DECISION: That the application be GRANTED subject to the conditions as outlined in the report and the late list. NOTES: In reaching its decision, the Committee took into consideration the information as set out in the Late List attached at Item 9.
Word for word from the decision Oldham published for this meeting.Source: committees.oldham.gov.uk
2.1It is recommended that the application be approved subject to the conditions set out in this report and that the Head of Planning shall be authorised to issue the decision following the completion of a Section 106 agreement requiring the payment of a sum of £38,700 for the cost of planting replacement trees, as well as a contribution of £8,800 to compensate for the loss of biodiversity.
3. SITE DESCRIPTION
3.1The almost square shaped site measures approx. 0.66 ha and is located on the southern side of Greenside Way, Greengate Industrial Estate, Chadderton. It is currently vacant and forms part of lands allocated for Business and Employment Uses within the Oldham Local Plan.
3.2The site is relatively flat in terms of topography and there are some mature trees on the site. The general area is characterised by commercial uses of various types, reflecting the allocation of the land within the Local Plan and to the south of the site is a golf course. The site would be accessed via a new access point off Greenside Way. 4. THE PROPOSAL
4.1The application proposes the erection of 3no. E(G)/B2/B8 blocks (comprising 24no. hybrid units) and formation of a new access onto Greenside Way, together with external works, landscaping, and creation of a substation and meter rooms.
4.2Two of the three blocks (Type B) would be centrally located within the site while the third block (Type A) would be sited adjacent the southern site boundary. Each of the blocks would cover approx. 13m x 56m in area with an overall height of approx. 9m. In terms of external finish materials, each block would have its walls built using a combination of facing brick and artificial stone while the roof would be covered with interlocking concrete roof tiles.
4.3The proposal includes the erection of two meter rooms, each of which would cover an area of approx. 3m x 3m with a height of approx. 2.9m.
4.4The substation would cover an area of approx. 4.2m x 3.1m with a height of approx. 2.9m while the bin store would cover an area of approx. 10m x 3m with a height of approx. 1.85m. The cycle store on the other hand would cover an area of approx. 3m x 5.5m with a height of approx. 2.4m.
4.5The site would be accessed via a new access to be sited adjacent the north-eastern section of the site.
5. PLANNING HISTORY
5.1The site was part of a larger site where permission was granted under planning ref. FUL/348818/22 for the erection of two buildings with combined floorspace of 7,540m² GEA / 7,308m² GIA to be used in any combination of Use Class E(g)(i)(ii)(iii) (offices, research and development, light industrial), Use Class B2 (general industrial) and / or Use Class B8 (storage / distribution), with associated parking and refuse storage on 28th February, 2023.
6. RELEVANT PLANNING POLICIES
6.1The adopted Development Plan is the Joint Development Plan Document (Local Plan) which forms part of the Local Development Framework for Oldham. The site is allocated in the Proposals Map associated with this document for Business and Employment Use. As such, the following policies are considered relevant to the determination of this application:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.