Oxfordshire County Council
Cabinet, Tuesday 18 October 2022 at 2.00pm

Zero Emission Bus Regional Areas (ZEBRA) Funding Agreements

Agreed Executive 5 papers

Cabinet agreed this item on Tuesday 18 October 2022. Below is the council's own wording, with the papers it was decided on.

Item132/22

Resolved

RESOLVED to: delegate authority to the Corporate Director for Environment and Place, in consultation with the Director for Law and Governance and the Cabinet Member for Highway Management to negotiate, finalise and enter into funding agreements with Oxford Bus Company (Go-Ahead) and Stagecoach to provide electric buses and charging infrastructure based on the funding milestones set out in this paper.
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Cabinet, 8 pages

Recommendation

Cabinet is RECOMMENDED to delegate authority to the Corporate Director for Environment and Place, in consultation with the Director for Law and Governance and the Cabinet Member for Highway Management to negotiate, finalise and enter into funding agreements with Oxford Bus Company (Go- Ahead) and Stagecoach to provide electric buses and charging infrastructure based on the funding milestones set out in this paper.

Executive summary

1. The Department for Transport (DfT) has agreed to Oxfordshire County Council’s funding ‘ask’ for the delivery of its Zero Emission Bus Regional Areas programme (ZEBRA). ZEBRA services will be procured and operated by the two main bus operators serving Oxfordshire – Oxford Bus Company and Stagecoach.

2. Funding from DfT is to be paid directly to Oxfordshire County Council who will need to oversee the delivery of ZEBRA and manage grant payments to the bus operators for the procurement of buses and related infrastructure. It is a requirement that the bus operators place orders for buses by December 2022 as orders made after this date will mean a significant increase in costs.

3. Oxfordshire County Council therefore needs to agree payment terms and key milestones with bus operators to ensure the project’s timely delivery and the release of funds at appropriate points and ensure the funding conditions set out by the DfT are met. These provisions will be covered through legally binding funding agreements with the operators. The value of the grants being offered to operators means Cabinet approval is sought to enter into these funding agreements. Under the Local Authorities (Functions and Responsibilities) (England) Regulations 2000 and the council’s Constitution, the Cabinet is the appropriate decision-making body.

4. Bus operators’ participation in the ZEBRA project is conditional on the county council committing to measures to increase bus productivity in the city by at least 10%. The proposed trial traffic filters in Oxford will account for over half of this productivity improvement, so operators’ participation in ZEBRA – at the current time and its current form – is in effect conditional on the trial traffic filters proceeding. If a decision is made not to proceed with the trial traffic filters, the ZEBRA project will not progress in its present form and the current funding CA9

agreement will have to be terminated. It may be possible for other measures to achieve the 10% improvements to be agreed between Oxfordshire County Council and the operators, but there is no guarantee of this. Owing to the time required to develop any such alternative, the county council would need to ask the Department for Transport to defer Oxfordshire’s ZEBRA award until a future year – again with no guarantee of success.

Background

5. In January 2022 Oxfordshire County Council applied to the DfT for grant funding to enable the procurement of electric buses for use within the Oxford SmartZone area. In March 2022 the funding bid was approved, and Oxfordshire County Council was awarded £32.8 million by the DfT. This has been supplemented by £6 million of capital funding by Oxfordshire County Council and £43.7 million from the Oxford Bus Company (Go-Ahead) and Stagecoach.

6. It is anticipated the project will deliver 159 electric buses for use on routes operating wholly within the Oxford SmartZone, along with associated infrastructure. The bus operators are responsible for the delivery of these elements.

7. A project delivery group between Oxfordshire County Council, the Oxford Bus Company and Stagecoach is being established and will be administered by Oxfordshire County Council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CA_OCT1822R09 Annex 1-Oxfordshire MOU /22Appendix 4 pages Download
PDF
CA_OCT1822R09 Annex 2: ZEBRA Payment Milestones /22Appendix 2 pages Download
PDF
CA_OCT1822R09 Annex 3: OCC Subsidy Assessment against Principles ZEBRA Draft 26.09.22 /22Appendix 9 pages Download
PDF
CA_OCT1822R09 Annex 4 -ZEBRA ECIA /22Appendix 24 pages Download
PDF
Zero Emission Bus Regional Areas (ZEBRA) Funding AgreementsReport 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Oxfordshire

Search all
  1. Zero Emission Bus Regional Areas (ZEBRA) Funding AgreementsThis decision
  2. Oxford Zero Emission Zone Pilot Scheme - Income Sharing AgreementAgreed
  3. Oxford Zero Emission Zone Pilot Scheme - Income Sharing AgreementDeferred
  4. Oxford Zero Emission Zone Pilot Formal ConsultationNoted

More from Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Response to Motion by Councillor Evans on Motor Neurone DiseaseContact: Izzie Rockingham, Commissioning Manager (Improve Enable) [email protected] Report by the ... Approved Open
15 Sep 2026 DfT Local Transport Delivery PlanContact: Hannah Battye, Head of Place Shaping [email protected] Report by the Director of Environment ... Approved Open
15 Sep 2026 Treasury Management Quarter 1 Report 2026/27RESOLVED to note the council’s treasury management activity at the end of the first quarter of 2026/27. Noted Open
15 Sep 2026 Forward Plan and Future BusinessRESOLVED to note the items currently identified for forthcoming meetings. Noted Open
28 Jul 2026 Proposed Changes to Adult Social Care Contributions PolicyRESOLVED to:- Note the contents of this report and confirm its agreement for a) Reducing the initial Disability Relat... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies