CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Oxford City Council
City Executive Board (became Cabinet, Monday 13 May 2019 at 5.00pm

Rose Hill Community Centre Development - Next Steps

Approved Executive 1 paper

City Executive Board (became Cabinet approved this item on Monday 13 May 2019. Below is the council's own wording, with the papers it was decided on.

Item140

Resolved

Resolved to:- (1) Approve the project to progress the construction of a new community hub in Rose Hill; (2) Grant authority to the Executive Director, Community Services to approve the award of the construction contract for the building of the Rose Hill Community Centre, subject to tenders being within budget.
Word for word from the decision Oxford published for this meeting. Source: mycouncil.oxford.gov.uk

Follow this further

Built from Oxford's papers

What the report saysPro

Report to City Executive Board (became Cabinet

Agenda Item 13

To: City Executive Board

Date: 12th February 2014

Report of: Head of Leisure, Parks and Communities, and Service Manager, Regeneration and Major Projects

Title of Report: ROSE HILL COMMUNITY CENTRE CONSTRUCTION CONTRACT AWARD

Summary and Recommendations

Purpose of report: Request delegated authority to award the construction contract for Rose Hill Community Centre

Key decision: No

Executive lead member: Councillor Steve Curran and Councillor Ed Turner

Policy Framework: An Efficient and Effective Council

Recommendation(s):

To approve the project to progress the construction of a new community hub in Rose Hill.

To grant authority to the Executive Director for Community Services to approve the award of the construction contract for the building of the Rose Hill Community Centre, subject to tenders being within budget.

Introduction

1. The report provides an update to CEB on the progress of the Rose Hill Community Centre development and requests a delegation of authority from CEB to the Executive Director of Community Services.

Project Update

2. The pre-construction phase of the project remains on track. Progress is being monitored and managed by officers and Project Managers from The Clarkson Alliance. At this stage an opening date of the new Community Centre is scheduled for Spring 2015. This timetable will be tested within the procurement of the construction contractors.

343 3. The final design, which has been worked on in consultation with the community and councillors, was approved by the Project Board on the 20th December 2013. This is being issued to construction companies in January 2014.

4. A detailed communications strategy is in place which sets out the continued work with all stakeholders. This includes the participation of community groups, with a presentation planned in February on the final design to the Rose Hill Regeneration Partnership. In addition, the Council will have an opportunity to promote its brand and key messages on the hoardings that will be used on the site.

5. Further information and participation during the construction phase is planned, to give the community ownership and raise aspirations for the success of the project.

6. CEB should be aware that the residential and the community centre schemes are separate. CEB gave approval to the Rose Hill project on 19th December 2012. The project includes the development of the new Community Centre and sale of the sites of the existing community centre and the advice centre for residential development. The capital receipt from these land sales will be used to part fund the new community centre. This report deals only with the new community centre construction. The residential elements will follow separately after the new building is complete as there is a requirement for continuity of use.

Contract Award

7. The tender documents are to be issued in January 2014, with a closing date for responses in early March 2014.

8. The project plan seeks to have the construction contract in place by the end of March, with the successful contractor on site by mid-April. Delegated authority would be required to achieve this aim due to restrictions around CEB dates and timescales.

9. The tendering process is being carried out in line with Oxford City Council’s procurement policy and that Business Improvement team and Legal are fully involved. The value of works is below the EU procurement thresholds. Based on expressions of interest for other recent construction projects, tenders will be invited using the open tender process.

Finance

10. The budget for the project is £4,286,000; this includes a 7.9% contingency. The budgeted build cost is £3,485,726. £322,000 of the design and consultancy costs has been spent or committed for the end

344 of the 2013/14 financial year. An additional £228,000 has been bid for in the 2014/15 budget now that the final scheme has been designed and an updated cost plan produced.

Risk

11. A risk resister is included in appendix one.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Rose Hill Community Centre Development: Next StepsReport 125 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Oxford

Search all
  1. Rose Hill Community Centre Development - Next StepsThis decision
  2. Rose Hill Community FacilityNoted
  3. 139 Rose Hill: 12/02969/VARApproved

More from Oxford City Executive Board (became Cabinet

All decisions
MeetingDecisionOutcome
13 May 2019 Public QuestionsResolved to note the questions and answers provided. Noted Open
13 May 2019 Scrutiny Committee ReportsResolved to thank the Scrutiny Committees and the Scrutiny Panel for their useful input and to accept the recommendat... Agreed Open
13 May 2019 Scrutiny Committee ReportsIt was agreed that the Action Plan could be presented to the Housing Scrutiny Panel for review and monitoring. (4) Pr... Agreed Open
13 May 2019 Scrutiny Committee ReportsResolved to thank the Committee for its input and accept the recommendations in the report. Decided Open
13 May 2019 Scrutiny Committee ReportsResolved, on the Scrutiny Select Committee report on public health:- (1) To endorse each of the recommendations of th... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies