Mazars LLP External Audit Recommendations

Agreed Finance 1 paper

Audit Committee agreed this item on Tuesday 2 November 2021. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

It was agreed with the Council and Unity Partnership that an action plan would be put in place to ensure that all reconciliations were undertaken in a timely manner. · The consolidation of the Council’s group entities - As part of the closedown process for 2021/22, the Council had included additional checks and reconciliations in its closedown timetable to ensure that all transactions and reconciling items were matched between the Council, MioCare CIC and Unity Partnership Ltd. · IT general controls associated with access to Agresso – The Council would review the sign on arrangements for non-Single Sign On (SSO) users whilst migrating as many users as possible over to SSO. Password controls would be tightened up for non-SO users so that passwords would expire after 90 days. The Agresso functionality in relation to password security would also be reviewed to determine whether enhanced controls could be mandated to non-SSO users. · The IT Service Continuity Plan – there was an active IT disaster Recovery procedure in place held by Unity IT that would see the restoration of IT services in a catastrophic event This plan would be linked to the overall Business Disaster Recovery Plan. The recovery would see a complete rebuild of infrastructure, which is then populated with the data back-ups. Where required, Service Continuity Plans would be invoked while the infrastructure was being restored. The current disaster recovery solution could not easily be tested outside of assuring the quality of data back-ups. However, the process was under change as part of the migration to Cloud/ SaaSbased solutions. This would see the high availability and a more robust disaster recovery solution in place for Agresso and all other Council systems. RESOLVED that: 1. the responses to the recommendations highlighted by the Council’s external auditors, Mazars LLP, in the draft Audit Completion Report and subsequent letter entitled ‘Conclusion of Pending Matters – Audit Completion Report be noted. 2. how the Council has implemented the recommendations be noted.
Word for word from the decision Oldham published for this meeting. Source: committees.oldham.gov.uk

Follow this further

Built from Oldham's papers

What the report saysPro

Report to Audit Committee

Reason for decision

Following the 2020/21 Statement of Accounts audit, the Council’s external auditors, Mazars LLP, made recommendations in the draft Audit Completion Report (ACR) and subsequent letter entitled ‘Conclusion of Pending Matters – Audit Completion Report. In line with best practice principles, the Council has implemented the recommendations for inclusion in the workplan for 2021/22 and as part of the preparation of the Council’s 2021/22 Statement of Accounts.

Executive summary

The report sets out the Council’s response to the recommendations highlighted in the Mazars LLP draft Audit Completion report for 2020/21 and subsequent letter entitled ‘Conclusion of Pending Matters – Audit Completion Report. There are 4 recommendations in total, one relating to the Housing Benefit reconciliation to the General Ledger, one on the consolidation of the Group Accounts and two recommendations are from the conclusion of the work on the IT audit.

Recommendations

It is recommended that the Audit Committee notes:

a) the responses to the recommendations highlighted by the Council’s external auditors, Mazars LLP, in the draft Audit Completion Report and subsequent letter entitled ‘Conclusion of Pending Matters – Audit Completion Report. b) how the Council has implemented the recommendations. Audit Committee 2 November 2021

Background

1.1This report presents the Council’s response to the recommendations highlighted in the 2020/21 draft Audit Completion Report and subsequent letter entitled ‘Conclusion of Pending Matters – Audit Completion Report provided by the Council’s external auditors, Mazars LLP, on completion of the 2020/21 Statement of Accounts audit.

1.2The audit work identified some minor matters which resulted in four low priority recommendations. The four recommendations related to:

• Housing Benefit system to General Ledger reconciliations • The consolidation of the Council’s group entities • IT general controls associated with access to Agresso • The IT Service Continuity Plan

1.3The Councils response to these recommendations is set out in sections 2 to 5.

2. Housing Benefit System to General Ledger reconciliations

2.1As part of the interim audit in August 2020, Mazars LLP, requested the Housing Benefit system to General Ledger reconciliations. When the reconciliations were received, they noted that the reconciliations for the period August 2020 to March 2021 were all completed in March 2021, in the case of August 2020, 7 months after the period end.

2.2The potential impacts for the Council, are that imbalances are not identified in a timely manner and that there are unexplained items that do not have an adequate investigation. This could lead to difficulty in identifying and clearing any reconciling items and any discrepancies are not able to be rectified in a timely manner and any unusual activity is not identified. Mazars LLP recommended that the Housing Benefit system is reconciled to the General Ledger on a prompt monthly timetable within an agreed time frame from month end.

2.3The Council has reviewed and updated the Housing Benefit reconciliation timeframe. The Council’s officers and colleagues from The Unity Partnership Ltd have agreed an action plan to ensure that all reconciliations are undertaken in a timely manner.

3. The Consolidation of the Council’s Group Entities

3.1When completing the Group accounts audit work, Mazars LLP identified that the Council’s closedown arrangements for the consolidation of its group entities includes a process to identify transactions and balances within the group entities. This involves interrogating the Council records to identify transactions and balances however, it does not include interrogation of the MioCare CIC and Unity Partnership Ltd accounts.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Mazars LLP External Audit RecommendationsReport 868 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 15 attended
AR
Anne RyansOfficer, in attendance
MS
Mark StensonOfficer, in attendance
CS
Constitutional ServicesSecretary, expected
KM
Karen MurrayOfficer, in attendance
RA
Riaz AhmadCommittee Member, present
MA
Mohammed AlyasCommittee Member, present
NB
Norman BriggsCommittee Member, apologies
PD
Peter DeanCommittee Member, present
CG
Chris GlosterCommittee Member, present
MN
Mohammed Nazrul IslamVice-Chair, present
LL
Luke LancasterCommittee Member, apologies, sent representative
AA
Ali Aqueel SalamatCommittee Member, present

All 15 on the meeting page

On this subject at Oldham

Search all
  1. Mazars LLP External Audit RecommendationsThis decision
  2. Public Sector Audit Appointments - Confirmation of Mazars LLP as the Council's External Auditor for 2023/24 to 2027/28.Decided

More from Oldham Audit Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 MinutesThat the of the meeting of the Audit Committee, held 26 th Manch 2026, be approved as a correct and the accompanying ... Approved Open
22 Jul 2026 Members' Allowances UpdateThat the Audit Committee notes ... view the full minutes text for item 6. Decided Open
22 Jul 2026 Audit Strategy MemorandumThat the report be noted. Noted Open
22 Jul 2026 Draft 2025/26 Annual Statement of AccountsThat the Council’s draft Statement of Accounts for 2025/26, be noted. Noted Open
22 Jul 2026 Treasury Management Review 2025/26That the Audit Committee notes and endorses the Treasury Management Outturn report and the Treasury Management activi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies