Resolved to:- 1) Approve the construction of the competition standard swimming pool adjoined to Blackbird Leys Leisure Centre and an increase in the contingency provision of £350k to cover risks, in particular; the implications of ground works and the Town Green application; 2) Delegate authority to the Executive Director of City Services, in consultation with the Head of Law and Governance, to award the construction contract to Willmott Dixon; 3) Delegate authority to the Executive Director of City Services to amend the contract with Fusion Lifestyle to include the management of the new competition standard swimming pool, subject to the agreement of satisfactory terms; and 4) Instruct officers to implement a decommissioning plan for Temple Cowley and Blackbird Leys Pools.
Word for word from the decision Oxford published for this meeting.Source: mycouncil.oxford.gov.uk
1.1In May 2009 the Leisure Facilities Review was approved by the City Executive Board. The Board gave project approval for a new pool at Blackbird Leys Leisure Centre which on completion would enable the closure of Temple Cowley Pools and Blackbird Leys Pool.
1.2Following a feasibility study the full business case was subsequently agreed by the City Executive Board in September 2010.
1.3This report updates the position following the tender process and recommends the way forward.
2. Facility Design
2.1The scheme consists of the original eight lane 25 metre competition standard pool, a floating floor enabling flexible programming of sessions, a teaching pool, spectator seating and a toddler fun pool.
2.2Additional elements were added following the pre-planning consultation. They are a poolside sauna, a soft play area, an increased number of individual showers, improved disabled adaptations, increased spectator seating, flexible changing group rooms that can be segregated by gender when required, modesty screening to the poolside, increased parking spaces and local transport infrastructure improvements.
3. Tender Process
3.1The tender process was detailed in the report approved by the City Executive Board on the 9th of March 2011.
3.2In accordance with the City Executive Board report of the 9th March, Willmott Dixon were appointed to undertake certain limited preliminary work on the project, but on the basis that having successfully tendered for the substantive construction contract, they were in place to be appointed to undertake the substantive contract in the event that the Council decided to proceed with the project. The construction contract would, therefore, now be let subject to Willmott Dixon’s guaranteed maximum price, reduced by further value engineering, to ensure that costs are held within budget.
3.3The guaranteed maximum construction price excluding fees and contingencies is £7,148,000.
2 3.4 The NEC31 form of contract will be used and this will dovetail the NEC3 contract for professional services in place for Mace who are providing the technical professional support and project management support to the project.
3.5The contract will require Willmott Dixon to provide a bond of 10% of the construction value, require full transparency of the sub-contractor pricing for each work package and will commit Willmott Dixon to payment of the sub-contractors in accordance with the Fair Payment Charter.
3.6Where possible, at least one local firm submitted a bid for each package of works. This resulted in 27 local firms receiving the opportunity to bid for various work packages.
4. Management of the New Pool
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.