Council resolved to: 1. Adopt the CIL Charging Schedule in line with the recommendation of the independent examiner as set out in Appendix 1; 2. Approve the date on which the amended tariffs will come into effect. 3. Delegate authority to the Director of Planning and Regulatory to make any necessary further minor changes to the documents or any minor change to the implementation date for the new CIL rates
Word for word from the decision Oxford published for this meeting.Source: mycouncil.oxford.gov.uk
To: Council Date: 14 July 2025 Report of: Director of Planning and Regulation Title of Report: Community Infrastructure Levy – to approve of amended Charging Schedule
Summary and recommendations Decision being For Council to approve the Partial Review of the taken: Community Infrastructure Levy Charging Schedule Key decision: No Cabinet Member: Councillor Alex Hollingsworth Cabinet Member for Planning and Culture Corporate Priority: Enable an Inclusive Economy Deliver More Affordable Housing Support Thriving Communities Pursue a Zero Carbon Oxford Policy Framework: The Community Infrastructure Levy (CIL) is a charge on new developments which helps to fund infrastructure, as is set out in CIL Regulations 2010 (as amended).1 The CIL Charging Schedule sets out a standard tariff on development in Oxford City.
Recommendation(s): that Council resolves to: 1. Adopt the CIL Charging Schedule in line with the recommendation of the independent examiner as set out in Appendix 1; 2. Approve the date on which the amended tariffs will come into effect. 3. Delegate authority to the Director of Planning and Regulatory to make any necessary further minor changes to the documents or any minor change to the implementation date for the new CIL rates.
Appendix No. Appendix Title Exempt from Publication Appendix 1 The CIL Charging No Schedule as amended Appendix 2 Inspectors Report No
69 Introduction and background 1. The CIL Charging Schedule sets out a tariff in the form of a standard charge on new development to help the funding of infrastructure in Oxford. The City Council has been charging CIL on qualifying developments since 2013. The rates charged have risen with inflation but not been reviewed since the first Charging Schedule was published. 2. A Partial Review of the CIL Charging Schedule has been underway since 2023 and involved public consultation and an examination by an independent examiner. In the Charging Schedule submitted for examination, the City Council proposed amending the rate chargeable on Office and Research and Development uses from £33.74/m2 to £168.74/m2 (£172.28 m2 under current indexation). All other rates for all other uses would be unaffected by the review. 3. The Examiners’ Report was received on 30th April 2025. The report found that the proposed rate would not threaten delivery of Office and Research & Development business in Oxford and concludes that the draft Oxford City Council Community Infrastructure Levy Charging Schedule provides an appropriate basis for the collection of the levy in the area. The purpose of this report therefore is to request that Cabinet recommend to Full Council that they approve the amended CIL Charging Schedule for use in calculating the planning charge on new development to help the funding of infrastructure.
Findings of the independent examiner 4. The City Council asked Intelligent Plans and Examinations (IPE) to examine the Partial Review of the Charging Schedule who appointed [name removed] (Hons) DipTP MRTPI ARCIS to the examination. The examination hearing was held on the 31st March 2025. Those who had responded to the consultation had the opportunity to appear at the examination in person or to rely on their written representations. Seven parties requested to be heard in person and the examination was concluded in one session.
5. The Council received the Examiner’s final report on 30th April 2025. In his conclusions the Examiner states: “I consider the viability assessment to be robust and conclude that the rate proposed would not threaten delivery of office/R&D development in Oxford. The proposed rates are justified, therefore. I conclude that the partial review of the draft Oxford City Community Infrastructure Levy Charging Schedule, satisfies the drafting requirements and I therefore recommend that the draft Charging Schedule be approved.”
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.