safety, capital projects and disabled facilities grants.
Recommendation(s): That the contents of the report and appendix be noted.
Responsible Strategic Stephen Hinds (Director of Finance & Transformation) Director, Head of Service (0116) 257 2681 and Officer Contact(s): [email protected]
Adrian Thorpe (Head of Planning, Development and Regeneration) (0116) 257 2645 [email protected]
Steve Nash (Housing Services Manager) (0116) 257 2662 [email protected]
John Stemp (Property Manager) (0116) 257 2726 [email protected]
Corporate Priorities: An Inclusive and Engaged Borough (CP1) Effective Service Provision (CP2) Green & Safe Places (CP4)
Vision and Values: “A Strong Borough Together” (Vision) Accountability (V1) Customer Focus (V5)
Report Implications:-
Legal: There are no implications arising from this report.
Financial: Although there are no direct implications arising directly from this report it is worth noting the severe financial pressure that some of these services operate under.
Corporate Risk Management: Decreasing Financial Resources (CR1) Effective Utilisation of Assets/Buildings (CR5) Regulatory Governance (CR6)
Equalities and Equalities There are no implications arising from this report. Assessment (EA): EA not applicable.
Human Rights: There are no implications arising from this report.
Health and Safety: There are no implications arising from this report.
Statutory Officers’ Comments:-
Head of Paid Service: The report is satisfactory.
Chief Finance Officer: The report is satisfactory.
Monitoring Officer: The report is satisfactory.
Consultees: None.
Background Papers: None.
Appendices: 1. Capital Programme 2018-19 - Q2 Budget Outturn and Update on Progress to 31/10/18.
1. Voids
1.1Quarter 2’s performance was 15 working days on average for normal void turnaround which remains below the target of 20 working days. During this period there were 9 properties re- let under the category of a normal void. There were 2 further properties which required major works taking an average of 43.5 days each. The number of void properties remains low.
2. Tenancy Agreement
2.1Preparation of the required notice for consultation is continuing. A draft table of changes has been prepared and is now being considered from a legal perspective to ensure we comply with all necessary statutory provisions. The current target is to commence consultation in December 2018.
3. Homelessness
3.1Homeless presentations have increased since April 2018. Staff must now adhere to the new administrative burdens imposed on the Council by the Homelessness Reduction Act 2017. There has been a trend in cases becoming complex to investigate and manage as other agencies and support services reduce. As an example the Council is now finding itself regularly accommodating people who we consider lack the essential skills for independent living but whom we are assured do not meet the threshold for statutory support services from health and social care authorities. Hence staff time is being absorbed in dealing with sorting out the problems that arise in temporary accommodation because a larger than expected proportion of customers lack resilience and coping skills. A subset of these customers require the level of support and assistance in day to day living which falls outside of the remit of the Housing Options team.
3.2The Homeless Reduction Act 2017 has been in force since April 2018 and in that time 198 homeless applications have been made.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme 2018-19 Q2 Budget Outturn and Update on Progress to 31/10/18Appendix 1 | 52 KB | Download |
PDF |
Community Services Update (Q2 2018/19)Report | 83 KB | DownloadRead as text |
Follow Service Delivery Committee at Oadby and Wigston and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Minutes of the Previous MeetingRESOLVED THAT: The minutes of the previous meeting held on 9 June 2026 be taken as read, confirmed and approved. | Approved | Open |
| 1 Sep 2026 | Action List Arising from the Previous MeetingRESOLVED THAT: The action list from the previous meeting held on 09 June 2026 be noted. | Noted | Open |
| 1 Sep 2026 | Corporate Performance Update (Q1 2026/27)RESOLVED THAT: The performance of the Council against its Corporate Objectives in delivering services be noted. Counc... | Noted | Open |
| 1 Sep 2026 | Housing Management Performance and Compliance (Q1 2026/27)RESOLVED THAT: The content of the report and appendices be noted. | Noted | Open |
| 9 Jun 2026 | Apologies for AbsenceRESOLVED THAT: Councillor K J Loydall be appointed as Vice-Chair for the duration of this meeting only. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.