CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Oldham Metropolitan Borough Council
Governance, Strategy and Resources Scrutiny Board, Monday 28 September 2026 at 6.00pm

Oldham Heat Network - Local Development Order Public Consultation

Approved Scrutiny 2 papers

AI summaryThe Governance, Strategy and Resources Scrutiny Board endorsed public consultation on the draft Oldham District Heat Network Local Development Order and sought Group Leaders' concurrence so the Chief Executive can formally approve. Consultation costs will be met from existing approved budgets and resources.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedThe board endorsed both documents for public consultation.
MoneyNo additional financial implicationsAll consultation costs, including officer time, use existing approved resources.
What happens nextChief Executive formal approvalConcurrence is requested, enabling formal approval on 5 October 2026.
Who it affectsOldham District Heat NetworkTender bidders may view the project as more commercially attractive.

What was decided

The board endorsed the submitted report's recommendations.

The recommendations are to approve the draft Local Development Order and Statement of Reason for public consultation.

The board requested the Group Leaders meeting to concur, enabling the Chief Executive to formally approve the recommendations in the report.

Why

The District Heat Network is the anchor project in the live Strategic Energy Partner tender. A Local Development Order is a key workstream that could affect the tender's success. Report P10

Without a Local Development Order, tender bidders may not find the anchor heat network project as commercially attractive. Report P12

Emergency powers were used because the decision could not wait until the next Cabinet meeting. No Leader or Deputy Leader had been appointed, and there was no certainty about when either would be appointed. Report P6, P20

What happens next

The Group Leaders meeting is asked to concur with the recommendations.

Following that concurrence, the Chief Executive can formally approve the recommendations in the submitted report.

The draft Local Development Order and Statement of Reason are to be approved for public consultation.

Options considered

  • Chosen: Endorse recommendations for public consultation. The Local Development Order is a key workstream for the anchor project and could support the live tender. Report P10, P17
  • Rejected: Wait until the next Cabinet meeting. The Council Constitution authorises urgent executive decisions that cannot wait until the next Cabinet meeting. Report P6
  • Rejected: Wait until a Leader and Deputy Leader are appointed. The Council has no Leader or Deputy Leader, and there is no certainty about when either will be appointed. Report P20
  • Rejected: Do not take the decision forward. Bidders may see the project as less commercially attractive, and the project development and procurement exercise could fail and incur costs. Report P12, P14

Implications

  • Financial: The consultation gives rise to no additional financial implications. All costs, including officer time, will be met from existing approved budgets and resources. Report P17
  • Risk: Without a Local Development Order, tender bidders may not find the anchor heat network project as commercially attractive. Report P12
  • Risk: Not taking the decision could result in a failed Strategic Energy Partnership project development and procurement exercise, with associated costs. Report P14
  • Legal: The decision relies on Section 9C of the Council Constitution to allow the Chief Executive to take urgent executive decisions that cannot wait until the next Cabinet meeting. Report P6
  • Governance: Emergency powers were used without consultation with a Leader or Deputy Leader. Neither had been appointed, and there was no certainty about when either would be appointed. Report P20
  • Other: The Local Development Order is a key workstream for the anchor project and could affect the success of the live Strategic Energy Partner tender. Report P10

Who and where

  • Oldham District Heat Network project Report P10
  • Strategic Energy Partnership tender bidders Report P12
  • Strategic Energy Partnership project development and procurement exercise Report P14

Timeline

  • 11th September 2026: The Monitoring Officer provided comments on emergency powers and leadership consultation. Report P19, P20
  • 14 September 2026: The Section 151 Officer confirmed no additional financial implications for consultation. Report P16, P17
  • 2026-09-28: The board endorsed the recommendations and requested Group Leaders' concurrence.
  • 5 October 2026: The report gives this as the date of decision for the Local Development Order proposal. Report P2, P4

Plain English for the jargon

  • Local Development Order: The draft order associated with the Oldham District Heat Network.
  • LDO: Short form used for the Local Development Order.
  • Anchor project: The District Heat Network project within the live Strategic Energy Partner procurement.
  • Strategic Energy Partnership: The live procurement of a Strategic Energy Partner for Oldham Borough.
  • Statement of Reason: The document submitted with the draft Local Development Order for public consultation.
  • Section 151 Officer: The statutory officer who confirmed consultation has no additional financial implications.
  • Monitoring Officer: The officer who considered emergency powers and consultation with the Leader or Deputy Leader.
  • Chief Executive: The person identified as the Local Development Order decision maker.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

That the Governance, Strategy and Resources Scrutiny Board, endorses the recommendations detailed in the submitted report of the Executive Director of Place/Deputy Chief Executive, to approve the draft Local Development Order and Statement of Reason for public consultation and requests that the Group Leaders meeting concurs, thereby enabling the Chief Executive to formally approve the recommendations in the report.
Word for word from the decision Oldham published for this meeting. Source: committees.oldham.gov.uk

Follow this further

Built from Oldham's papers

What the report saysPro

Report to Governance, Strategy and Resources Scrutiny Board

Emergency Powers Decision Report

Heat Network LDO Decision Maker: Chief Executive

Service Area: Growth Directorate: Place & Economic Growth Report Author: Andrew Hunt, Green Energy & Sustainability Manager Email: [email protected]

Date of Decision: 5 October 2026

1. Power to make the decision

The decision is being taken under the authorisation contained in Section 9C – Delegations to Specific Officers of Part 3 (Responsibility for Functions) of the Council Constitution for the Chief Executive to take any emergency decisions in respect of the Council’s executive functions which cannot be delayed until the next Cabinet meeting.

2. Decision Sought

Cabinet’s approval to publicly consult on the draft Local Development Order associated with the Oldham District Heat Network.

3. Reason for urgency

The District Heat Network project is the ‘anchor’ project in the Council’s current live procurement of a Strategic Energy Partner for Oldham Borough. Progressing a Local Development Order is a key workstream for the project which could impact on the success of the current tender.

4. Risk(s) of not taking the decision

That bidders to the current live Strategic Energy Partnership tender may not find Oldham’s ‘anchor’ heat network project as commercially attractive as with an LDO in place.

5. Financial impact if decision not taken forward

Costs associated with a potentially failed Strategic Energy Partnership project development and procurement exercise. 6. Statutory Officer clearances

a. Section 151 Officer

Name Lee Walsh Date 14 September 2026 Comments:

The recommendation to undertake consultation on the draft Local Development Order for the Oldham District Heat Network does not give rise to any additional financial implications. All costs associated with the consultation process, including officer time, will be met from within existing approved budgets and resources.

b. Monitoring Officer

Name: Alex Bougatef Date: 11th September 2026 Comments:

The exercise of emergency powers should be undertaken in consultation with the Leader or Deputy Leader of the Council. However, the Council has not yet appointed a Leader or Deputy Leader for the current municipal year; it is therefore not possible to consult them. In addition, there is no certainty about when a Leader or Deputy Leader will be appointed as the Council has failed at successive meetings to do so. For the reasons given in the report, an urgent decision relating to the report is required, and it cannot wait until the appointment of a Leader and Deputy Leader at some undetermined future date.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
007: Oldham Heat Network Local Development Order: Key Decision ReportDecisions 977 KB Download
PDF
Oldham Heat Network: Local Development Order Public ConsultationReport 129 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 23 attended
MA
Montaz Ali AzadCommittee Member, expected
AB
Alex BougatefOfficer, expected
AB
Andrew Barry BrooksCommittee Member, expected
ED
Eleanor DevlinOfficer, expected
JD
Jonathan DownsOfficer, expected
CD
Chris DunbarOfficer, expected
MG
Matthew GrattonOfficer, expected
AJ
Abdul Jabbar MBECommittee Member, expected
MK
Mark KenyonCommittee Member, expected
SK
Shelley KiplingOfficer, expected
FL
Fran LautmanOfficer, expected
HM
Heather MooreOfficer, expected

All 23 on the meeting page

On this subject at Oldham

Search all
  1. Oldham Heat Network - Local Development Order Public ConsultationThis decision
  2. Oldham Heat Network - Zonal Boundary ConsultationApproved

More from Oldham Governance, Strategy and Resources Scrutiny Board

All decisions
MeetingDecisionOutcome
28 Sep 2026 MinutesThat the minutes of the meeting of the Governance, Strategy and Resources Scrutiny Board held on 24 th March 2026 be ... Approved Open
28 Sep 2026 Oldham Local Heritage ListThat the Governance, Strategy and Resources Scrutiny Board, endorses the recommendations detailed in the submitted re... Approved Open
28 Sep 2026 Oldham Heat Network - Zonal Boundary ConsultationThat the Governance, Strategy and Resources Scrutiny Board, endorses the recommendations detailed in the submitted re... Approved Open
28 Sep 2026 Sites of biological importance updateThat the Governance, Strategy and Resources Scrutiny Board, endorses the recommendations detailed in the submitted re... Approved Open
28 Sep 2026 Parent Infant Mental Health ServicesThat the Governance, Strategy and Resources Scrutiny Board, endorses the recommendations detailed in the submitted re... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies