Capital Outturn Report 2023/24

Noted Executive 2 papers

Cabinet noted this item on Tuesday 18 June 2024. Below is the council's own wording, with the papers it was decided on.

Item89/24

Resolved

RESOLVED to: a) note the performance against the capital programme for 2023/24 as set out in the report. b) approve the creation of a new reserve to support the development of green financing and to make an initial contribution of £1.0m funded from the interest released at the end of 2023/24 (as set out in paragraph 65 of the report) Here's a summary of the document: Main ideas: · The report shows the capital spending and funding of the council for 2023/24: The report compares the actual capital expenditure and financing of the council for 2023/24 to the original and latest budget plans. It also highlights the main programmes and projects that were delivered or in progress during the year. · The report recommends the creation of a new reserve for green financing: The report proposes to approve the creation of a new reserve to support the development of green financing and to make an initial contribution of £1.0m funded from the interest released at the end of 2023/24. This is to help the council achieve its climate action goals and invest in low-carbon projects. · The report details the performance of the capital programme by strategy area: The report provides a summary of the actual expenditure for each strategy area, such as Pupil Place Plan, Major Infrastructure, Highways Asset Management Plan, Property Strategy, IT, Digital & Innovation Strategy, Passported Funding, and Vehicles & Equipment. It also explains the reasons for the variations between the latest and original ... view the full minutes text for item 89/24
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Cabinet, 19 pages

Recommendation

1. The Cabinet is RECOMMENDED to:

a) note the performance against the capital programme for 2023/24 as set out in the report. b) Approve the creation of a new reserve to support the development of green financing and to make an initial contribution of £1.0m funded from the interest released at the end of 2023/24 (as set out in paragraph 65)

Executive summary

2. The ten-year Capital Programme sets out the agreed capital investment to deliver the priorities identified in the council’s Capital and Investment Strategy. This report updates on the performance against the programme shown in the latest monitoring report for 2023/24 and also compares back to the capital programme agreed by Council in February 2023. Figures shown reflect those to be included in the Council’s Statement of Accounts for 2023/24.

3. The capital programme is updated throughout the year to reflect the latest delivery profiles and cost estimates for each programme. The last update was based on the January 2024 monitoring position, and this was agreed by Cabinet in March 2024. Planned capital spend for 2023/24 totalled £191.3m. Actual capital programme expenditure by 31st March 2024 was £175.9m. The variation between the latest programme and the actual expenditure is -£15.4m (-8%). This spend is now expected to take place in 2024/25.

4. The expenditure was funded by £83.1m of capital grants and other external contributions, £30.8m of developer contributions and Community Infrastructure Levy, £2.2m of revenue contributions, and £59.8m of prudential borrowing.

Introduction

5. Capital expenditure is defined as spending that creates an asset for the counci l (e.g. buildings, vehicles and equipment), and spending which meets the definition in regulations specified under the Local Government Act 2003 which includes spend on non-current assets that are not owned by the Council such as academy schools and the award of capital grants and funding agreements.

6. The council’s ten-year capital programme sets out the agreed capital investment to deliver the priorities identified in the Capital and Investment Strategy. This is agreed annually by Council alongside the revenue budget and Medium-Term Financial Strategy.

7. The capital programme is currently structured as follows:

 Pupil Place Plan: including basic need (new schools and expansion), maintenance, health and safety and improvements,  Major Infrastructure: including Growth Deal Infrastructure programme,  Highways and structural maintenance: including street lighting, and bridges,  Property Strategy: including health & safety, maintenance, improvements and the Investment Strategy,  IT, Digital & Innovation Strategy: including broadband, software and equipment,  Passported Funds: including Disabled Facilities Grant and Devolved Schools Capital,  Vehicles and Equipment: including fire and rescue vehicles and equipment,

8. Each strand of the programme is underpinned by supporting strategies which set out the need for capital investment and the contribution of that planned investment towards the council’s priorities. These include:

 Pupil Place Plan and Special Educational Needs and Disability (SEND) Sufficiency Plan  Local Transport & Connectivity Plan  Highways Asset Management Plan  Property & Assets  Household Waste Recycling  Libraries & Heritage  Climate Action Framework  IT & Digital

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Outturn Report 2023/24Report 19 pages DownloadRead as text
PDF
Capital Provisional Outturn Report 23-24 Annexes Final /24Appendix 74 KB Copy on its way

More from Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Response to Motion by Councillor Evans on Motor Neurone DiseaseContact: Izzie Rockingham, Commissioning Manager (Improve Enable) [email protected] Report by the ... Approved Open
15 Sep 2026 DfT Local Transport Delivery PlanContact: Hannah Battye, Head of Place Shaping [email protected] Report by the Director of Environment ... Approved Open
15 Sep 2026 Treasury Management Quarter 1 Report 2026/27RESOLVED to note the council’s treasury management activity at the end of the first quarter of 2026/27. Noted Open
15 Sep 2026 Forward Plan and Future BusinessRESOLVED to note the items currently identified for forthcoming meetings. Noted Open
28 Jul 2026 Proposed Changes to Adult Social Care Contributions PolicyRESOLVED to:- Note the contents of this report and confirm its agreement for a) Reducing the initial Disability Relat... Noted Open