Cabinet, Tuesday 21 November 2023 at 2.00pm

Business Services Transformation Programme Business Refocus

Approved Executive 1 paper

Cabinet approved this item on Tuesday 21 November 2023. Below is the council's own wording, with the papers it was decided on.

Item143/23

Resolved

RESOLVED to approve:- a. the refocusing of the programme on the delivery of improvements to existing human resources, finance, payroll and procurement functions and processes. b. that the programme does not progress the development of detailed requirements and a full business case to review delivery options for corporate support services and underpinning technology. c. the repurposing £1.23m of the existing approved £1.57m programme funding to deliver the refocused programme and return the remaining £345k to the Transformation Reserve.
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Cabinet, 7 pages

Recommendation

1. Cabinet is RECOMMENDED to:

a. Approve the refocusing of the programme on the delivery of improvements to existing human resources, finance, payroll and procurement functions and processes.

b. Approve that the programme does not progress the development of detailed requirements and a full business case to review delivery options for corporate support services and underpinning technology.

c. Approve the repurposing £1.23m of the existing approved £1.57m programme funding to deliver the refocused programme and return the remaining £345k to the Transformation Reserve.

Executive summary

2. This report provides an update on the progress of the Business Services Transformation Programme and seeks approval for a proposal to refocus, deliver improvements to existing human resources (HR), finance, payroll and procurement functions and processes and remain with Hampshire County Council’s Integrated Business Centre (IBC).

3. This report also seeks approval for the repurposing of £1.23m of the existing Cabinet approved £1.57m programme funding for delivery of the programme to date and to plan and deliver an Improvement Stage. The £1.57m was previously agreed at Cabinet in April 2023 for programme resources to prepare detailed requirements for a transformation and procurement process.

4. Prior to completion of the Improvement Stage a review will be completed to assess progress and determine next steps, including delivery of further identified improvements and / or required Council preparations and involvement in the IBC’s planned upgrade to SAP S/4HANA (the up-to-date version of SAP), which is planned to complete by September 2025.

Background

5. In 2015 the council entered a shared service arrangement that effectively outsourced its HR, finance, payroll and procurement support including the technology infrastructure via a partnership agreement with Hampshire County Council’s IBC, which had already been established supporting other public sector bodies.

6. A Case for Change review was undertaken in Q4 2021/22. The analysis identified opportunities and drivers to move from the existing shared services partnership and informed a high-level options appraisal and outline business case, which was completed in March 2023.

7. In April 2023 Cabinet approved the development of detailed requirements and a business case to review delivery options for corporate support services and underpinning technology including HR, finance, payroll and procurement in order to deliver services more efficiently, modernise business processes and upgrade current IT systems. Funding of £1.57m was approved for programme resources to prepare requirements for a transformation and to deliver a potential procurement process.

8. Following Cabinet approval, the programme launched a Requirements Stage to review operating model options, capture requirements and develop a business case to inform a decision at Cabinet in November to commence a procurement process. During this activity factors emerged which led to a proposal to refocus the programme, remain with IBC for the time being, and to deliver improvements to existing functions and processes.

9. The emergent factors that resulted in the proposal to refocus the programme include:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Business Services Transformation Programme Business RefocusReport 7 pages DownloadRead as text

More from Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Response to Motion by Councillor Evans on Motor Neurone DiseaseContact: Izzie Rockingham, Commissioning Manager (Improve Enable) [email protected] Report by the ... Approved Open
15 Sep 2026 DfT Local Transport Delivery PlanContact: Hannah Battye, Head of Place Shaping [email protected] Report by the Director of Environment ... Approved Open
15 Sep 2026 Treasury Management Quarter 1 Report 2026/27RESOLVED to note the council’s treasury management activity at the end of the first quarter of 2026/27. Noted Open
15 Sep 2026 Forward Plan and Future BusinessRESOLVED to note the items currently identified for forthcoming meetings. Noted Open
28 Jul 2026 Proposed Changes to Adult Social Care Contributions PolicyRESOLVED to:- Note the contents of this report and confirm its agreement for a) Reducing the initial Disability Relat... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies