Access to Witney: Shores Green Junction Approval of Contract Award of Construction
ApprovedCommittee1 paper
Infrastructure & Development Strategy approved this item on Thursday 15 August 2024. Below is the council's own wording, with the papers it was decided on.
RESOLVED to: a) Delegate authority to the Director of Environment and Highways, to approve the entering into a Works contract with Milestone Infrastructure for the value of £12.703m (excl. VAT) pursuant to the Pagabo Civil and Infrastructure Framework (Lot 2), and to approve entering into an Enabling Works contract with Milestone Infrastructure via their existing Highways Partnership Contract (HPC) - Terms and Services Contract, for the value of £1.900m, together representing the full construction of the Access to Witney Scheme.
Word for word from the decision Oxfordshire published for this meeting.Source: mycouncil.oxfordshire.gov.uk
Report to Infrastructure & Development Strategy, 3 pages
Recommendation
The Cabinet Member is RECOMMENDED to
a) Delegate authority to the Director of Environment and Highways, to approve the entering into a Works contract with Milestone Infrastructure for the value of £12.703m (excl. VAT) pursuant to the Pagabo Civil and Infrastructure Framework (Lot 2), and to approve entering into an Enabling Works contract with Milestone Infrastructure via their existing Highways Partnership Contract (HPC) - Terms and Services Contract, for the value of £1.900m, together representing the full construction of the Access to Witney Scheme.
Executive summary
1. The A40 Access to Witney scheme proposes improvements to the existing B4022/A40 junction at Shores Green. The purposes of the A40 Access to Witney transport scheme are:
(a) To reduce congestion and improve air quality in central Witney, including on Bridge Street and in the Air Quality Management Area. (b) To support the delivery of planned housing growth in Witney as set out in the West Oxfordshire Local Plan 2031. (c) To improve access to the A40 from northeast Witney.
2. Planning permission for the Scheme was granted by the County Planning Authority in July 2023, with further permissions granted in March 2024 for minor design variations. A Public Inquiry for the necessary Compulsory Purchase Orders (CPO) and Side Road Orders (SRO) was held in mid-March 2024, and a decision from the Secretary of State for Transport is awaited.
3. In parallel the council is still seeking to acquire all of the land interests that it requires for delivery of the Scheme through private negotiation wherever possible. Key Issues
4. It is essential that this decision is made urgently to ensure that the construction programme is not adversely affected. The key driver for using the Highways Partnership Contract Framework (Enabling Works) and the Pagabo Civil and Infrastructure Framework (Main Works) with Milestone Infrastructure is to expedite the construction process. This route will produce the shortest time to commence construction and ensure that the allocated Housing Growth Deal funding is spent by the end of March 2025, whilst adhering to the latest programme/timescales.
Financial implications
5. As identified previously, this report seeks to ensure that authority is in place for entering of a Works contract (for the value of £12.703m excl. VAT) to be issued to Milestone Infrastructure, pursuant to the Pagabo Civil and Infrastructure Framework (Lot 2), and an Enabling Works contract with Milestone Infrastructure called-off via the Highways Partnership Contract Framework (for the value of £1.900m excl. VAT), for the full construction of the Access to Witney Scheme.
6. The total estimated final cost (EFC) of the Scheme is £25.025m. The Scheme will be funded via a mixture of Housing Growth Deal Funding (£15.578m) , pending a re-allocation decision by FOP and Section 106 developer contributions (£9.447m) – S106 (Unsecured) of £6.64m which is to be forward funded by OCC Corporate Resources, and S106 (secured) of £2.81m held as secured contributions. The current total risk allocation for the project is £2.285m, forming 16% of the construction budget allocated.
7. There are no budgetary implications, as the budgets for the project have already been previously agreed by Cabinet.
Comments checked by: Rob Finlayson, Finance Business Partner ([email protected])
Legal implications
8. When procuring goods, services or works, the procurement must be conducted in accordance with the Council’s Contract Procedure Rules and, where applicable, the Public Contracts Regulations 2015 (PCRs).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Infrastructure & Development Strategy at Oxfordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.