Resolved
Resolved to approve the award to E.C.Harris of a contract to project manage (including full consultation of all stakeholders and multi disciplinary design services) this key refurbishment project for the Council’s tower blocks.
City Executive Board (became Cabinet approved this item on Monday 13 May 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved to approve the award to E.C.Harris of a contract to project manage (including full consultation of all stakeholders and multi disciplinary design services) this key refurbishment project for the Council’s tower blocks.
Appendix 1 - Risk Assessment Appendix 2 - Tender scores
1.1Project approval to refurbish the Council’s tower blocks was approved by the City Executive Board and Council in February 2012 as part of the HRA 2012/15 Capital programme budget approval process. This project also forms part of the HRA Business Plan.
93 1.2 The budget for the refurbishment is currently split over nine years.
1.3Due to the complex nature and scope of the project, our current staff resources do not have the experience, capacity or time needed to undertake the management of this project.
1.4The estimated costs exceeded the EU Procurement Regulations threshold and to ensure full compliance this tender has been advertised in accordance with the EU open tender process and advertised in the Official Journal of the European Union and the South East Business Portal.
2. Tender Process
2.1Fourteen businesses submitted tenders, five submissions were received from organisations with local offices.
2.2In order to help assess the submissions and provide an element of challenge, the Council commissioned a Project Manager from Acivico, Birmingham City Council’s Project Management team, to be part of the tender evaluation panel. Birmingham City Council has extensive experience of delivering tower blocks refurbishment programmes. Their input was extremely helpful to the Council’s tender evaluation panel.
2.3Tenders were evaluated in accordance with the Council’s Procurement Strategy; 60% quality and 40% price. The Council received a number of high quality tender submissions that offered a comprehensive project management approach and competitive price. Due to the possible contract length the panel carried out a comprehensive assessment of each bidders ability to manage the project of the possible nine years. . EC Harris demonstrated their ability to offer the flexibility to manage this project over a variable period should the budget be available over a shorter period, a competitive fixed price and included arrangements for providing specialist support to increase the potential for environmental improvements. This process has resulted in the tender scoring identifying E C Harris as the preferred bidder to manage this project.
3. Scope of the Refurbishment Project
3.1The scope of the works to be included in this appointment is wide ranging and includes:-
Facilitating stakeholder meetings.
Reporting on options available, including financial assessments and carbon savings in the case of heating replacement.
Production of working drawings and full specification of works for the refurbishment works and mechanical and electrical services (M&E), including architectural input on the design of the façade.
Liaising with the Council’s Procurement team for the main contractor tendering process, including evaluating tenders and making recommendations.
94 Monitoring works on site, including the provision of a Clerk of Works and weekly reporting.
Facilitating regular meetings with the Project Board and other stakeholders.
Agreeing monthly valuations and final account with the contractor.
Issuing variation orders as work proceeds.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Tower Blocks: Appointment of Project ManagerReport | 149 KB | DownloadRead as text |
Follow City Executive Board (became Cabinet at Oxford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 May 2019 | Public QuestionsResolved to note the questions and answers provided. | Noted | Open |
| 13 May 2019 | Scrutiny Committee ReportsResolved to thank the Scrutiny Committees and the Scrutiny Panel for their useful input and to accept the recommendat... | Agreed | Open |
| 13 May 2019 | Scrutiny Committee ReportsIt was agreed that the Action Plan could be presented to the Housing Scrutiny Panel for review and monitoring. (4) Pr... | Agreed | Open |
| 13 May 2019 | Scrutiny Committee ReportsResolved to thank the Committee for its input and accept the recommendations in the report. | Decided | Open |
| 13 May 2019 | Scrutiny Committee ReportsResolved, on the Scrutiny Select Committee report on public health:- (1) To endorse each of the recommendations of th... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.