City Executive Board (became Cabinet, Monday 13 May 2019 at 5.00pm

Pavilions Programme - Project Approval

Approved Executive 2 papers

City Executive Board (became Cabinet approved this item on Monday 13 May 2019. Below is the council's own wording, with the papers it was decided on.

Item24

Resolved

Resolved to:- (1) G rant Major Project Approval of £3.143million for the Pavilion Programme as set out in Appendix 1, subject to securing the relevant external funding; (2) RECOMMEND to Council an increase to the project budget to £3.143million subject to securing external funding, and Capital and Asset Management group agreeing the virements noted in Appendix 1; (3) Give delegated authority for the Executive Director, Community Services to undertake a procurement exercise for the construction contracts for the various pavilion projects detailed within the report and award the construction contracts to the successful tenderer (s) subject to them being within the overall budget.
Word for word from the decision Oxford published for this meeting. Source: mycouncil.oxford.gov.uk

Follow this further

Built from Oxford's papers

What the report saysPro

Report to City Executive Board (became Cabinet

Agenda Item 8

To: City Executive Board

Date: 10 July 2013

Report of: Head of Leisure, Parks and Communities

Title of Report: PAVILIONS PROGRAMME - PROJECT APPROVAL

Summary and Recommendations

Purpose of report: The report seeks project approval for the pavilion programme and requests delegated authority for the Executive Director of Community Services to award the various construction contracts when they arise.

Key decision? Yes

Executive lead member: Councillor Mark Lygo – Portfolio Holder for Sport and Parks

Policy Framework: Playing Pitch Strategy 2012-16

Recommendation(s): 1. To grant Major Project Approval of £3.143million for the Pavilion Programme as set out in appendix one, subject to securing the relevant external funding 2. Recommend to Council an increase to the project budget to £3.143million subject to securing external funding, and Capital & Asset Management group agreeing the virements noted in appendix one. 3. To give delegated authority for the Executive Director, Community Services to undertake a procurement exercise for the construction contracts for the various pavilion projects detailed within the report and award the construction contracts to the successful tenderer(s) subject to them being within the overall budget.

Appendices to report – Appendix 1 – Pavilion programme summary document Appendix 2 – Risk Assessment Appendix 3 – Equalities Impact Assessment

63 1. Introduction

1.1Oxford City Council is looking to modernise 12 of its sports pavilions across the city and to potentially build a new facility at Grandpont Recreation Ground. An overview of this is shown in appendix 1. The pavilions accommodate eight different sports, over 260 teams (or over 3,500 individuals) on a weekly basis.

1.2The pavilions review (an internal document) and the Council’s Playing Pitch and Outdoor Sport Strategy 2012-2026 have provided a solid evidence base for the present and futures needs of our sports pitches and pavilions. This work involved non-technical condition surveys, needs analysis, working with the relevant National Governing Bodies of Sport including the Oxfordshire Football Association, Sport England and significant consultation with clubs, officials and leagues. A football forum has also been held.

1.3The current condition of the pavilion stock attracts regular complaints from the users with most sports team registering complaints at the start of the season. These comments have also been replicated at the football forums that the City Council has held.

1.4A 2007 repairs backlog estimate was approximately £1.6 million to bring the pavilions to an average/good standard. This spend would help improve the facilities but not make any significant material changes so that the sites would still have the inherent problems that they have now in terms of security, inefficiency, site placement and vandalism.

1.5The improvement works will help enable improved access, security, provide greater opportunity to ensure clubs are sustainable, meet modern day standards and help to meet user expectations. Although most of the works will be refurbishment, we will be taking the opportunity to improve carbon performance and improve the external appearance to make them more appealing to a wider audience.

1.6The approved capital budget for the project is £2.708 million and is detailed in appendix one. However we will be looking to secure funding from external sources to increase this including the Football Foundation and Sport England to give a total project budget of £3.143 million.

1.7A significant amount of pre-works have been undertaken including title / legal searches, benefits mapping, site massing, work with the Environment Agency and County Highways Department and several surveys. We have also undertaken consultation and

64 communication with sports clubs and key stakeholders who use the pavilions in the first phase of the project.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pavilions Appendix 3Appendix 138 KB Download
PDF
Pavilions Programme: Project ApprovalReport 161 KB DownloadRead as text

More from Oxford City Executive Board (became Cabinet

All decisions
MeetingDecisionOutcome
13 May 2019 Public QuestionsResolved to note the questions and answers provided. Noted Open
13 May 2019 Scrutiny Committee ReportsResolved to thank the Scrutiny Committees and the Scrutiny Panel for their useful input and to accept the recommendat... Agreed Open
13 May 2019 Scrutiny Committee ReportsIt was agreed that the Action Plan could be presented to the Housing Scrutiny Panel for review and monitoring. (4) Pr... Agreed Open
13 May 2019 Scrutiny Committee ReportsResolved to thank the Committee for its input and accept the recommendations in the report. Decided Open
13 May 2019 Scrutiny Committee ReportsResolved, on the Scrutiny Select Committee report on public health:- (1) To endorse each of the recommendations of th... Agreed Open