Land at Horsewell Lane, Wigston and Options to Increase the Council’s Housing Stock

Noted Committee 1 paper

AI summaryOadby and Wigston sub-committee agrees to sell Horsewell Lane land on the open market and continue buying homes using Right to Buy receipts rather than starting new council house building projects.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedKeep buying properties with Right to Buy money
Moneycirca £90,000 expected receiptPlus £78,500 already spent on the project
What happens nextDispose of Horsewell Lane siteContinue property purchases through Right to Buy
Who it affectsCouncil tenants and housing applicantsHRA budget and housing stock growth

What was decided

The council will dispose of the land at Horsewell Lane on the open market, with the capital receipt used first to cover investigation costs and the rest going to the Housing Revenue Account. Report P7

Members noted the options of either starting a development at Paddock Street car park in Wigston or continuing to buy properties using Right to Buy receipts. Report P9, 3.1

The committee agreed to carry on purchasing properties, including new builds bought off plan, using Right to Buy money, and approved no development projects at this time. Report P9, 4.2, 4.3

Why

An April 2024 business case for 7 modular homes on the site was overtaken by changes in Right to Buy rules, fewer modular construction contractors, and a £2.14m capital cost seen as marginal for the council. Report 1.1, 1.2, 2.3, 2.4, 2.5

Selling the land on the open market without planning permission was judged best value after reviewing options including doing nothing, selling with permission, leaseback, gift and leaseback, council housing development, temporary homeless accommodation, and a leisure option next to the park. Report 2.7, P43, P44, P45, P46, P47, P48, P49

Government rule changes now let the council spend all of its Right to Buy receipts on buying properties until 31 March 2026, making property purchase a lower risk route to grow the housing stock than a major new build scheme. Report 1.6, 4.1, 4.2

What happens next

Officers will arrange the open market sale of Horsewell Lane and obtain an up-to-date valuation to confirm the likely circa £90,000 receipt. Report P52, 2.9

The council will continue buying homes, including new build properties off plan, using Right to Buy receipts, with a fallback option of supplementing this with HRA capital borrowing if needed. Report 4.2, 4.3

The Paddock Street car park development is held back; any future progress would need Homes England grant, planning permission, and further reports to the sub-committee at key milestones. Report 3.4, 3.5, 3.6, 3.9, P64

The money

  • circa £2.14m ex VAT Original Horsewell Lane development budget before the scheme was paused Report 2.2
  • £2.4m Original approved budget for the scheme in February 2022 Report 2.2
  • £78,500 Spent on the Horsewell Lane project to date, paid by the HRA Report 2.10
  • circa £90,000 Indicative receipt from open market sale of the Horsewell Lane land, subject to fresh valuation Report P52, 2.9
  • circa £3m (including 20% contingency but excluding VAT) Early estimate of capital investment needed to develop the Paddock Street car park site Report 3.3
  • circa £155k (including contingency) Cost of professional fees and surveys to take Paddock Street to a full planning application and contractor procurement, based on May 2025 costs Report 3.7
  • £1.42 million Right to Buy receipts held in reserve by the council as at 1 April 2025 Report 4.1

Options considered

  • Rejected: Do nothing with the Horsewell Lane site. Does not realise any benefit for the HRA Report P43
  • Chosen: Sell the Horsewell Lane site on the open market without planning permission. Best value after review, provides a capital receipt to the HRA and frees up development to more suitable sites Report P43, 2.9
  • Rejected: Sell the Horsewell Lane site with planning permission. Higher sale price would not outweigh design and planning costs and would delay the sale Report P44
  • Rejected: Sell the Horsewell Lane site and lease back a property on it. Low development potential and significant ongoing revenue costs for the lease Report P45
  • Rejected: Gift the Horsewell Lane land and lease back a property. More attractive to developers than a sale and leaseback but still not best value for the council Report P46
  • Rejected: Develop the Horsewell Lane site for council housing. Limited number of units, changes in homelessness need, and changes in the construction sector mean better value on other sites Report P47, 2.8
  • Rejected: Use the Horsewell Lane site for temporary homeless accommodation. Other sites could offer better economies of scale and value Report P48
  • Rejected: Use the Horsewell Lane site for a leisure option next to the park. Site is not large enough to deliver significant new facilities Report P49
  • Rejected: Initiate a development project at Paddock Street car park to build new council properties. Noted as an option but no development projects approved at this time; scheme would need Homes England grant and carries significant risk and officer time costs Report P9, 3.1, 3.4, 3.6, P66
  • Chosen: Continue purchasing properties using Right to Buy receipts, including new build off plan. Significantly lower risk than a major development and makes use of Right to Buy flexibility until 31 March 2026 Report P9, 1.6, 4.1, 4.2, 4.3

Implications

  • Financial: The HRA will receive a capital receipt from the sale of Horsewell Lane land, first used to repay the £78,500 already spent investigating the site. Report 2.10, P7
  • Financial: Property purchases will be funded from £1.42 million of Right to Buy receipts held in reserve, with HRA capital borrowing available as a supplement if needed. Report 4.1, 4.2
  • Risk: A Paddock Street development would need significant upfront revenue spend on planning and procurement, with no guarantee of Homes England grant even after planning approval. Report 3.6, 3.7, P66
  • Risk: Government flexibility to spend Right to Buy receipts on property purchases is only confirmed until 31 March 2026. Report 1.6, 4.1
  • Staffing: A building project would take up a significant amount of officer time that could otherwise go to improving services for existing tenants. Report P66
  • Equalities: Equalities assessment is not applicable at this stage, with no equalities implications identified in the report. Report P18
  • Legal: Officers report no legal, human rights, or health and safety implications arising from the report. Report P15, P19, P20

Who and where

  • The HRA and the council's wider housing finances Report P7, 2.10, 4.1
  • Existing council tenants, who could see officer time redirected to services rather than a major building project Report P66
  • Households on the housing waiting list, particularly those needing social housing of 2 and 3 bedroom properties and bungalows that the modular scheme would have offered Report 1.1, P47
  • People experiencing homelessness in the borough, given the assessed need for that type of accommodation Report P47, P48
  • Wigston residents and businesses near Paddock Street car park, since any future scheme there would require a tenant and community consultation Report 3.1, 3.2, 3.7

Timeline

  • February 2022: Original budget of £2.4m approved for the Horsewell Lane scheme Report 2.2
  • 16 April 2024: Business case approved for 7 modular housing units at Horsewell Lane Report 1.1, 2.1
  • 17 December 2024: Update to Capital Project Sub Committee on funding change and shift from modular to traditional construction Report 1.3, 2.5
  • 1 April 2025: Council held £1.42 million Right to Buy receipts in reserve Report 4.1
  • 27 November 2025: Capital Project Sub Committee agreed to sell Horsewell Lane land and continue buying properties with Right to Buy money Report P1
  • 31 March 2026: Current end date for the Government rule allowing Right to Buy receipts to be spent on buying properties Report 1.6, 4.1

Plain English for the jargon

  • HRA: Housing Revenue Account, the ring-fenced account councils use for income and spending on their own housing stock
  • Right to Buy receipts: Money the council keeps when a council tenant buys their home under the Right to Buy scheme, which must be used for housing purposes under set rules
  • Capital receipt: Income from the sale of a capital asset such as land or buildings
  • Modular construction: A building method where homes are made from factory-built sections that are then assembled on site
  • Homes England: The Government agency that funds new affordable housing
  • JCT Design and Build: A standard UK construction contract where a contractor takes on design responsibility and builds the project to an agreed brief
  • Levelling Up Fund: A UK Government fund for local infrastructure projects, including the Walkable Wigston bid that included the Paddock Street site
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item31

Resolved

RESOLVED THAT: i) The Council dispose of the land at Horsewell Lane on the open market; ii) The capital receipt arising from the sale be used to offset costs incurred to date in relation to investigating the development potential of the site, with the remainder acting as a capital receipt to the HRA; iii) The options to either initiate a development project at the existing car park site at Paddock Street in Wigston in order to build new properties or to continue purchasing properties using right to buy monies be noted; and iv) The option of continuing to purchase properties (including the option of buying new build off plan) using right to buy monies be agreed and no development projects be approved at this time.
Word for word from the decision Oadby and Wigston published for this meeting. Source: moderngov.oadby-wigston.gov.uk

Follow this further

Built from Oadby and Wigston's papers

What the report saysPro

Report to Capital Projects Sub-Committee

Matter for Capital Project Sub Thursday, 27 Information and Committee November 2025 Decision

Report Title: Land at Horsewell Lane, Wigston and Options to Increase the Council’s Housing Stock

Report Author(s): Adrian Thorpe (Head of The Built Environment)

Purpose of Report: This report relates to the Business Case that has been approved with regard to the vacant land at Horsewell Lane in Wigston and the previous report to CPSC in December 2024.

Report Summary: An overview of the options available for the Horsewell Lane Site with a recommended preferred option together with an analysis of options to increase housing stock in the Borough.

Recommendation(s): Horsewell Lane

A. The Council disposes of the land at Horsewell Lane on the open market; B. The capital receipt arising from the sale is used to offset costs incurred to date in relation to investigating the development potential of the site, with the remainder acting as a capital receipt to the HRA;

Options to Increase the Council’s Housing Stock

C. That Members note the options to either initiate a development project at the existing car park site at Paddock Street in Wigston in order to build new properties or to continue purchasing properties using right to buy monies; and D. That taking all of the factors into account as set out in the report, Members agree to the option of continuing to purchase properties (including the option of buying new build off plan) using right to buy monies and do not proceed with any development project at this time.

Senior Leadership, Teresa Neal (Strategic Director) Head of Service, (0116) 257 2642 Manager, Officer and [email protected] Other Contact(s): Adrian Thorpe (Head of the Built Environment) (0116) 257 2645 [email protected]

Chris Eyre (Housing Manager) (0116) 257 2726 [email protected]

Strategic Objectives: Our Council (SO1) Our Communities (SO2) Our Economy (SO3) Our Environment (SO4)

Vision and Values: "Our Borough - The Place To Be” (Vision) Customer & Community Focused (V1) Proud of Everything We Do (V2) Collaborative & Creative (V3) Resourceful & Resilient (V4)

Report Implications:-

Legal: There are no implications arising from this report.

Financial: The implications are as set out in the report.

Corporate Risk Decreasing Financial Resources / Increasing Financial Pressures (CR1) Management: Effective Utilisation of Assets / Buildings (CR5) Organisational / Transformational Change (CR8) Economy / Regeneration (CR9)

Equalities and Equalities There are no implications arising from this report. Assessment (EA): EA not applicable at this stage.

Human Rights: There are no implications arising from this report.

Health and Safety: There are no implications arising from this report.

Statutory Officers’ Comments:-

Head of Paid Service: The report is satisfactory.

Chief Finance Officer: The report is satisfactory.

Monitoring Officer: The report is satisfactory.

Consultees: None.

Background Papers: None.

Appendices: None.

1. Introduction

1.1A business case was prepared for the proposed development of Horsewell Lane site that identified a preferred option to construct 7 modular housing units on the site for Social Housing (a mixture of 2 & 3 bedroom properties and a bungalow). This was presented to Council and approved in April 2024.

1.2Following the submission of the business case, there have been changes to the project funding source and given the nature of the development it was also suggested that traditional construction methods would be more suitable for the development.

1.3An update that reflected the above was presented to Capital Project Sub Committee on 17th December 2024. 1.4 Given the relatively high capital expenditure for the scheme (circa £2.14m ex VAT) CPSC requested a further options appraisal be carried out for the Horsewell Lane site to ensure that the Council was receiving ‘best value’ for the investment.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Land at Horsewell Lane, Wigston and Options to Increase the Council’s Housing StockReport 221 KB DownloadRead as text

At this meeting

Whole meeting
31Land at Horsewell Lane, Wigston and Options to Increase the Council’s Housing StockThis decision

Who was there

5 of 10 attended
SB
Samuel BallOfficer, in attendance
LA
Councillor Lee A BentleyCommittee Member, present
JK
Councillor Jasvir K ChohanCommittee Member, present as substitute
JK
Councillor John K FordCommittee Member, present
SZ
Councillor Samia Z HaqChair, present
P(
Councillor Pritibala (Priti) JoshiCommittee Member, in attendance
CJ
Councillor Carl J R MartinCommittee Member, apologies, sent representative
AT
Adrian ThorpeOfficer, in attendance
CA
Councillor Carl A M WalterCommittee Member, absent
SW
Sebastian WheelikerClerk, in attendance

More from Oadby and Wigston Capital Projects Sub-Committee

All decisions
MeetingDecisionOutcome
17 Dec 2024 Wednesday, 30 August 2023RESOLVED THAT: The minutes of the previous meeting held on 30 August 2023 be taken as read, confirmed and approved. Approved Open
17 Dec 2024 Exclusion of Press and PublicRESOLVED THAT: The press and public were excluded from the remainder of the meeting in accordance with Section 100(A)... Decided Open
17 Oct 2024 Exclusion of Press and PublicRESOLVED THAT: The press and public be excluded from the remainder of the meeting in accordance with Section 100(A)(4... Decided Open
30 Aug 2023 Office Relocation Project ClosureRESOLVED THAT: The content of the report be noted. Noted Open
30 Aug 2023 Exclusion of Press and PublicRESOLVED THAT: The press and public were excluded from the remainder of the meeting in accordance with Section 100(A)... Decided Open