Item39/20
Resolved
RESOLVED ( nem con) that the Committee’s resolution of 1 June 2020 to approve application no. MW.0066/19 subject to the applicant signing a Section 106 agreement for the matters outlined in Annex 2 of the committee report of 1 June 2020 and a routeing agreement to ensure that HGVs follow the route approved for HGVs associated with the existing quarry and subject to conditions to be determined by the Director of Planning and Place, to include those set out in Annex 1 of the Committee report of 1 June 2020 be amended such that condition 4 reads as follows: Temporary consent – extraction completed by six years from the date of commencement as notified pursuant to condition 2 and restoration completed by the date seven years from the date of commencement.
Word for word from the decision Oxfordshire published for this meeting.
Source: mycouncil.oxfordshire.gov.uk