Resolved
RESOLVED that the information as contained in the late list be noted.
Planning Committee noted this item on Wednesday 4 June 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the information as contained in the late list be noted.
PLANNING COMMITTEE 4th June 2025 Late information
AGENDA PAGES DETAILS
9 - 26 AGENDA ITEM 6 FUL/353032/24 - Crompton And Royton Golf Club, High Barn Street, Royton
ADDITIONAL REPRESENTATIONS:
Following the publication of the Planning Committee agenda an additional representation has been received, which made the following additional comments:
The Officers’ Report does not address issues that had been raised.
Their comments had previously been summarised but they noted that the comments in regards the final line in the amenity section has been 'cut short' and should read '....there will not be any post- development off site flows onto lower third party land in these events'.
Whilst referenced, the comments have not been directly addressed in the report, and indeed the Lead Local Flood Authority (LLFA) have provided no comments on the application. The drainage strategy is not commented upon or summarised in the report.
There is no condition requiring the submission of a detailed drainage strategy, or providing any clear requirements of said strategy. This provides no confidence that the matter of drainage has been considered by the LPA, whether it is acceptable in planning policy terms, and whether it will impact the delivery of the remaining development at Cowlishaw. Therefore, all of their previous concerns remain.
On this basis, they strongly request that the application is presented to Planning Committee with the requirement for the submission of further details relating to drainage. To secure this and to ensure our concerns are addressed, they recommend that the following condition is included within an Update Report:
"Notwithstanding existing plans and prior to commencement of any development, a detailed surface water drainage scheme shall be submitted to the local planning authority for approval in writing.
The scheme shall include: a) confirmation of the permeability of the imported fill b) assessment and demonstration of whether all runoff will permeate through the upper layers of material or whether there will be a proportion of overland runoff during high rainfall events - evidence is to include calculated infiltration rates based on BRE 365 testing alongside drainage calculations to justify the proposals c) evidence regarding overland flood flows in extreme storm events to demonstrate that there will not be any off-site discharge onto lower third party land in these events in the post-development scenario."
As with previous comments, these comments are intended to be constructive and seek to ensure the proposal does not compromise the deliverability of the adjacent residential allocation.”
LLFA/Drainage Response:
Having considered the planning application, the LLFA have raised no objections to the proposals subject to the imposition of the following conditions:
1. The proposed development must proceed in strict accordance with the Flood Risk Assessment and the mitigation measures identified within it. REASON - To manage surface water runoff sustainably and to prevent increased flood risk, in accordance with Policy JP-S4 of the PfE and the NPPF.
2. No surface water and/or land drainage shall be allowed to connect directly or indirectly with the public sewerage network. REASON: To prevent overloading of the public sewerage system, to protect the health and safety of existing residents and ensure no pollution or detriment to the environment
3. Prior to use of the development, a Surface Water Validation Report that demonstrates that the drainage scheme and exceedance routes has been carried out in accordance with the approved documents must be submitted to the Local Planning Authority, including but not limited to, the following:
(a) Confirmation of infiltration rates should be provided
(b) A Topographical survey to verify the works have been completed to the agreed design (levels, contours and required import volume)
(c) Photographs thoroughout each stage of construction
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Late ListReport | 247 KB | DownloadRead as text |
Follow Planning Committee at Oldham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Aug 2026 | Election of ChairRESOLVED that Councillor Charters be elected Chair for the duration of the meeting. | Decided | Open |
| 19 Aug 2026 | Minutes of Previous MeetingRESOLVED that the minutes of the meeting held on 8 th July 2026 be approved as a correct record. | Approved | Open |
| 19 Aug 2026 | FUL/355703/26 - 45 - 49 Ripponden Road, Oldham, OL1 4EWThat the application be REFUSED for the following reason: “The proposed House in Multiple Occupation (HMO) would resu... | Refused | Open |
| 19 Aug 2026 | FUL/355368/25 - 74 Haigh Lane, Chadderton, Oldham, OL1 2TLThat the application be REFUSED for the reasons as set out in the report. NOTES: 1 . That Ward Members attended the m... | Refused | Open |
| 19 Aug 2026 | FUL/354250/25 - Street Bridge Inn, 230 Roman Road, Oldham, OL8 3QHThat the application be GRANTED subject to the conditions as outlined in the report, the amended condition 3 containe... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.