Resolved
RESOLVED to defer consideration of this item to the meeting on 19 May 2026.
Cabinet deferred this item on Tuesday 21 April 2026. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to defer consideration of this item to the meeting on 19 May 2026.
1. Cabinet is RECOMMENDED to:
a) approve “part 1” of the congestion charge investment plan, as detailed at Annex 1 and outlined in paragraph 23
b) approve “part 2” of the congestion charge investment plan, as detailed at Annex 1 and outlined in paragraph 23
c) confirm that allocations to specific projects or schemes in line with the areas of spend identified in Part 2 of the investment plan (including the reserve) can be made under the delegation authorised by resolution (e) of the 10 September 2025 cabinet decision: • delegate approval for future surplus investment to the Director for Environment and Highways, in consultation with the Executive Director of Resources and Section 151 Officer, Cabinet Member for Transport Management and Cabinet Member for Finance, Property and Transformation.
2. This report sets out the proposed investment plan for surplus congestion charge income and explains why the Director for Environment and Highways has referred the investment plan to cabinet rather than using delegated powers cabinet authorised in September 2025 when approving the scheme.
3. The reason for referral back to cabinet is a higher-than-expected available surplus along with the scale and range of options now available.
4. Officers’ recommendations for the use of surplus income are set out at Annex 1.
5. Cabinet approved the temporary congestion charge on 10 September 2025 in response to congestion impacts associated with the Botley Road closure. At that time, Cabinet resolved to delegate approval of future surplus investment, subject to consultation with senior officers and relevant Cabinet Members.
V2.1 Sept 2025 6. The charge came into operation on 29 October 2025 and is expected to operate until the reopening of Botley Road, currently anticipated by 31 August 2026.
7. The surplus from the congestion charge was initially estimated at £3.2m over a ten‑month period. Updated forecasts based on early operational data now indicate a potential surplus of approximately £4.5m over the same period, although this remains subject to change as further data becomes available. This forecast is derived from income from daily charge payments and penalty charges, minus operating costs.
Corporate Policies and Priorities
8. By law, any surplus generated by a congestion charging scheme may only be spent for the purpose of directly or indirectly facilitating the achievement of the authority’s local transport policies.
9. In Oxfordshire, the relevant policies are set out in the Local Transport and Connectivity Plan (LTCP) and the Central Oxfordshire Travel Plan (COTP). All proposed investments must therefore demonstrably support the policy objectives outlined in these documents.
Recommended Investment Plan
10. The total surplus income is currently forecast to be £4.53m. With £1.34m having been spent or committed through previous decision-making, this leaves a forecast surplus of £3.19m currently unallocated.
11. Officers have considered several different potential investment initiatives and different combinations of those investments.
12. This was carried out taking into account: • transport benefits, including impacts on city centre visitor numbers • the requirement for all expenditure to comply with the Transport Act 2000 requirements • ongoing monitoring of the temporary congestion charge • the 2025 Citizens’ Assembly’s transport recommendations • the consultation on the temporary congestion charge • equality and inclusion impacts • climate impacts • the balance between immediate and longer-term benefits
officers are recommending a package of investment as outlined at Table 3 and at Annex 1.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CC Investment plan Annex 1: recommended investment plan /26Appendix | 3 pages | Download |
PDF |
CC Investment plan Annex 2: Go Ahead statement on free P&R /26Appendix | 4 pages | Download |
PDF |
CC Investment plan Annex 3: alternatives to investment plan part 1 /26Appendix | 2 pages | Download |
PDF |
CC Investment plan Annex 4: EqIA /26Appendix | 28 pages | Download |
PDF |
CC Investment plan Annex 5: climate impact assessment /26Appendix | 6 pages | Download |
PDF |
Oxford Congestion Charge Investment PlanReport | 8 pages | DownloadRead as text |
Follow Cabinet at Oxfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Response to Motion by Councillor Evans on Motor Neurone DiseaseContact: Izzie Rockingham, Commissioning Manager (Improve Enable) [email protected] Report by the ... | Approved | Open |
| 15 Sep 2026 | DfT Local Transport Delivery PlanContact: Hannah Battye, Head of Place Shaping [email protected] Report by the Director of Environment ... | Approved | Open |
| 15 Sep 2026 | Treasury Management Quarter 1 Report 2026/27RESOLVED to note the council’s treasury management activity at the end of the first quarter of 2026/27. | Noted | Open |
| 15 Sep 2026 | Forward Plan and Future BusinessRESOLVED to note the items currently identified for forthcoming meetings. | Noted | Open |
| 28 Jul 2026 | Proposed Changes to Adult Social Care Contributions PolicyRESOLVED to:- Note the contents of this report and confirm its agreement for a) Reducing the initial Disability Relat... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.