Cabinet noted this item on Tuesday 21 December 2010. Below is the council's own wording, with the papers it was decided on.

Item143/10

Resolved

to accept the r ecommendations set out in the report of the Audit Working Group and to note that many were already in progress.
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Cabinet, 32 pages

Background

1. At their meeting on 17th November, Audit Committee considered a report by [name removed], Chairman, Audit Working Group (AWG), on the 2009/10 ICT overspend.

2. Audit committee decided to refer the report to the Cabinet together with an update by the Acting Head of ICT of how the matters raised in the report have been addressed.

3. The Audit Committee decision is attached as Annex 1.

4. The full report from [name removed] is attached as Annexx 2.

5. The update report from Acting Head of ICT is attached as Annexx 3

RECOMMENDATION 6. The Cabinet is RECOMMENDED to consider the conclusions of the report from [name removed] and the actions described in the update report from the Acting Head of ICT Services.

GRAHAM SHAW Acting Head of ICT Services

Background papers: Nil

Contact Officer: Graham Shaw Tel: 01865 816593

December, 2010 CA13

ANNEX 1

Extract from AUDIT COMMITTEE DECISIONS WEDNESDAY, 17 NOVEMBER 2010

10. ICT Overspend 2009/10

Report by [name removed], Chairman, Audit Working Group (AWG), on behalf of the AWG (AU10).

The Committee is RECOMMENDED to note the report, in particular: In noting the report, the Committee (a) the conclusion that measures RESOLVED: taken to mitigate the ICT overspend in late 2008/9 (a) that a copy of the report AU10 probably contributed to a be sent to all councillors; delay in taking effective cost- containment measures in (b) to refer the report to the Cabinet 2009/10; together with an update by the Acting Head of ICT of how the (b) that there was over- matters raised in the report have commitment coupled with a been addressed; and lack of flexibility to respond to adverse events in early 2009; (c) at the suggestion of Councillor Melinda Tilley, Chairman of the (c) that pressures on the core ICT Strategy & Partnerships Scrutiny budget continue, but that Committee, that the report be significant efficiencies have considered by that Committee on 18 been achieved and more will November 2010 as part of item 8 arise from recent and 'Corporate ICT Strategy', prior to forthcoming staff Cabinet consideration of this matter restructuring; on 21 December 2010.

(d) that project work, whether (d) to thank [name removed] for his work and strategic or departmental, the report. should not be undertaken by ICT without clear financial agreements with the relevant sponsoring agent (e.g. Directorate or Project Board);

(e) that there remain significant external risks to the ICT budget in respect of SAP, Microsoft and IBM applications; CA13

(f) that ICT management are aware of current risks and have in place a new Corporate ICT Strategy and action plan to mitigate them. CA13

ANNEX 2

AUDIT COMMITTEE 17 November 2010

AUDIT WORKING GROUP: ICT OVERSPEND 2009/10

Report by [name removed], Chairman AWG, on behalf of the Audit Working Group.

Summary

The Audit Working Group (AWG) on 21st April 2010 was asked by the Audit Committee to investigate an overspend in the County’s ICT function in 2009/10 which necessitated a supplementary estimate of £2.250m being provided. We were also asked for assurance that processes were in place to control the budget in 2010/11.

Our work has involved examining the public documents of the County in relation to ICT over a number of years (mainly Cabinet papers), together with considering internal submissions made to us by the ICT management team both in person and in writing, and information from some other officers who had a close connection with certain aspects of ICT operations in 2009/10. An interim report was made to the Audit Committee on 30 June 2010 and a full draft report was considered by the AWG on 8 September. The draft was sent to officers for comment immediately after the meeting. The present document presents the conclusions from the investigation, taking account of the current position.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ICT Overspend 2009/10Report 32 pages DownloadRead as text

More from Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Response to Motion by Councillor Evans on Motor Neurone DiseaseContact: Izzie Rockingham, Commissioning Manager (Improve Enable) [email protected] Report by the ... Approved Open
15 Sep 2026 DfT Local Transport Delivery PlanContact: Hannah Battye, Head of Place Shaping [email protected] Report by the Director of Environment ... Approved Open
15 Sep 2026 Treasury Management Quarter 1 Report 2026/27RESOLVED to note the council’s treasury management activity at the end of the first quarter of 2026/27. Noted Open
15 Sep 2026 Forward Plan and Future BusinessRESOLVED to note the items currently identified for forthcoming meetings. Noted Open
28 Jul 2026 Proposed Changes to Adult Social Care Contributions PolicyRESOLVED to:- Note the contents of this report and confirm its agreement for a) Reducing the initial Disability Relat... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies