What was decided
Authority was delegated to the Director of Environment and Highways, in consultation with the Head of Legal and Governance, to award the £70m NEC4 Engineering and Construction Contract to Balfour Beatty Group Limited under the Scape Civil Engineering and Infrastructure Framework (Lot 2), once Stage 1 scope, target cost, programme and Option X22 budget and pricing are finalised.
Authority was also delegated to issue a Notice to Proceed for the main construction works, once the Stage 2 scope, target cost and programme are finalised.
Why
The decision is needed to progress the Housing Infrastructure Fund (HIF2) A40 Eynsham to Wolvercote scheme, using the Scape Civil Engineering and Infrastructure Framework (Lot 2) to appoint a contractor.
What happens next
Finalise the Stage 1 scope, target cost, programme and Option X22 Budget and Pricing Information, then award the contract to Balfour Beatty.
Finalise the Stage 2 scope, target cost and programme, then issue a Notice to Proceed so main construction works can begin.
The money
- £70m Estimated total value of the NEC4 construction contract for the A40 Eynsham Park and Ride to Wolvercote scheme
Options considered
- Chosen: Award the NEC4 contract to Balfour Beatty Group Limited under the Scape Civil Engineering and Infrastructure Framework (Lot 2), subject to finalising Stage 1 and Stage 2 details. Presented as the recommended route to deliver the HIF2 A40 scheme
Implications
- Financial: Estimated total contract value of £70m for the A40 Eynsham Park and Ride to Wolvercote scheme.
- Legal: Award is subject to consultation with the Head of Legal and Governance Services (Deputy Monitoring Officer) and use of the established Scape framework.
- Risk: The contract is awarded and works proceed only after finalising target cost and programme for each stage, leaving cost and timing risk with the council until then.
- Other: Procurement is run through the Scape Civil Engineering and Infrastructure Framework (Lot 2) rather than a new open tender.
Who and where
- Balfour Beatty Group Limited (proposed contractor under the Scape framework)
- Drivers and communities using the A40 between Eynsham and Wolvercote
- Director of Environment and Highways and Head of Legal and Governance Services at Oxfordshire County Council
Timeline
- 2026-06-01: Cabinet Member for Highway Construction and Repair takes the decision on the A40 contract
Plain English for the jargon
- HIF2: Housing Infrastructure Fund 2, a government funding programme supporting housing-related infrastructure
- NEC4 Engineering and Construction Contract: A standard form of construction contract published by the Institution of Civil Engineers, used here for the main works
- Scape Civil Engineering and Infrastructure Framework (Lot 2): A pre-established public sector procurement framework used to appoint civil engineering contractors
- Option X22: An NEC4 contract option relating to the early warning and budget/pricing information procedures
- Notice to Proceed: Formal instruction to the contractor to start the main construction works under the contract
- Stage 1 and Stage 2: Two phases of the contract: Stage 1 covers mobilisation, target cost and programme finalisation, Stage 2 covers the main construction works