Resolved
Resolved to:- (1) Grant project approval for the Council’s involvement in the project to utilise Energy Company Obligation (ECO) funding, in combination with funding supplied by the Council, to improve the energy efficiency of the Council’s hard to heat housing; (2) Note the officer virement of £250k from the underspend in the 2013/14 Housing Revenue Account (HRA) capital programme and the inclusion of a further £250k in the draft 2014/15 HRA budget to fund the Council’s contribution to the project; (3) Grant delegated authority to the Executive Director, Housing and Regeneration, to authorise the Council’s entry into all appropriate contracts required to implement the project; (4) Agree that if ECO funding is not successful, alternative proposals for the work to proceed be brought back for consideration; (5) Ask that a report back on progress be brought to the Board’s first meeting in the Council Year 2014/15.
Word for word from the decision Oxford published for this meeting.
Source: mycouncil.oxford.gov.uk