AI summaryOldham Audit Committee endorsed the Quarter 3 Internal Audit and Counter Fraud Progress Report for 2025/26 and asked future reports to include year-on-year comparisons, Greater Manchester benchmarking and limited-opinion follow-ups.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedQuarter 3 Internal Audit Progress Report endorsed with reporting changes.
Money£183,096.63 identifiedFraud, errors and overpayments found year to date.
What happens nextFuture quarterly reportsAdd prior year figures, GM benchmarking, limited-opinion updates.
Who it affectsCouncil audit assuranceAffects how Audit Committee monitors internal audit.
What was decided
The Audit Committee endorsed the Internal Audit Progress Report for Quarter 3 of 2025/26, covering October to December 2025. Report P6, 1.1
Future quarterly Internal Audit Progress Reports must include comparative figures from the same period in previous years, benchmarking against selected Greater Manchester authorities, and updates on areas that previously received limited audit opinions.
Why
The Audit Committee's Terms of Reference require it to review summary findings from internal audit and seek assurance that management action has been taken where needed. Report P1, P2
The report helps the Committee discharge those responsibilities alongside the Head of Audit and Counter Fraud's Annual Report and Opinion for 2025/26. Report P3
What happens next
Four reports on Miocare Supported Living, Home to School Transport (follow up), SEND Special School Placements and Oldham Total Care are being finalised with services and will be reported in due course. Report P5, P21, P22, 2.3
Work continues on Let Estate (follow up), Highways Maintenance, Waste Management and the Fostering Service, with outcomes to be reported later. Report P23, P24, 2.3
Further National Fraud Initiative results, including Single Person Discounts and Blue Badge cases, will be monitored and reported in future committee updates. Report 3.4, 3.5
The money
£183,096.63 Total financial outcomes from Counter Fraud, 1 April to 31 December 2025 Report P82
£62,282.33 Fraud and Error Overpayments from Corporate Cases, year to date Report P78
£106,257.54 CTR Fraud and Error Overpayments identified, year to date Report P81
£14,556.76 HB Fraud and Error Overpayments from CTR investigations, year to date Report P80
£11,656.32 Fraud, Error and Overpayments from Corporate Cases in Quarter 3 Report P31, P78
£6,069.80 HB Fraud, Error and Overpayments from CTR investigations in Quarter 3 Report P31, P80
£37,487.64 CTR Fraud, Error and Overpayments identified in Quarter 3 Report P31, P81
Options considered
Chosen: Accept and note the progress and performance of the Audit and Counter Fraud Team. Preferred option set out in the report Report P37, P38, 5.1
Rejected: Decline to accept the progress and suggest an alternative approach Report P37
Implications
Risk: The 2025/26 Audit and Counter Fraud Plan and each project's terms of reference were prepared using a risk-based approach. Report 11.1
Other: Several previously completed audits in 2024/25 and 2025/26 received Limited opinions, covering areas such as Direct Payments, Residential Care, Debt Recovery, IT Supplier Management, Cloud Service Management, Corporate Performance Management, Overtime, Children's to Adults Social Care Transitions, IT Physical Security, Children's Services Complaints and Payment Card Industry Data Security Standards. Report P70
Equalities: No Equality Impact Assessment was completed for this report. Report 17.1
Oldham Council Internal Audit and Counter Fraud Team Report P3, P4
Council directorates covered by reviews, including Corporate Resources, People, and Place Report P70
Services with reviews being finalised: Miocare Supported Living, Home to School Transport, SEND Special School Placements, Oldham Total Care Report P22, 2.3
Services with ongoing reviews: Let Estate, Highways Maintenance, Waste Management, Fostering Service Report P24, 2.3
Timeline
1 April 2025 to 31 December 2025: Period covered by the progress report Report 1.1, P75
Quarter 3 2025/26 (October to December 2025): One grant assurance review completed: Arts Council Grant for Northmoor Library Report 2.3, P19, P70
14 January 2026: Audit Committee meeting that endorsed the report Report P7
Plain English for the jargon
FFS: Fundamental Financial Systems reviews, which give assurance to support the Annual Financial Statements
CTR: Council Tax Reduction scheme, covering discounts and reductions for residents on low incomes
HB: Housing Benefit, paid to help people on low income with rent
NFI: National Fraud Initiative, a UK-wide data matching exercise run by the Cabinet Office to detect fraud and error
Limited opinion: Audit opinion where significant gaps, weaknesses or non-compliance were identified and improvement is required to the system of governance, risk management and control
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
That the Audit Committee endorsed the Internal Audit Progress Report, for Quarter 3 - 2025/26 (October – December). 2. That future quarterly Internal Audit Progress Reports should include comparative figures from corresponding periods from previous years, benchmarking against selected other authorities in Greater Manchester and updates on those areas that have received limited audit opinions.
Word for word from the decision Oldham published for this meeting.Source: committees.oldham.gov.uk
The Audit Committee’s Terms of Reference state that:
4.4.2 The Audit Committee shall: a) be responsible for oversight of the Council’s Internal Audit arrangements and will; (ii) review summary findings and the main issues arising from internal audit reports and seek assurance that management action has been taken where necessary;
This report provides Members with a high-level progress report on the work of the Internal Audit and Counter Fraud team for Q3 of the 2025/26 financial year. Which, alongside the Head of Audit and Counter Fraud’s Annual Report and Opinion for the year 2025/26, assists the Committee in discharging its responsibilities as set out in the Audit Committee’s Terms of Reference, which form part of the Council’s Constitution.
Executive summary
Audit and Counter Fraud Team activity during Q3 2025/26 included:
An assurance review of Arts Council grant funding for works to Northmoor Library. Four further reports in connection with Miocare Supported Living establishments, SEND Special School Placements, Home to School Transport and Oldham Total Care (OTC) are also being finalised with the relevant services. The outcomes of these reviews will be reported in due course. Corporate Counter Fraud activities have identified £183,096 of fraud, errors and overpayments in the year to date.
Recommendation
Members are requested to consider the 2025/26 Q3 Audit and Counter Fraud Progress Report. Audit Committee 14 January 2026
2025/26 Q3 Internal Audit and Counter Fraud Progress Report
Background
1.1This report summarises the work of the Audit and Counter Fraud Team between 1 April 2025 and 31 December 2025.
1.2The main content of the report is structured as follows:
2. 2025/26 Audit and Counter Fraud Service: Progress Update
2.1Priorities for the 2025/26 Audit and Counter Fraud Plan include:
Fundamental Financial Systems (FFS) reviews to provide assurance in support of the Authority’s Annual Financial Statements. Audits which are considered high priority and included in the Annual Internal Audit Plan. Counter Fraud work to prevent and detect fraud, theft and corruption. Investigations of both internal and external fraud. Support in connection with postal votes for local, regional, and parliamentary elections.
Progress against these priorities is summarised below:
2025/26 Fundamental Financial Systems (FFS) reports
2.2Work on the 2025/26 FFS reviews has commenced. The outcomes of the 2025/26 FFS reviews will be reported in due course.
Other work completed
2.3One Grant Assurance review was completed in Q3 in connection with:
Arts Council Grant - Northmoor Library
The outcomes of all finalised reports, and other work for the year to date, are shown at Appendix 1.
Four further reports are in the process of finalisation with service departments in respect of:
Miocare Supported Living Home to School Transport – Follow up SEND Special School Placements Oldham Total Care (OTC)
Work is also ongoing in respect of:
Let Estate – Follow up Highways Maintenance Waste Management Fostering Service
The outcomes of these reviews will be reported in due course. Other Work Undertaken
2.4The team has also supported both the Director of Finance and other colleagues within the Finance Service, and in other service areas, with ad hoc requests for support and assistance throughout the period as required.
2.5The Head of Audit and Counter Fraud continues to support the Committee, with a number of reports produced for review and consideration at this meeting.
3 Corporate Counter Fraud
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Treasury Management Review 2025/26That the Audit Committee notes and endorses the Treasury Management Outturn report and the Treasury Management activi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.