Resolved
Resolved to note the current position on finance, corporate performance measures and risk for the first quarter of 2011/12.
City Executive Board (became Cabinet noted this item on Monday 13 May 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved to note the current position on finance, corporate performance measures and risk for the first quarter of 2011/12.
1. This report represents Quarter 1 of the financial year; it highlights major variances to the approved budget in the form of outturn variances.
2. The current month’s outturn shows a favourable variance of £68k to the 2011-12 approved budget.
3. The Council's budget contained major savings and efficiency proposals, totalling some £4.3 million for this financial year, and with a contingency set aside in case these were not achieved. In addition, the Council faces some major financial challenges, stemming from cuts to housing benefit, rising fuel costs, and income pressures due to the recession. As a consequence, good progress is being made in keeping the budget on-track, although there are some issues highlighted below.
4. Discussions with Cost Centre Managers and Heads of Service have identified a number of pressures and opportunities related to the full year outturn that will need to be managed during the year:
23 Major pressures identified – General Fund (2011-12 Outturn)
• Waste and recycling £120k • Car Parking – Worcester Street £90k • Customer Services – Fundamental Service Review £33k
5. At this stage services are working through mitigation actions for these variances. They have been included within the outturn as they currently represent a risk to the overall budget. Finance will work with service areas to ensure mitigation plans are put in place to offset these risks. Once robust plans are in place to cover these potential overspends the forecast outturn will be amended as appropriate.
Major Opportunities identified – General Fund
• A favourable St Aldates rent review decision will result in a one off release of provision @ £100k, plus an going favourable variance driven by a lower than anticipated annual rent settlement. This will be factored in to the outturn once the agreement has been signed. • New Homes Bonus £472k which was not budgeted for • Investment income is expected to be £40k favourable to approved budget due to the implementation of a more proactive approach to treasury management.
24 6. Appendix A provides an analysis of the forecast General Fund revenue outturn broken down by directorate. Table 1 below provides a summary.
Table 1 – General Fund Forecast Outturn as at 30th June 2011
Approved Latest Projected Outturn Budget Budget Outturn Variance 11/12 @30th to Latest June 2011 Budget £000's £000's £000's £000's Directorates: Chief Executive 3,964 3,925 4,000 75 City Regeneration 5,200 4,999 4,999 0 City Services 8,958 8,848 8,881 33 Finance & Efficiency 6,107 6,458 6,458 0
Total Excluding SLAs And Capital Charges 24,229 24,230 24,338 108
Capital Charges and other Non Controllable Costs (1,746) (1,746) (1,746) 0
Total of Corporate and other associated Budgets 2,478 2,478 2,438 (40) Transfer to Balances 816 816 816 0 Net Budget Requirement 25,777 25,778 25,846 (68)
Funding External Funding 13,399 13,399 13,399 0 Council Tax 12,355 12,355 12,355 0 Collection Fund surplus 24 24 24 0 Total Funding Available 25,778 25,778 25,778 0
(Surplus) / Deficit for Year (0) (0) (68) (68)
Working Balance
1st April 2011 4,428 Transfers in 816 31st March 2012 5,244
7. The difference between the approved budget and the latest budget at service level is explained by virements of ICT maintenance budgets and movement in the budget for Markets.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Finance appendix GF Full Savings Pressures List June 2011 (4)Appendix | 73 KB | Download |
PDF |
Quarterly Reporting: Finance, Performance and Risk: 2011/12Report | 241 KB | DownloadRead as text |
PDF |
RiskReport | 56 KB | Download |
PDF |
Risk appendixAppendix | 42 KB | Download |
PDF |
performanceReport | 28 KB | Download |
PDF |
performance apxReport | 71 KB | Download |
Follow City Executive Board (became Cabinet at Oxford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 May 2019 | Public QuestionsResolved to note the questions and answers provided. | Noted | Open |
| 13 May 2019 | Scrutiny Committee ReportsResolved to thank the Scrutiny Committees and the Scrutiny Panel for their useful input and to accept the recommendat... | Agreed | Open |
| 13 May 2019 | Scrutiny Committee ReportsIt was agreed that the Action Plan could be presented to the Housing Scrutiny Panel for review and monitoring. (4) Pr... | Agreed | Open |
| 13 May 2019 | Scrutiny Committee ReportsResolved to thank the Committee for its input and accept the recommendations in the report. | Decided | Open |
| 13 May 2019 | Scrutiny Committee ReportsResolved, on the Scrutiny Select Committee report on public health:- (1) To endorse each of the recommendations of th... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.