Resolved
RESOLVED THAT: The content of the report be noted.
AI summaryOadby and Wigston Licensing and Regulatory Committee noted the Year 1 output report for the Warm Homes: Local Grant, which recorded £130,388 spent and 11 private homes upgraded with 31 measures installed.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED THAT: The content of the report be noted.
Licensing and Thursday, 18 June Matter for Regulatory Committee 2026 Information
Report Title: Warm Homes: Local Grant - Year 1 Output Report (April 2025 - March 2026)
Report Author(s): Baljit Rakkar (Grants Project Officer)
Purpose of Report: To provide Members with the outcome of Year 1 of Warm Homes: Local Grant
Report Summary: The report outlines the number of measures installed in Private Homes across the Borough between the period of April 2025 & March 2026.
Recommendation(s): That the content of the report be noted.
Senior Leadership, Colleen Warren (Chief Finance Officer / Section 151 Officer) Head of Service, (0116) 257 2759 Manager, Officer and [email protected] Other Contact(s): Minna Scott (Environmental Health Manager) (0116) 257 2779 [email protected]
Ben Clark-Monks (Selective Licensing Team Leader) (0116) 257 2883 [email protected]
Baljit Rakkar (Grants Project Officer) (0116) 257 2613 [email protected]
Strategic Objectives: Our Council (SO1) Our Communities (SO2) Our Environment (SO4)
Vision and Values: "Our Borough - The place to be" (Vision) Excellence - We strive to work to a high standard and deliver high quality services (V2) Accountability - We do what we say and take responsibility for our actions (V3) Customer Focused - We do the best for our customers (V4)
Report Implications:-
Legal: There are no implications arising from this report.
Financial: The implications are as set out at paragraph(s) 1.3, 2.3, 2.4 and 3.1 of this report.
Corporate Risk Decreasing Financial Resources / Increasing Financial Pressures (CR1) Management: Key Supplier / Partnership Failure (CR2) Reputation Damage (CR4) Economy / Regeneration (CR9) Increased Fraud (CR10)
Equalities and Equalities There are no implications arising from this report. Assessment (EA): EA not applicable
Human Rights: There are no implications arising from this report.
Health and Safety: There are no implications directly arising from this report.
Statutory Officers’ Comments:-
Head of Paid Service: The report is satisfactory.
Chief Finance Officer: The report is satisfactory.
Monitoring Officer: The report is satisfactory.
Consultees: None.
Background Papers: None.
Appendices: None.
1. Background of Project
1.1The Warm Homes: Local Grant is a UK Government-funded fuel poverty scheme, funded through the Department for Energy Security and Net Zero (DESNZ) and delivered by Local Authorities in England. The scheme aims to improve the energy efficiency of homes and increase low carbon heating installations for low-income households.
1.2The scheme opened in April 2025 and will allocate £500 million to 73 projects across 270 local authorities over the next three years, with delivery ending in March 2028.
1.3Oadby & Wigston Borough council secured just over £940,500 for Warm Homes Local Grant for the term of the project.
2. Year One Performance and Results
2.1Procurement commenced in July 2025 following the provision of the grant funding agreement from the Midlands Net Zero hub, with separate contracts being awarded and signed in January 2026 for retrofit assessment and installation, following best practice guidance from the Midlands Net Zero Hub in relation to installation scrutiny.
2.2Delivery commenced in January 2026 with works required to be completed by 31 March 2026 to coincide with ending of the 25/26 financial year as mandated by DESNZ.
2.3The initial delivery budget for year 1 was £100,000, which was overachieved and a total of £130,388 grant funding was spent.
2.4Overachieving this budget allowed additional funding to be secured equating to £30,388 to support year 1 installations beyond the initial budget scope.
2.5This equated to 11 homes being upgraded to an EPC rating of C and or above and installation of a total of 31 measures. A breakdown of the measures installed is below. 2.6 Measures Installed
Solar Photovoltaic Array (Solar PV) 10
Ventilation 9
Loft Insulation 10
Cavity Wall Insulation 1
High Retention Storage Heaters 1
Total 31
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Warm Homes: Local Grant: Year 1 Output ReportReport | 193 KB | DownloadRead as text |
Follow Licensing & Regulatory Committee at Oadby and Wigston and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2026 | Minutes of the Previous MeetingRESOLVED THAT: The minutes of the previous meeting held on 5 March 2026 be taken as read, confirmed and approved. | Approved | Open |
| 18 Jun 2026 | Action List Arising from the Previous MeetingRESOLVED THAT: The Action List arising from the previous meeting held on 5 March 2026 be noted. | Noted | Open |
| 18 Jun 2026 | Parkland Primary School Air Quality EvaluationRESOLVED THAT: i) The positive outcomes from the Parklands Primary pilot be noted; ii) Continued partnership working ... | Noted | Open |
| 18 Jun 2026 | Food Safety Annual Service Plan (2026/27)RESOLVED THAT: The content of the report and appendix be noted. | Noted | Open |
| 5 Mar 2026 | Minutes of the Previous MeetingRESOLVED THAT: The minutes of the previous meeting held on 4 December 2025 be taken as read, confirmed and approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.