Bicester Village Western Infrastructure - Proposed Pedestrian Crossings
ApprovedCommittee1 paper
AI summaryOxfordshire County Council approved four crossings at the Kings End, Middleton Stoney Road and Oxford Road roundabout junction: three parallel crossings and one Toucan crossing [D]. Bicester Village provided funding for consultation and implementation, and a stage 3 road safety audit will follow completion [P12] [P33].
Written from the decision and the officer reportPDF Pro
OutcomeApprovedThree parallel crossings and one Toucan crossing [D]
MoneyFunding from Bicester Village [P12]Consultation and implementation following approval [P12] [D]
What happens nextImplement the four crossings [D]Stage 3 road safety audit follows completion [P33]
Who it affectsPedestrians and pedal cyclists [P7]Four approach roads around the junction [P6]
What was decided
Two parallel crossings were approved as advertised: one on Kings End, approx.10 metres north of the roundabout junction, and one on the new access road, approx.10 metres east of the roundabout junction. The new access road crossing will sit on a raised table feature [D] [P3]. Report P3
A Toucan crossing was approved on Oxford Road, approx.15 metres south of the roundabout junction, as advertised [D] [P4]. Report P4
A parallel crossing was approved on Middleton Stoney Road, approx.19 metres west of the roundabout junction, as amended since advertisement [D] [P5]. Report P5
Why
The crossings are intended to improve pedestrian and pedal cyclist safety following planned improvement works or amendments to the junction [P20]. Report P20
The crossings follow desired pedestrian and cycle routes to reduce route deviation and encourage crossings at controlled locations [P30]. Report P30
The wider junction scheme already had planning permission from Cherwell District Council. The new roundabout is intended to increase capacity, relieve congestion and improve walking and cycling links [P29]. Report P29
What happens next
Introduce the four approved crossings, including the raised table feature on the new access road [D].
An independent stage 3 road safety audit will follow upon completion [P33]. Report P33
Implement the planned keep clear markings and wider signage strategy. Possible further Middleton Stoney Road improvements are under review and are likely to be subject to a separate active travel scheme [P34]. Report P34
Options considered
Chosen: Parallel crossings on Kings End, the new access road and Middleton Stoney Road. Parallel crossings were considered most suitable to allow both traffic flow and safe crossing provision. Report P2, P3, P5, P31
Chosen: A Toucan crossing on Oxford Road Report P4, P7
Chosen: Move the Middleton Stoney Road crossing closer to the roundabout. To reduce route deviation for pedestrian and cycle users. Report P5, P32
Implications
Legal: The consultation complied with legal requirements, including under the Highways Act 1980. Oxfordshire County Council promoted the scheme as Highway Authority under that Act [P13] [P14]. Report P13, P14
Risk: The proposals have undergone independent road safety audit stages 1 and 2, with stage 3 to follow upon completion. No potential significant health and safety or service provision risks have been identified [P21] [P33]. Report P21, P33
Financial: Bicester Village provided funding for consultation and implementation following approval. No potentially significant financial impacts have been identified [P12] [D] [P21]. Report P12, P21
Equalities: No negative implications for equalities or inclusion have been identified [P18]. Report P18
Other: The consultation received 74 survey responses and four direct emails. Support was recorded for every crossing: Kings End 42 (57%), Middleton Stoney Road 39 (53%), new access road 51 (69%) and Oxford Road 39 (53%). Respondents raised concerns about congestion, crossings being too close to the roundabout and traffic access [P24] [P25] [P26] [P29] [P30] [P34]. Report P24, P25, P26, P29, P30, P34
Other: The new access arm is intended for entry and egress to the park and cemetery only. It is not intended to become the primary access for Bicester Village traffic [P34]. Report P34
Climate: The proposals actively support the Greener Oxfordshire and Healthier Oxfordshire priorities. These include safe and sustainable travel and opportunities for healthy choices [P8] [P9] [P11]. Report P8, P9, P11
Staffing: The appraisal and consultation were undertaken within officers' regular duties. No additional or negative capacity impact is expected [P16]. Report P16
Between 16 October and 14 November 2025: Formal consultation took place, with a newspaper notice and emails to organisations required by law and key stakeholders [P23]. Report P23
2025-12-11: The four crossing proposals were approved [D].
Upon completion: The scheme will undergo an independent stage 3 road safety audit [P33]. Report P33
Plain English for the jargon
Parallel crossing: A zebra crossing for pedestrians with an adjacent cycle route that has priority [P7].
Toucan crossing: A signal controlled crossing for pedestrians and pedal cyclists [P7].
Desire line: The route of travel for pedestrians and cycles that the crossing is designed to follow [P30].
Raised table: A raised feature where the new access road crossing will be sited [P3].
Stage 3 road safety audit: An audit stage that will follow completion, after stages 1 and 2 [P33].
Highway Authority: The council role in which the scheme was promoted under the Highways Act 1980 [P14].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item106/25
Resolved
RESOLVED to: a) Approve the introduction of the following new Parallel Crossings as advertised: i . Kings End, approx.10 metres north of the roundabout junction, ii. New access road, approx.10 metres east of the roundabout junction, to be sited on a raised table feature. b) Approve the introduction of a new Toucan Crossing on Oxford Road, approx.15 metres south of the roundabout junction, as advertised. c) Approve the introduction of a new parallel crossing on Middleton Stoney Road, approx.19 metres west of the roundabout junction, as amended since advertisement.
Word for word from the decision Oxfordshire published for this meeting.Source: mycouncil.oxfordshire.gov.uk
(a) Approve the introduction of the following new Parallel Crossings as advertised:
i. Kings End, approx.10 metres north of the roundabout junction, ii. New access road, approx.10 metres east of the roundabout junction, to be sited on a raised table feature.
(b) Approve the introduction of a new Toucan Crossing on Oxford Road, approx.15 metres south of the roundabout junction, as advertised.
(c) Approve the introduction of a new parallel crossing on Middleton Stoney Road, approx.19 metres west of the roundabout junction, as amended since advertisement.
Executive summary
2. This report presents responses received to a statutory consultation on proposals to construct four new crossings on the approach roads to the Kings End/Middleton Stoney Road/Oxford Road roundabout junction (including the new access road) – as shown in Annex 1.
3. The proposals comprise of Parallel Crossings, which consist of a separate zebra crossing for pedestrian use, with an adjacent parallel priority cycleway, to be located on Kings End, Middleton Stoney Road, and the new access road, as well as a Toucan Crossing, which is a signal-controlled crossing for use by both pedestrians and pedal cyclists, to be located on Oxford Road. Corporate Policies and Priorities
4. Of the three priorities identified within the newly adopted ‘Oxfordshire Strategic Plan 2025-2028’ which are listed below, these proposals actively support priority nos.1 & 3:
(1) Greener Oxfordshire – “We want our communities to enjoy clean air, access to green space, and safe and sustainable ways to move around. This means reducing traffic congestion and investing in public transport, cycling and walking; protecting our natural environment; and helping Oxfordshire respond and adapt to a changing climate.”
(2) Fairer Oxfordshire – “We want all our residents to benefit from the advantages our county has to offer. This means supporting a local economy that benefits everyone; assisting people who face challenges in finding work; making our services as easy to access as possible; and helping communities in need.”
(3) Healthier Oxfordshire – “We want all our residents to be happy, healthy and safe. This means helping children get the best start in life; creating opportunities for young people to reach their full potential; supporting older people to age well and stay independent for as long as possible; and encouraging everyone to make healthy choices.”
Financial implications
5. Funding for consultation on the proposals (and implementation if approved) has been provided by Bicester Village.
Legal implications
6. The consultation that has been undertaken complies with the consultation requirements for the various elements as required by law including under the Highways Act 1980, and any other relevant legislation.
7. The scheme has been promoted by Oxfordshire County Council as the Highway Authority under the Highways Act 1980.
Comments checked by: Jennifer Crouch – Principal Solicitor (Regulatory) [email protected] Staff Implications
8. There are no negative staff implications, with the appraisal of the proposals, as well as the consultation process having been undertaken by Officers from the ‘Infrastructure Delivery’ and ‘TRO & Schemes’ teams as part of their regular day-to-day duties, with no additional/negative impact on capacity expected.
Equality & Inclusion Implications
8. No negative implications in respect of equalities or inclusion have been identified in respect of the proposals.
Sustainability Implications
9. The proposals are being put forward to help improve pedestrian & pedal cyclist safety in the area as a result of planned improvement works/amendments to the junction.
Risk management
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Proposed Bus Stops - Ladygrove, DidcotRESOLVED to: a) Approve the introduction of two new bus stop clearways (with ‘No stopping except local buses’ restric...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.