Resolved to:- (1) Approve the project to progress the construction of a new community hub in Rose Hill; (2) Grant authority to the Executive Director, Community Services to approve the award of the construction contract for the building of the Rose Hill Community Centre, subject to tenders being within budget.
Word for word from the decision Oxford published for this meeting.Source: mycouncil.oxford.gov.uk
Report of: Head of Leisure, Parks and Communities, and Service Manager, Regeneration and Major Projects
Title of Report: ROSE HILL COMMUNITY CENTRE CONSTRUCTION CONTRACT AWARD
Summary and Recommendations
Purpose of report: Request delegated authority to award the construction contract for Rose Hill Community Centre
Key decision: No
Executive lead member: Councillor Steve Curran and Councillor Ed Turner
Policy Framework: An Efficient and Effective Council
Recommendation(s):
To approve the project to progress the construction of a new community hub in Rose Hill.
To grant authority to the Executive Director for Community Services to approve the award of the construction contract for the building of the Rose Hill Community Centre, subject to tenders being within budget.
Introduction
1. The report provides an update to CEB on the progress of the Rose Hill Community Centre development and requests a delegation of authority from CEB to the Executive Director of Community Services.
Project Update
2. The pre-construction phase of the project remains on track. Progress is being monitored and managed by officers and Project Managers from The Clarkson Alliance. At this stage an opening date of the new Community Centre is scheduled for Spring 2015. This timetable will be tested within the procurement of the construction contractors.
343 3. The final design, which has been worked on in consultation with the community and councillors, was approved by the Project Board on the 20th December 2013. This is being issued to construction companies in January 2014.
4. A detailed communications strategy is in place which sets out the continued work with all stakeholders. This includes the participation of community groups, with a presentation planned in February on the final design to the Rose Hill Regeneration Partnership. In addition, the Council will have an opportunity to promote its brand and key messages on the hoardings that will be used on the site.
5. Further information and participation during the construction phase is planned, to give the community ownership and raise aspirations for the success of the project.
6. CEB should be aware that the residential and the community centre schemes are separate. CEB gave approval to the Rose Hill project on 19th December 2012. The project includes the development of the new Community Centre and sale of the sites of the existing community centre and the advice centre for residential development. The capital receipt from these land sales will be used to part fund the new community centre. This report deals only with the new community centre construction. The residential elements will follow separately after the new building is complete as there is a requirement for continuity of use.
Contract Award
7. The tender documents are to be issued in January 2014, with a closing date for responses in early March 2014.
8. The project plan seeks to have the construction contract in place by the end of March, with the successful contractor on site by mid-April. Delegated authority would be required to achieve this aim due to restrictions around CEB dates and timescales.
9. The tendering process is being carried out in line with Oxford City Council’s procurement policy and that Business Improvement team and Legal are fully involved. The value of works is below the EU procurement thresholds. Based on expressions of interest for other recent construction projects, tenders will be invited using the open tender process.
Finance
10. The budget for the project is £4,286,000; this includes a 7.9% contingency. The budgeted build cost is £3,485,726. £322,000 of the design and consultancy costs has been spent or committed for the end
344 of the 2013/14 financial year. An additional £228,000 has been bid for in the 2014/15 budget now that the final scheme has been designed and an updated cost plan produced.
Risk
11. A risk resister is included in appendix one.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.