RESOLVED that 1. the report be noted; 2. a review be undertaken for those schemes which require continued funding to be done as part of the system wide budgeting and financial prioritisation process, the outcome of this process being reported to this Board in due course.
Word for word from the decision Oldham published for this meeting.Source: committees.oldham.gov.uk
Report Author: Ben Galbraith, Chief Finance Officer, Oldham CCG
Reason for the decision: To provide an update to Commissioning Partnership Board on work undertaken to date to evaluate the impact of schemes funded from the GM Transformation Funds and agree the next steps on evaluation work.
Summary: The purpose of the report is to outline the national funding arrangement changes that have taken place in 2020/21 affecting the GM Transformation Fund and Oldham’s allocation.
The paper sets out a financial update for 2020/21 and sets out next steps to allow the Commissioning Partnership Board to consider funding as part of the system wide budgeting and financial prioritisation process for 2021/22.
What are the alternative option(s) to The approach being taken is to ensure those be considered? Please give the schemes viable for taking forward will be reason(s) for recommendation(s): considered for funding in 2021/22 once funding arrangements are confirmed.
To continue with no assessment of the schemes for 2021/22, means one of three alternative options for the schemes: a) all schemes end; b) funding is found from existing budgets in the context of existing commissioned services; or c) there is an increase in the financial deficit of the Oldham system.
Recommendation(s): The Commissioning Partnership Board is asked to:
note the contents of the report; and
agree that a review will be undertaken for those schemes which require continued funding. This will be done as part of the system wide budgeting and financial prioritisation process. The outcome of this process will be the subject of a further report in due course to the CPB.
Implications:
What are the financial implications? Funding guidance has been delayed for 2021/22 and whilst early indications assume funding for April – June 2021 will continue on the same basis as 2020/21, assessment of schemes need to take place and factored into the financial prioritisation process otherwise it risks a pressure to the financial situation in the system.
What are the procurement There may be procurement implications should implications? any schemes and new business cases be approved, but these are not covered in the scope of this report.
What are the legal implications? There may be legal implications should any schemes and new business cases be approved, but these are not covered in the scope of this report.
What are the Human Resources There may be HR implications should schemes implications? and new business cases be approved, but these are not covered in the scope of this report.
Equality and Diversity Impact EIAs were completed for those schemes Assessment attached or not required approved. Further EIAs would be completed for because (please give reason) any new business cases approved.
What are the property implications There may be property implications should schemes and new business cases be approved, but these are not covered in the scope of this report. Risks: Financial Risk: If the Oldham locality does not identify recurrent funding sources for services which have historically been funded from the GM Transformation Fund going forward, then Oldham may risk losing some services which are needed due to a lack of funding or continuing with schemes that have no case for continuation and placing a greater financial pressure on the Oldham system.
Has the relevant Legal Officer confirmed that the Yes recommendations within this report are lawful and comply with the Council’s Constitution/CCG’s Standing Orders?
Has the relevant Finance Officer confirmed that any Yes expenditure referred to within this report is consistent with the S.75 budget?
Are any of the recommendations within this report contrary to No the Policy Framework of the Council/CCG?
Reason(s) for exemption from publication: None
Reason why this Is a Key Decision Not applicable
(
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.