RESOLVED – That the sub-committee agreed to the recommendations of the advisory panel with three amendments: 1. Application 3 - Fully repair the ongoing issues within the OBA Millennium Cultural Centre: The sub-committee agreed to the panel recommendations that £50,000 be provided from the Fund. They specified however that the funds should be used for necessary health and safety improvements rather than other items, including fire doors, the leaking roof, lighting and toilets. 2. Application 13 – Salmon Fields Highway Improvement: The sub-committee decided to fund this project with the full £25,000 requested, rather than find the final £5,000 from other sources 3. Application 18 – Refurbish Progress Community Hub: The sub-committee chose to reject this project on the basis that the community benefit was unclear and therefore the Local Improvement Fund was not the appropriate funding source for the project. 4. As ... view the full minutes text for item 7.
Word for word from the decision Oldham published for this meeting.Source: committees.oldham.gov.uk
Local Improvement Fund 2021/22: Cross-Party Advisory Panel Recommendations
Amount Advisory Panel Feedback Requested Panel Recommend ation Central Application 1 – Creating a wildlife £28,835 FUND Overall a positive application, creating a community space, helping residents sanctuary at Sickle Street engage with wildlife.
Application 2 – Update the £65,000 DO NOT FUND The panel agreed that the application required additional design work. outdated weather pitch / astro It would also be helpful to consider what the wider use of the grounds may be. turf on West End Street The panel raised concerns about the use of match funding that hasn’t been secured yet, adding risk to the successful delivery of the project. The panel recommended the application be deferred to a future funding round, so the concerns raised can be fully answered.
Application 3 – Fully repair the £37,500-£108,200 FUND There are some financial figures included in the application, though it is not ongoing issues within the OBA (Advisory Panel clear how they break down, or the link between the different elements of the Millennium Cultural Centre recommend bid and the benefits providing £50,000 The panel agreed that the project was important for the local community so LIF funding) proposed allocating £50,000 to the project to enable the delivery of urgent works.
East Application 4 – Refurbishing £56,310 FUND The panel agreed that it was important to ensure a fair allocation of funding existing street furniture and between the two parks, based on the priorities outlined in the funding community notice boards at applications. This needs to be agreed by ward members. Stoneleigh and Whitehall Lane parks
Application 5 – Saddleworth £60,587-£79,502 DO NOT FUND The Advisory Panel felt that the project had merit. However, they felt that the Historical Society Holly Bank level of benefit compared to cost was lower than other projects and therefore Project would not be as impactful.
1 They recommended that the project be looked at again in future if more LIF funding were available.
Application 6 – Carry out £18,410 FUND The panel recognised the positivity of the project, especially as the group have essential repairs to Friezland already actively sought other funding to support the delivery of the project. arena The panel felt that the application was incredibly positive, helping refurbish a well-used community asset.
Application 7 – Deliver £22,930 FUND The panel agreed that this was a positive application, recognising that improvements to child safety and improvements would lead to greater child safety in the area. road congestion along Rowland Way and Medlock Way
Application 8 – Repairs and £10,000 FUND The panel agreed that the refurbishments would help to continue providing an refurbishment of Springhead important community facility, so recommended allocating funding, Community Centre
Application 9 – Belmont Ave. £35,200 DO NOT FUND The panel agreed that the application has merit but raised concerns about open space improvements funding. Could grant funding be explored to support the bid? The panel agreed that if this is a safety issue (the path is unsafe), it should not be funded by the LIF. It is recommended that Members discuss with Highways, so a safety assessment can be undertaken.
If the pathway improvement element of the project was removed, the remaining application would be Revenue and not eligible for the LIF.
The panel recommended seeing if Pocket Park funding be explored. Officers were requested to provide feedback directly to the applicant, so that other funding sources could be considered, including a future bid to the LIF if appropriate.
Application 10 – Lydgate Leaving £20,000 FUND The panel agreed that the application was well developed, and welcomed the Lockdown additional funding secured from a range of other sources to supplement the funding from the LIF.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Consideration of LIF Bids 2023/24RESOLVED – 1. That the foll owing requests for funding from Districts were considered and determined as follows: Appl...
Consideration of LIF Bids 2023/24RESOLVED – That The following requests for funding for East District were considered and agreed: 2. LEES RBL - £500 a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.